Title: Introduction to the WTO
1Federal State Regulatory Issues
Elizabeth W. WhittleNixon Peabody LLP401 9th
Street, N.W.Washington, D.C. 20004(202)
585-8338ewhittle_at_nixonpeabody.com
July 25, 2007
2Federal and State Regulatory Issues
- As a wholesale supplier of power, a wind
developer will be subject to regulation under the
Federal Power Act (FPA). The Federal Energy
Regulatory Commission (FERC) administers the FPA.
FERC has jurisdiction over both the transmission
and the sale of this power. - Siting and related matters are subject to the
jurisdiction of the states.
3Transmission Regulatory Scheme
- Transmission service is governed by utility
tariffs. In many regions, transmission service
is provided by an Independent System
operator/regional transmission organization
(RTO/ISO). - RTO/ISOs do not own the transmission assets, but
have operational control over them. - Open-access, non-discriminatory transmission
service is provided pursuant to a Tariff on file
and approved by FERC.
4Transmission Regulatory Scheme
- Tariffs govern
- Interconnection
- Transmission
- Ancillary service
- Rates
- Dispute resolution
5Interconnection
- The interconnection process has been
standardized. Each Transmission Owner or RTO/ISO
has tariff provisions governing the process from
the filing of an interconnection request to the
execution of the Interconnection Agreement. - While the process is standardized, there are
limited regional differences that are permitted
by FERC. Milstones must be met to remain in the
interconnection queue. - The process includes a number of steps, many of
which must be followed by deposits. Developer
must pay for the costs of all studies. - Interconnection Request - 10,000
- System Reliability Study - 50,000
- Facility Study - 100,000
- Interconnection Agreement - 250,000 if cant
show evidence of site control
6Sale of Power at Market-Based Rates
- FERC authorization is required to sell power at
market-based rates even if power is sold only
into the RTO/ISO market. - In order to obtain authority to engage in sales
for resale at market-based rates the Developer
must show that - It lacks market power over generation
- It lacks market power over transmission
- Cannot erect other barriers to entry and
- Neither it nor its affiliates engage in
reciprocal deals or otherwise abuse an affiliate
relationship.
7Sale of Power at Market-Based Rates (Contd)
- On June 21, 2007 FERC issued Order No. 697 (119
FERC 61,295), which revises some of FERCs
market-based rates rules. - The Final Rule is 643 pages long!
- FERC examines vertical and horizontal market
power.
8Sale of Power at Market-Based Rates (Contd)
- Horizontal Market Power If an entity passes the
market screens established by the FERC, the
entity is presumed to lack market power. - If an entity fails the market screens, the entity
is presumed to possess market power and must
rebut the presumption by performing the delivered
price test. - The geographic market is usually either the
sellers balancing authority area or the
RTO/ISO footprint.
9Sale of Power at Market-Based Rates (Contd)
- Vertical Market Power FERC assumes that no
market power exists if there is an open access
transmission tariff on file. - FERC can revoke market-based rates and impose
cost-based rates on the entity and, in some
cases, the entitys affiliates.
10Ongoing Obligations Market-Based Rates
- Once a seller obtains market based rate
authority, there are reporting obligations. - Each quarter, the seller must report to FERC
electronically details of its activities,
including Mwh sold, aggregate prices, etc. Even
if there is no activity, the report must be
filed.
11Market Power Updates
- Category 1 Sellers (those marketers which own or
control 500MW or less and not affiliated with a
public utility with a franchised service
territory) do not have to file market power
updates periodically. - Category 2 Sellers (those who are not Category 1)
must file updates to show that they continue to
qualify. FERC establishes a filing schedule for
the periodic updates. - All sellers must file changes in circumstances
with the FERC.
12Qualifying Facility/Exempt Wholesale Generator
- Wind projects are qualifying small power
production facilities. - The Public Utility Regulatory Policies Act of
1978 (PURPA) required among other things the
utility, if requested, to purchase all of the
output (net) of QFs at the utilitys avoided
cost. - Also, under PURPA, the FERC was given the
authority to exempt QFs from provisions of the
FPA, including rate regulation under Section 205. - On August 8, 2005, Congress enacted the Energy
Policy Act of 2005 (EPAct) which among other
things gave FERC the authority to allow the
utility to escape from the mandatory purchase
obligation if QF has non-discriminatory access to
three markets defined in the legislation.
13Qualifying Facility/Exempt Wholesale Generator
(Contd)
- FERC implemented EPAct and issued Order No 688,
(71 FR64342 (2006), Order on rehg, 119 FERC
61,305 (2007), which established guidelines for
utilities to escape from the mandatory purchase
obligation. FERC created three rebuttable
presumptions. - For projects with a capacity over 20MW, in Day
2 RTO/ISO markets, there is a rebuttable
presumption that those markets are workably
competitive. The 4 Day 2 markets are Midwest
ISO, New York ISO, PJM and ISO-New England.
14Qualifying Facility/Exempt Wholesale Generator
(Contd)
- For projects with a capacity over 20MW, QFs
located in markets where service is provided
under an open access transmission tariff are
presumed to have non-discriminatory access to
markets in that transmission providers
territory. - QFs with a net capacity 20MW or less are presumed
to not have non-discriminatory access to any
markets.
15Qualifying Facility/Exempt Wholesale Generator
(Contd)
- As a result of these presumptions, many QFs with
a net capacity of greater than 20MW will no
longer have local utility as an involuntary
purchaser of power. That doesnt mean that the
utility wont voluntarily purchase the power at
an agreed upon or auction-based price. - If a project does not avail itself of the
benefits of QF status, developers obtain Exempt
Wholesale Generator (EWG) Status. EWGs are
exempt from certain regulations under the Public
Utility Holding Company Act of 2005.
16Qualifying Facility/Exempt Wholesale Generator
(Contd)
- In EPAct, the Congress repealed the Public
Utility Holding Company Act of 1935, eliminating
the onerous SEC-related reporting requirements
that fell on public utility holding companies. - While the exemption from regulations as an EWG
may not seem as valuable, it is important to
maintain EWG status in order to claim certain
exemptions from filing, e.g., to dispose of a
facility under FPA Section 203. (See FERC Order
No. 669). - Once EWG status is obtained, material changes in
circumstances -- changes in upstream ownership,
etc. must be reported to FERC.
17State-Related Issues
- Many wind development requirements are under
State jurisdiction. Unlike natural gas pipelines
where FERC has siting jurisdiction, siting
matters are left to the State. - Each State has it own siting schemes. Most
require an approval/certificate from the Public
Utility Commission (PUC) that the project is in
the public convenience and necessity. - Often this review entails an environmental
assessment or related environmental document and
the involvement of state environmental agencies. - Many environmental studies are often required - -
noise, bats, birds, impacts on landowners, etc. - Counties and towns also have authority under
local zoning laws.
18State-Related Issues (Contd)
- States may be the administrator of renewable
energy credit/RPS standards. - Many states also regulate the utility as a public
utility, although each may have lightened
regulation or a way to obtain exemptions from
state commission jurisdiction. - In New York, for example, developers file an
application for lightened regulation.