DOUBLE BARREL GREEN SYSTEM - PowerPoint PPT Presentation

1 / 50
About This Presentation
Title:

DOUBLE BARREL GREEN SYSTEM

Description:

DOUBLE BARREL GREEN SYSTEM AN EQUIPMENT MEANS TO PRODUCE WARM MIX By Malcolm Swanson, P.E. Vice President Engineering Astec, Inc. – PowerPoint PPT presentation

Number of Views:92
Avg rating:3.0/5.0
Slides: 51
Provided by: RobinJ153
Category:

less

Transcript and Presenter's Notes

Title: DOUBLE BARREL GREEN SYSTEM


1
DOUBLE BARREL GREEN SYSTEM AN EQUIPMENT MEANS
TO PRODUCE WARM MIX By Malcolm Swanson,
P.E. Vice President Engineering Astec, Inc.
2
SUSTAINABILITY
  • Conserving our resources
  • Reducing energy consumption
  • Reducing Greenhouse Emissions
  • Being more environmentally friendly
  • And building a better, long-lasting pavement

3
GLOBAL WARMING
4
(No Transcript)
5
WARM MIX TECHNOLOGIES
  • ADDITIVES
  • Aspha-Min
  • WAM
  • Evotherm
  • Sasobit
  • EQUIPMENT
  • Double Barrel Green

6
The ASTEC Double Barrel Green System Is An
Equipment Package That Enables The Making Of
Warm Mix By Adding Only Water to the Liquid
Asphalt.
7
Outline
  • Background and Benefits of Warm Mix
  • Equipment Explanation
  • Case Studies
  • Experience to Date

8
Background
  • Mix temperatures 50-100F (28 44 C) cooler than
    conventional mix methods
  • Achieved by lowering the viscosity of the AC
    binder
  • Methods additives, additives with water, foaming
    with water only, etc.
  • Foaming first introduced in the 1950s
  • High fuel cost and pressure to reduce emissions
    make Warm Mix more attractive.

9
Benefits of Warm Mix
  • Improves mix workability
  • Reduces emissions
  • Eliminates blue smoke and odor
  • Less total emissions
  • Improves Comfort safety of workers
  • Improves Pavements
  • Extends resources via more recycle
  • Less fuel
  • Increases Plant Capacity

10
Improves Workability
11
(No Transcript)
12
(No Transcript)
13
Reduces Emissions
14
CONVENTIONAL HOT MIX
WARM MIX
15
No Smoke No SmellWhy?
  • Light oils are either put in asphalt or
    left in asphalt during refining
  • These light oils boil above 285oF (140 C)
  • By mixing at below 285oF (140 C), the boiling
    point is never reached eliminating
    smoke (vapor) and corresponding smell

16
Reduces total emissionsWhy?
  • Producing mix at lower temperatures requires
    less fuel burning.
  • The increased ability to use RAP decreases
    emissions associated with production of virgin
    materials.

17
Improved Comfort and Safety of Workers
18
No Smoke At Paver No Extreme Temperatures
19
Improves Pavements
20
Why will we have a Longer Life Pavement?
  • Less oxidation of mix
  • More uniformity of compaction
  • With fractionating RAPbetter control of
    gradation

21
Extends Resources by Recycling More
22
High Percentage Recycle Mix with Standard Grade
of Asphalt
  • Two deterrents to running recycle above 20
    have been
  • High Stack Temperature
  • Need for a softer virgin liquid to
    ensure compaction because of the stiffer
    liquid in the RAP

23
Make High Percentage Recycle Mix with Standard
Grade of Asphalt
  • To achieve compaction (density)run 275oF
    and foam virgin liquid
  • By using a standard liquid 64-22, you
    produce a much softer product than with
    virgin mix because
  • Lower temperature results in less oxidation
  • Light oil remains in liquid
  • Steam produced from drying the RAP creates an
    inert atmosphere

24
Uses Less fuel
25
Uses Less Fuel
Making Mix at 50 100 F Lower Temperatures than
Traditional HMA Requires 11 to 25 Less Fuel
(Depends on Mix Type and Other Conditions.)
26
Increases Plant Production Capacity
27
Increases Plant Production Capacity
Lower Exhaust Gas Temperatures and Less Fuel
Burned Take Load Off of the Exhaust System.
28
ASTEC Double Barrel Green System Equipment
Explanation
29
DOUBLE BARREL GREEN
30
The Double Barrel Green System Injects Water
Into Liquid Asphalt.
  • Injected At The Rate Of 2 Of The Liquid Asphalt
    By Weight
  • Small Faction Of The Injected Water Becomes
    Trapped As Steam Bubbles In The Liquid
    Asphalt
  • The Effect On The Mix Is To Extend The Workable
    Temperature Downward to about 212 F (100 C).

31
WATER IS INJECTED INTO THE AC INSIDE THE FOAM
NOZZLE.
32
Steam Bubbles Produce Foamed AC.
33
?
mm
mm
FOAM EXPANDS THE LIQUID ASPHALT AND INCREASES
FILM THICKNESS
34
THE SYSTEM CONSISTS OF WATER TANK AND CONTROL
SKID..
35
FOAM UNIT MOUNTED ON DOUBLE BARREL .
36
CONTROL SYSTEM
37
Junction Box
Water Solenoid Valve
Water Manifold
Water
Hot Oil Out
Hot Oil In
AC
AC Valve (one of nine)
Nozzle Manifold
38
LIQUID AC
HOT OIL
WATER
FOAMED AC
39
How much water ?
40
How Much Water? 2 of liquid AC by weight 2
LBS. of Water for 1 Ton of Mix
41
Case StudiesDone by
  • National Center for Asphalt Technology
  • Created in 1986
  • NAPA (National Asphalt Pavement Association)
  • Auburn University (Alabama)
  • Created to improve pavements
  • Test Track
  • 17,500 sq. ft.(1626 sq.m) laboratory

42
Andrea Kvasnak, PhD
  • BS from University of Florida 1999
  • MS from University of Vermont 2002
  • PhD from Iowa State University 2006

Contact ank0004_at_auburn.edu
www.ncat.us
43
Case Study 1
  • Completed April 18, 2007
  • Three foam mixes (2 H2O to AC)
  • 1. Base, 30 RAP
  • 2. Surface Coarse, virgin aggregate
  • 3. Surface Coarse, 30 RAP
  • Two locations at Astec HQ
  • Samples taken and tested by National Center for
    Asphalt Technology (NCAT)

44
Case Study 2
  • Completed June 21, 2007
  • 50 RAP and PG 64-22 binder
  • 3400 ton job
  • Location North Terrace Rd, Chattanooga,
    Tennessee
  • Samples taken and tested by National Center for
    Asphalt Technology (NCAT)

45
Summary Conclusions of Cases 1 and 2
  • 1.Coating and mixing of the warm mixes were
    equivalent to that expected for conventional hot
    mixes.
  • 2.Workability of the warm mix at 250 F (121 C) to
    270 F (132 C) was similar to that of hot mix at
    temperatures above 300 F (150 C).
  • contd

46
Summary (contd)
3. There was no smoke. 4. There was evidence that
the warm mix was susceptible to stripping. This
has been a characteristic of warm mix in general.
One reason could be that the binder is not aged
during mixing. Potential solutions include using
a harder AC or an anti-strip agent.
47
High profile demonstrations
  • Southeastern Materials / City of Chattanooga,
    3400 tons 50 RAP
  • Columbia Bit. (Vancouver), 100tons Virgin.
  • S.T. Wooten (Sims), 400tons, 20 and 40
  • S.T. Wooten (Sims), 400tons, 40
  • LoJac (Nashville), 1200tons, Virgin
  • Shelly Materials (Columbus), 1200tons, 25
  • Boggs Materials (Rock Hill), 1200tons, 50
  • Columbia Bit. (Vancouver), 1500tons, 50
  • LoJac (Nashville), 500tons, 40

48
7-26-07 to 7-28-07 Storage Test
  • Approximately 50 tons of mix made at 300 tph
    with 20 RAP at 138 C.
  • Stored for 24 hours and checked all normal
  • Few tons of mix sold to a private customer.
  • No problems. Mix behaved normally.
  • Stored for another 24 hours (48 total) and
    emptied all normal.

49
Questions ?
50
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com