Title: EPA
1EPAs New Rule for Cooling Water Intake
Structures at Existing (Phase II) Facilities
Kristy A.N. BulleitHunton Williams1900 K
Street, N.W.Washington, DC 20006 202-955-1547
kbulleit_at_hunton.com
James N. Christman and Elizabeth E. Aldridge
Hunton WilliamsRiverfront Plaza, East Tower,
951 East Byrd Street Richmond, VA
23219 804-788-8368 jchristman_at_hunton.com 804-788
-8549 ealdridge_at_hunton.com
2Background
- Phase II rule for existing facilities was signed
February 16, 2004 - To be published in the Federal Register in about
mid-March 2004 - Becomes final for judicial review purposes two
weeks after publication in the Federal Register
3Background
- On February 3, 2004, the Second Circuit Court of
Appeals ruled that restoration cannot be used for
new (Phase I) facilities - Nevertheless, EPA decided to allow restoration in
the Phase II rule, but limited the circumstances
under which it can be used.
4Applies to a Facility If
- Primary activity is to generate and transmit
electric power or to generate electric power for
sale to a different entity for transmission - Has a total design intake flow ? 50 MGD
- Uses ? 25 of water withdrawn exclusively for
cooling purposes - Commenced construction on or before January 17,
2002
5Adding New Units
- Existing facility includes any modification of
or addition of a unit at an existing facility
that is not a new facility ( 125.83) - An existing facility that adds a new generating
unit at the same site for repowering and
concurrently increases the design capacity of its
intake structure or adds a new intake structure
where it did not previously have one (when
converting a gas turbine to a combined cycle
unit, for example) is an existing facility
6Existing Facility Includes
- New units added to a facility for purposes of the
same general industrial operation - EPA does not want to discourage upgrades,
modifications, or repowering that would increase
energy efficiency or supply
7The Rule in a NutshellTwo Performance Standards
- Calculate baseline
- Reduce impingement mortality 80-90 from baseline
- Also reduce entrainment 60-90 if
- Capacity utilization ? 15 (not a peaking unit)
and either - Withdrawn water from tidal river, estuary, ocean,
or Great Lakes or - Design intake flow withdraws gt 5 of mean annual
flow of freshwater river or stream
8Capacity Utilization Rate
- Ratio of average annual net generation (in MWh)
and total net capability to generate power (in
MW) multiplied by number of hours during year. - If facility has multiple CWIS and each structure
serves a separate unit or group of units, CWIS
capacity utilization rate may be calculated
separately.
9Capacity Utilization Rate (contd)
- Measured over representative 5 year period,
unless plant commits to remain below 15 - Only applies to steam units
10Five Ways to Comply
- Cooling water flow commensurate with a
closed-cycle recirculating system - -- Maximum through-screen design intake
velocity of 0.5 ft/s meets impingement mortality
standard only - Demonstrate that existing intake reduces
impingement mortality 80-95 from a calculation
baseline and, for some plants, reduces
entrainment 60-90
11Five Ways to Comply (contd)
- Reduce impingement mortality 80-95 and, for some
plants, reduce entrainment by 60-90 using - - Design and construction technologies
- - Operational measures
- - Restoration, in some cases
- In freshwater rivers and streams, use cylindrical
wedge-wire screens meeting conditions in
125.99(a)(1) - - Or a technology-approved by the state that
can consistently meet the performance standards
in the state
12Conditions for Wedge-wire Screens
- Freshwater river or stream
- Sufficient ambient counter currents to promote
cleaning of screen face - Maximum through-screen design intake velocity?
0.5 ft/s - Slot size appropriate for eggs, larvae, and
juveniles at site - Entire main condenser cooling water flow directed
through the screens (except small flows lt 2 MGD
for auxiliary plant cooling)
13Five Ways to Comply (contd)
- Site-specific requirements under the cost-cost or
cost-benefit test
14Applying the Performance Standards
- Calculation baseline Estimate of impingement
mortality and entrainment that would occur
assuming - Cooling water system designed as once-through
- Opening located at the shoreline near the water
surface - 3/8-inch mesh traveling screen parallel to the
shoreline - No controls implemented in whole or in part for
the purpose of reducing impingement mortality and
entrainment.
15Applying the Performance Standards
- EPA intends to allow credit for
- Angled screen face to guide organisms away from
intake structure - Opening place in water column instead of at
surface - Any structural or operational controls used in
whole or part to reduce impingement mortality or
entrainment - As built baseline assessment also allowed.
16Special Provisions forLakes and Reservoirs
- If you withdraw cooling water from a lake
- (other than the Great Lakes) or reservoir,
- and you propose to increase the design intake
flow, - then, increased flow must not disrupt the
natural thermal stratification or turnover
pattern - unless the disruption does not adversely affect
management of fisheries
17Interpreting thePerformance Standards
- Permit writer has significant discretion as to
how the performance standards are applied in the
permit - Permit writer may determine that all species must
be considered or only representative species - Permit writer averaging period apparently can be
up to a full five-year permit term (see preamble
p. 163)
18Exceptions for Excessive Costs
- Rule offers cost-cost test and cost-benefit
test - If your costs are significantly greater, you
can get site-specific requirements
19Cost-Cost Test
- Six-step process prescribed
- Determine what technology EPA used for your
facility - Use EPAs costing equation to calculate
annualized capital and net operation and
maintenance costs for a facility with your design
intake flow using the technology chosen by EPA
20Cost-Cost Test (contd)
- Calculate your own costs and show that they are
significantly greater than the costs estimated
by EPAs method - Significantly is not defined
21Cost-Benefit Test
- Cost of compliance must be significantly greater
than the benefits of complying - While entrainment survival is not part of
performance standard, it may be considered
through application of cost-benefit test.
22Costs and Benefits
- EPA has retreated from some of its worst
cost-benefit methods - 50 rule for non-use benefits
- Habitat replacement cost analysis of benefits
- Societal revealed preference analysis for
threatened and endangered species
23Benefits Valuation Study Requirments
- Describe methodology
- Develop valuation estimates
- Document assumptions
- Analyze sources of uncertainty
- Arrange for peer review (consulting resource
agencies about peer reviewers) - Describe non-monetized benefits
24What Site-Specific Requirements?
- The site-specific alternative technology must
achieve an efficacy that is - As close as practicable to the applicable
performance standards - Without resulting in costs that are significantly
greater than the EPA costs or the calculated
benefits at your facility
25Operational Measures
- You may meet the performance standards by
operational measures - Reductions in cooling water intake flow
- Variable speed pumps
- Seasonal flow reductions or shutdowns
- More frequent rotation of traveling screens
26Restoration
- Restoration can be used only if permittee first
shows that design and construction
technologies/operational measures are less
feasible, less cost-effective, or less
environmentally desirable. - Restoration results must be substantially similar
to performance standards or site-specific
alternative. - Restoration Plan may focus on species of concern
to resources agencies.
27Application Requirements
- All plants must submit source waterbody physical
data, CWIS data, and cooling system data - Plants that neither have nor propose to install
closed-cycle cooling will have to perform and
submit a Comprehensive Demonstration Study (CDS)
(unless plant has design velocity lt 0.5 ft./s and
is subject only to impingement requirements, in
which case no CDS required).
28Application Requirements (contd)
- CDS components depend on specific compliance
option chosen. - Unless facility plans to show it already meets
performance standards, all CDS start with
submission of Proposal for Information Collection
to permit writer
29Application Requirements (cont)
- Other CDS components may include
- Source waterbody flow information
- Impingement Mortality and/or Entrainment
Characterization Study - Technology and Compliance Assessment Information,
which may include - Design and Construction Technology Plan
- Technology Installation and Operation Plan
30TIOP
- The Technology Installation and Operation Plan
describes how you will install, operate, monitor,
and maintain the intake technology and adaptive
management steps to take if the technology does
not perform as expected. - TIOP is crucial, because permittee may request
that TIOP compliance compliance with rule. - If permittee fails to comply with performance
standard but meets TIOP, it may request
site-specific alternative requirements.
31Application Requirements (contd)
- Restoration Plan (if appropriate)
- Information to Support Site-specific
Determination of BTA, including - Comprehensive Cost Evaluation Study
- Valuation of Monetized Benefits of Reducing
(IME) (cost-benefit test only) - Site-specific Technology Plan
- Verification Monitoring Plan (including proposal
for identifying moribund fish)
32When Must You Comply?
- Submit the information with the next permit
application - If your permit expires lt 4 years after
publication, you may ask to submit the
information up to 3 ½ years after publication of
the rule in the Federal Register
33Permit Renewals After the First
- In permit terms after the first, you may ask that
compliance and restoration be based on compliance
with the Technology Installation and Operation
Plan and Restoration Plan - One year before permit expiration, if you are in
compliance with your TIOP and/or performance
standards, you may request reduced data
requirements for permit renewal. - Permit writer may change requirements at each
permit renewal
34Cooling Ponds
- EPA does not intend to change the regulatory
status of cooling ponds - Cooling ponds are waters of the U.S. if they
meet the definition
35State-Approved Alternatives and Reserve State
Authority
- State may have functionally equivalent program
- Must produce results comparable to EPAs
performance standards - Permit writer may establish more stringent
requirements if EPAs rule would not meet the
requirements of state law or other federal law
36Trading
- State may adopt trading programs
- Must be within the same watershed
- May trade fish for fish but not pollutants for
fish
37Nuclear Safety
- If the EPA rule would conflict with an NRC safety
requirement, you can have site-specific
requirements