Project planning tool - PowerPoint PPT Presentation

About This Presentation
Title:

Project planning tool

Description:

Project planning tool Objectives Understand the reasons why projects sometimes fail Describe the different scheduling tools, including Gantt charts and PERT/CPM ... – PowerPoint PPT presentation

Number of Views:135
Avg rating:3.0/5.0
Slides: 25
Provided by: PeterK187
Learn more at: https://www.oocities.org
Category:

less

Transcript and Presenter's Notes

Title: Project planning tool


1
Project planning tool
2
Objectives
  • Understand the reasons why projects sometimes
    fail
  • Describe the different scheduling tools,
    including Gantt charts and PERT/CPM charts
  • Calculate completion times, start dates, and end
    dates for a project

3
Keys to Project Success
  • Successful systems must satisfy business
    requirements, meet users needs, stay within
    budget, and be completed on time
  • The essential objective is to provide a solution
    to a business problem

4
Keys to Project Success
  • Some reasons for failure
  • Unclear requirements, targets, or scope
  • Shortcuts or sloppy work
  • Poor design choices
  • Insufficient testing or test procedures
  • Lack of software change control
  • Changes in culture, funding, or objectives
  • Unrealistic cost estimates
  • Poor monitoring and control of progress
  • Inadequate reaction to early signs of problems
  • Failure to recognize activity dependencies
  • Personality conflicts and employee turnover

5
Project Planning
  • A project plan is an overall framework for
    managing costs and schedules
  • The planning process involves
  • Activities (tasks)
  • Events (milestones)

6
Project Planning
  • An activity, or task, is a basic unit of work
    that is planned, monitored, and tracked
  • An event, or milestone, is a reference point that
    is used to manage the project
  • Every activity has two events one marks the
    start of the task, the other marks the end
  • Events must be easily recognizable

7
Project Scheduling
  • The project manager must know
  • The duration of each task
  • The order in which the tasks will be performed
  • The start and end times for each activity
  • Who will be assigned to each task
  • Assignments should not overload or under-utilize
    team members
  • A level workload is desirable

8
Scheduling Tools
  • A project manager can use several graphical
    planning tools
  • Gantt charts
  • PERT/CPM charts

9
Scheduling Tools
  • Gantt charts
  • A Gantt chart is a horizontal bar chart that
    illustrates a schedule
  • Time is shown on the horizontal axis and
    activities are arranged vertically
  • The position of a bar shows the start and end of
    a task, and the length of the bar shows the
    tasks duration

10
Scheduling Tools
  • Gantt charts
  • Tasks can be combined into activity groups to
    simplify the chart
  • Various methods exist for tracking progress
  • Shade the completed portion of a bar
  • Use a triangle or arrowhead as an indicator
  • Use a second bar to show the completed work

11
Scheduling Tools
  • PERT/CPM
  • The Program Evaluation Review Technique (PERT)
    and the Critical Path Method (CPM) were developed
    separately but now are referred to as PERT/CPM
  • A PERT/CPM chart displays a project as a network
    diagram, with activities shown as vectors, and
    events represented by nodes

12
Scheduling Tools
  • PERT/CPM charting conventions
  • The vectors representing tasks connect the nodes,
    which indicate milestones
  • The activitys estimated duration is shown below
    the vector

13
Scheduling Tools
  • PERT/CPM charting conventions
  • The vectors representing tasks connect the nodes,
    which indicate milestones
  • The activitys estimated duration is shown below
    the vector
  • Tasks that must be completed in a specific
    sequence are called dependent, or serial, tasks

14
Scheduling Tools
  • PERT/CPM charting conventions
  • The vectors representing tasks connect the nodes,
    which indicate milestones
  • The activitys estimated duration is shown below
    the vector
  • Tasks that must be completed in a specific
    sequence are called dependent, or serial, tasks
  • Dummy activities can be used to show task
    dependencies

15
Scheduling Tools
  • PERT/CPM charting conventions
  • A project can be represented with a Gantt chart
    and a PERT/CPM chart
  • Significant differences exist between the two
    methods, and each method has strengths and
    weaknesses

16
Scheduling Tools
  • Activity duration
  • A weighted formula can be used to estimate
    activity duration
  • The formula calculates a weighted result based on
    three separate estimates (optimistic (O),
    pessimistic (P), and most likely (M))

17
Scheduling Tools
  • Earliest completion times
  • The earliest completion time for an activity is
    called the ECT
  • The ECT is the minimum amount of time needed to
    complete all the activities that precede the event

18
Scheduling Tools
  • Earliest completion times
  • Working from left to right on the chart, the ECT
    is calculated by taking the ECT of the preceding
    event and adding the duration of the immediately
    preceding task
  • If the event has more than one preceding task,
    use the largest ECT of the preceding tasks,
    including any dummy tasks
  • The ECT is shown as a number in the upper-right
    section of the event node symbol

19
Scheduling Tools
  • Latest completion times
  • The latest completion time for an activity is
    called the LCT
  • The LCT is the latest time at which the event can
    occur without delaying the overall project

20
Scheduling Tools
  • Latest completion times
  • To determine an LCT, you reverse the procedure
    for an ECT
  • Work from right to left, and subtract the LCT of
    the following task
  • If the event has more than one following task,
    use the smallest LCT of the following tasks,
    including any dummy tasks
  • The LCT is shown as a number in the lower-right
    section of the event node symbol

21
Scheduling Tools
  • Slack times
  • The slack time for an event is the amount of time
    by which an event can be late without delaying
    the project
  • The slack time is the difference between the LCT
    and the ECT, if any

22
Scheduling Tools
  • Critical path
  • A critical path is a series of events and
    activities with no slack time
  • At least one complete path will exist where every
    node has equal ECTs and LCTs
  • If any task on the critical path is delayed
    beyond its LCT, the entire project falls behind
    by that amount of time
  • Project managers focus on the critical path in
    order to keep the project on track

23
Scheduling Tools
  • Comparing Gantt charts and PERT/CPM
  • PERT/CPM charts show all task dependencies, and
    are better for scheduling, monitoring, and
    controlling projects
  • Gantt charts graphically display the timing and
    duration of activities, and can display task
    completion status effectively
  • PERT/CPM charts are more complicated than Gantt
    charts, especially for larger projects

24
End of Lecture 6
Write a Comment
User Comments (0)
About PowerShow.com