Title: New Nuclear Build - Economic Regulation?
1New Nuclear Build - Economic Regulation?
Gregg Butler Director Integrated Decision
Management Ltd Professor of Science in
Sustainable Development, University of Manchester
2Reactors in the UK Experience to date
- Generation I Magnox 10 stations 9 different
designs (plus another two exported!) - Generation 2a AGR 7 stations 4 designs, 3
design and construction consortia - Generation 2b PWR 1 station, derived from US
design but extensively modified ends as very
much a one of a kind - Comment
- 18 reactors, 14 designs
- only the near-identical Heysham 2 and Torness
stations were built in parallel, and this proved
very beneficial in minimising delays and
improving construction efficiency
3Licensing Regime
- Safety licensing regime therefore developed to
cope with anything - Permissioning regime based on Safety Assessment
Principles (SAPs) - Risk levels governed by Tolerability of Risk
- Safety improvement driven by So Far As is
Reasonably Practicable (SFAIRP) within the
framework of Tolerability of Risk
4 Tolerability of Risk
Risk cannot be justified save In extraordinary
circumstances
10-2
Unacceptable region
10-4
Effect on maximally exposed individual -
Tolerability of Risk
ALARP or Tolerability region
10-6
Necessary to maintain assurance that risk
remains at this level
Broadly acceptable region
10-8
5ToR Gross Disproportionality Where to Stop?
- If Gross Disproportionality is to be bounded then
the Tolerable and Broadly Acceptable regions
need to be stabilised - All the current signs point to erosion
- Nuclear site delicensing now relies on meeting
10-6 as a limit - In the environmental field, guidance on BPM
explicitly removes any thought of valuing Gross
Disproportionality
6ToR Gross Disproportionality Where to Stop?
A Review of the Application of Best Practicable
Means within a Regulatory Framework for Managing
Radioactive Wastes - March 2005 As a matter
of principle, the (Environment) Agencies define
no lower threshold of dose or environmental
contamination below which BPM does not apply
Put simply, BPM requires site operators to
ensure that the measures in place to manage
radioactive wastes are not unreasonably
costly. In all cases, however, the onus is on the
site operator to implement measures to the point
where the costs of any further measures would be
grossly disproportionate to the risks they would
reduce or avert. .a quantitative
definition of grossly disproportionate would be
difficult, if not impossible
7Licensing Regime and PWRs
- The UK licensing regime has only had one try at
licensing an international design - Sizewell B was an operating US design, and was
examined from the ground up - Time pressures were not on the project teams
side they gave in a lot! - Sizewell ended up much more complex and expensive
than its mother station with many developments
during the late stages of design and even during
the build
8Licensing and Regulation Sizewell B Took 14
Years to Plan and Build
From www.niauk.org
Sizewell B experience - 7 years from site
selection to site license -
Construction 6.5 years
9Any risk of a repetition no chance for new
build!
From www.niauk.org
Sizewell B experience - 7 years from site
selection to site license -
Construction 6.5 years