CASCADING FAILURE - PowerPoint PPT Presentation

About This Presentation
Title:

CASCADING FAILURE

Description:

Title: Initial evidence for self-organized criticality in blackouts Author: Ian Dobson Last modified by: Ian Dobson Created Date: 12/31/1999 8:36:49 PM – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 50
Provided by: IanD160
Category:

less

Transcript and Presenter's Notes

Title: CASCADING FAILURE


1
CASCADING FAILURE
Ian Dobson ECE dept., University of Wisconsin
USA Ben Carreras Oak Ridge National Lab
USA David Newman Physics dept., University of
Alaska USA
Presentation at University of Liege March 2003
Funding in part from USA DOE CERTS and NSF is
gratefully acknowledged
2
power tail
probability
(log scale)
-1
S
-S
e
blackout size S (log scale)
power tails have huge impact on large blackout
risk.
risk probability x cost
3
NERC blackout data15 years, 427 blackouts
1984-1998 (also sandpile data)
power tail in NERC data consistent with power
system operated near criticality
4
Cascading failure large blackouts
  • dependent rare events many combinations hard
    to analyze or simulate
  • mechanisms hidden failures, overloads,
    oscillations, transients, control or operator
    error, ... but all depend on loading

5
Loading and cascading
  • LOW LOAD- weak dependence- events nearly
    independent - exponential tails in blackout size
    pdf
  • CRITICAL LOAD- power tails in blackout size pdf
  • HIGHER LOAD- strong dependence- total blackout
    likely

6
Extremes of loading
log-log plot
VERY LOW LOADING independent failures pdf has
exponential tail
PDF
blackout size
TRANSITION ??
VERY HIGH LOADING total blackout with
probability one
PDF
blackout size
7
Types of dependency in failure of systems with
many components
  • independent
  • common mode
  • common cause
  • cascading failure

8
CASCADEA probabilistic loading-dependent model
of cascading failure
9
CASCADE model
  • n identical components with random initial load
    uniform in Lmin, Lmax
  • initial disturbance D adds load to each component
  • component fails when its load exceeds threshold
    Lfail and then adds load P to every other
    component. Load transfer amount P measures
    component coupling, dependency
  • iterate until no further failures

10
5 component example
11
5 component example
12
Normalize so that initial load range is 0,1
and failure threshold is 1
  • normalized initial disturbance d d
  • normalized load transfer p
  • p

D - (Lfail - Lmax) Lmax -Lmin
P Lmax -Lmin
13
Formulas for probability of r components fail
for 0ltdlt1
r-1
n-r
)
(
d (rpd) (1-rp-d) npdlt1 quasibinomial
distribution Consul 74
n r
  • for npd gt1, extended quasibinomial
  • quasibinomial for smaller r
  • zero for intermediate r
  • remaining probability for r n

14
average number of failures lt r gt n100 components
d
p
15
example of applicationmodeling load increase
-
  • Lmax Lfail 1
  • increase average load L by increasing Lmin

1
L
-
-
0
16
example of application
  • n 100 components
  • P D 0.005
  • p d

0.005 1 - Lmin
17
probability distribution asaverage load L
increases
18
ltrgt
average failures ltrgt versus load L pd and n100
19
example 2 of applicationback off Lmax ( n-1
criterion)
-
Lfail 1
k
-
Lmax
-
Lmin 0
20
Increase average load leads to change in d and p
constant
21
GPD formulas for probability of r components
fail
r-1
-rl-q
  • (rlq) e / r! nlqltnrltn
  • remaining probability for r n.
  • For rltn agrees with
  • generalized Poisson distribution GPD

  • for nlqgtn, extended GPD
  • GPD for smaller r
  • zero for intermediate r
  • remaining probability for r n

22
probability distribution as average load L
increasesGPD model
23
SUMMARY OF CASCADE
  • features of loading-dependent cascading failure
    are captured in probabilistic model with analytic
    solution
  • extended quasibinomial distribution with n,d,p
    approximated by GPD with qnd, lnp.
  • distributions show exponential or power tails or
    high probability of total failure
  • power tail and total failure regimes show greatly
    increased risk of catastrophic failure
  • power tails when lnp1.

24
OPAA power systems blackoutmodel including
cascading failure and self-organizing dynamics
25
Why would power systems operate near criticality??
  • Near criticality, expected blackout size sharply
    increases increased risk of cascading failure.

26
Forces shaping power transmission
  • Load increase (2 per year) and increase in bulk
    power transfers, economics
  • Engineering
  • new controls and equipment
  • upgrade weakest parts

these engineering forces are part of the
dynamics!
27
Ingredients of SOC in idealized sandpile
  • system state local max gradients
  • event sand topples (cascade of events is an
    avalanche)
  • addition of sand builds up sandpile
  • gravity pulls down sandpile
  • Hence dynamic equilibrium with avalanches of all
    sizes and long time correlations

28
Analogy between power system and sand pile
29
OPA model Summary
  • transmission system modeled with DC load flow and
    LP dispatch
  • random initial disturbances and probabilistic
    cascading line outages and overloads
  • underlying load growth load variations
  • engineering responses to blackouts upgrade lines
    involved in blackouts upgrade generation

30
DC load flow model(linear, no losses, real power
only)
Power injections at buses P
max
generators have max power P
Line flows F
max
line flow limits F
31
Slow and fast timescales
  • SLOW load growth and responses to blackouts.
    (days to years)slow dynamics indexed by days
  • FAST cascading events.(minutes to hours)fast
    dynamics happen at daily peak load timing
    neglected

32
Response to blackout by engineers
For lines involved in the blackout,
max
increase line limit F by a fixed
percentage.
Also, when total generation margin drops below
threshold,increase generator power limit P at
selected generators coordinated with line limits.
max
33
Fast cascade dynamics
  • Start with daily flows and injections
  • Outage lines with given probability (initial
    disturbance)
  • Use LP to redispatch
  • Outage lines overloaded in step 3 with given
    probability
  • If outage goto 3, else stop

Objective produce list of lines involved in
cascade consistent with system constraints
34
Conventional LP redispatch to satisfy limits
Minimize change in generation and loads (load
change weighted x 100) subject to
overall power balance line flow limits load
shedding positive and less than total
load generation positive and less than generator
limit
35
Model
Is the total generation margin below critical?
1 day loop
Yes
Secular increase on demand Random fluctuation of
loads Upgrade of lines after blackout Possible
random outage
No
A new generator build after n days
LP calculation
If power shed, it is a blackout
Are any overload lines?
1 minute loop
Yes, test for outage
no
Yes
No outage
Line outage
36
Possible Approaches to Modeling Blackout Dynamics
Complexity (nonlinear dynamics, interdependences)
Model detail (increase details in the
models, structure of networks,)
OPA model
By incorporating the complex behavior, the OPA
approach aims to extract universal features
(power tails,).
37
OPA model results include
  • self-organization to a dynamic equilibrium
  • complicated critical point behaviors

38
Time evolution
  • The system evolves to steady state.
  • A measure of the state of the system is the
    average fractional line loading.

200 days
39
Steady state
40
OPA/NERC results
41
Application of the OPA model
  • The probability distribution function of blackout
    size for different networks has a similar
    functional form - universality?

42
Effect of blackout mitigation methods on pdf of
blackout size
obvious methods can have counterintuitive
effects
43
Mitigation
  • Require a certain minimum number of transmission
    lines to overload before any line outages can
    occur.

44
A minimum number of line overloads before any
line outages
  • With no mitigation, there are blackouts with line
    outages ranging from zero up to 20.
  • When we suppress outages unless there are n gt
    nmax overloaded lines, there is an increase in
    the number of large blackouts.
  • The overall result is only a reduction of 15 of
    the total number of blackouts.
  • this reduction may not yield overall benefit to
    consumers.

45
Forest fire mitigation
46
Dynamics essential in evaluating blackout
mitigation methods
  • Suppose power system organizes itself to near
    criticality
  • We try a mitigation method requiring 30 lines to
    overload before outages occur.
  • Method effective in short time scale. In long
    time scale very large blackouts occur.

47
KEY POINTS
  • NERC data suggests power tails and power system
    operated near criticality
  • power tails imply significant risk of large
    blackouts and nonstandard risk analysis
  • cascading loading-dependent failure
  • engineering improvements and economic forces can
    drive to criticality
  • in mitigating blackout risk, sensible approaches
    can have unintended consequences

48
BIG PICTURE
  • Substantial risk of large blackouts caused by
    cascading events need to address a huge number
    of rare interactions
  • Where is the edge for high risk of cascading
    failure? How do we detect this in designing
    complex engineering systems?
  • Risk analysis and blackout mitigation based on
    entire pdf, including high risk large blackouts.
  • Developing understanding and methods is better
    than the direct experimental approach of waiting
    for large blackouts to happen!

49
Papers on this topic are available from
http//eceserv0.ece.wisc.edu/dobson/home.html
Write a Comment
User Comments (0)
About PowerShow.com