Title: Website:
1Power SystemPlanning and Investment
- Richard Sedano and Richard Cowart
- NEDRI
- March 26, 2003
2Demand Side Solutions Have Value
- But there are barriers
- Solving Structural Barriers to Demand Response
- Involves addressing planning and investment
practices - Also removes some barriers affecting energy
efficiency and distributed generation
3Priorities and Realities
- Electric Market is Regional
- Public Policy Involved, Just a Matter of When
- Potential to improve investment decisions or slow
them down - Resource Parity Assures Least Cost
- Principles apply throughout power system
4Objectives
- Market oriented decisions with competitive forces
at work - Cost causation has merit
- Socialization granted only after passing a test
- Cost recover mechanisms comparable for all
resource solutions
5Demand Resources in Grid Planning and Investment
- Demand resources have a role in three areas
- Regional System Planning
- Regional Grid Investment Policy
- Distribution Utility Planning
6(A) Symptoms of Regional Electric Market Problems
- Lack of timely transmission line proposals
- Generation construction that causes congestion
- Lack of connection between electricity investment
decisions and environmental implications - Lack of consideration of customer resources to
solve grid problems - Lack of co-ordination of investment plans by
monopoly and competitive companies
7System Planning Recommendations
- Regional cooperation by states
- Continuing regional planning process
- Driven by system needs
- All solutions available
8Multi-StateCoordination
- Recommendation 1 Increase coordination among the
states and between states and the ISO - Efficiency to regulatory decision-making
- Certainty to the marketplace
- Guide ISO toward more efficient planning
- Avoid duplication of effort
- Support authority, independence of states
How far will States Go?
9Regional Power System Planning Process
- Recommendation 2 Conduct a continuing regional
power system planning process to identify system
needs and alternative strategies to meet them. - Cyclical
- Transparent
- System needs treated over time
- Maximum planning horizon
- Maintain responsiveness to emergent conditions
- Improve public confidence
10Regional Power System Planning Process
- Formal Role for State Governments if states want
it - Focus on areas of interest
- Involve more stakeholders
- Attract all solutions
11ComprehensiveSolution Set
- Recommendation 3 The outcome of a regional power
system planning process should be an evaluation
on an even-handed basis of a wide range of
feasible solutions to emerging problems,
including investments in generation,
transmission, and demand-side options. - Regardless of the planning process, all
reasonable solutions should be considered and
evaluated similarly - Candidate solutions come from competitive and
regulated entities - State regulation would have to support solutions
coming from regulated entities - Implementing a solution affects the economics of
the others
12System Investment Recommendations
- Market oriented investments preferred
- State authority remains
- Cost causation is appropriate
- Socialization is appropriate for some
reliability-oriented investments - Efficient Reliability Standard should apply
- Resource parity
- Least cost standard
- Cost recovery comparability
13(B) Grid Investment Policies
- Recommendation 4 Leave investment and siting
decisions in the hands of market participants and
state regulators wherever possible, assigning
cost responsibility to those who create the need
for system upgrades, and those who benefit from
them. - After grid problems and potential solutions are
identified in the system planning process, these
results should be posted publicly so that market
participants can consider what actions they might
take within the existing market structure to meet
emerging needs. Wherever possible, RSAC should
permit market-based and state-based responses to
emerge. - Public, regional intervention to promote or pay
for grid solutions should be taken only where it
is evident that adequate resolution is not
forthcoming in the market, or that the investment
in question is one that, as a matter of equity,
ought to be undertaken by grid managers with cost
recovery imposed through tariffs.
14(5) Efficient Reliability Test
- Recommendation 5
- ISO-New England, NEPOOL, and FERC should apply an
Efficient Reliability test, based on principles
of least-cost analysis and resource parity, when
considering proposals to socialize the costs of
system improvements through wholesale rules and
transmission tariffs.
15(5a)Two principles
- Resource parity Energy efficiency, load
management, demand-side bidding, and distributed
resources in addition to traditional generation
and transmission resources -- are all potentially
cost-effective means of meeting reliability needs
identified by system operators and power pool
managers. NEDRI recommends that when socialized
cost recovery is sought, that demand-side
resources be treated comparably to supply-side
and wires options both in analysis and in access
to funding. - Least-cost standard A principal criterion for
selecting a solution that is qualified to receive
socialized support should be whether it is the
lowest-cost, reasonably available solution to an
unmet system need, considered on a total cost
basis.
16(5b) Screening proposals to socialize grid costs
- NEDRI recommends that NEPOOL, ISO-New England,
and FERC adopt the following standard as a means
of screening proposals to socialize grid
enhancements - Before socializing the costs of a proposed
reliability-enhancing investment through tariff,
uplift, or other cost-sharing requirement, ISO-NE
(and FERC) should require the applicant to
demonstrate - (1) That the relevant market is fully open to
demand-side as well as supply-side resources - (2) That the proposed investment is the lowest
cost, reasonably-available means to correct a
remaining market failure and - (3) That benefits from the investment will be
widespread, and thus appropriate for support
through broad-based funding.
17(6) Comparable cost recovery opportunities
- Recommendation 6 Ensure comparable cost recovery
opportunities for transmission and
non-transmission resource solutions - Whether a grid problem is resolved through a
transmission or non-transmission solution, or a
combination of them, the solution should qualify
for cost recovery through transmission tariffs or
wholesale uplift charges on the same basis.
18(C) Distribution System Planning and Demand
Resources
- Recommendation 7 Distribution companies can and
should apply recommendations 1-6 - Distribution needs distinct from regional system
needs - Many circuits, shorter horizons
- Practices focus on traditional solutions
- Demand opportunities significant
- All resource planning focus requires a new
perspective
19Distribution needs distinct from regional system
needs
- Localized
- Distinct performance of individual circuits
- Timing driven by specific events or customers
- Shorter time horizons
20Redefinition of Distribution Planning
- Focus on wire solutions to address growth-related
challenges - Challenge to distribution planners
- A distinct source of value from customer
resources avoided distribution costs - Construction
- Losses, voltage support
- Full menu of customer resources
21Distributed Utility Planning
- Focus on circuits
- Factor in cost of incremental customer resources
(societal test) - Regulatory Policy matters
- Expect DUP to consider customer resources
- Pricing
- Break link between net income and sales
- Staffing
- Pilot
22Possible Roles of the Multi-State Entity
- Transmission Siting Advice
- Regional Resource Adequacy
- Congestion Monitoring
- Market Power Monitoring
- Gas Supply Co-ordination
- Environmental Issue Integration
- Technical Potential Assessments
- Innovative Solutions Advice
- Public Benefits Co-ordination
23RTEP Process Flow with observations
Need longer horizon
Opportunity to engage more rings of interested
people
Meetings throughout region are good
Public Policy input is inconsistent, not reliable
Unequal treatment for cost recovery among
resources is too large a barrier to get best
choices
Non-transmission alternatives not permitted to
compete (planning, cost recovery) here unclear
how any distributed resource options are
considered
Declaration of appropriate projects lacks weight
Queueing remains a problem
No effect on state decision-making on pricing,
metering, siting, distributed resources