Title: DAP Problem Statement
1WGARM Projects
- Digital Archives Programme, DAP
- Start up, SOW, RFI, RFP, Contract Award
- Phase I, Strategic Plan - 2003/2004
- Phase II, Implementation (pilot) - 2005/06
- Appraisal Decision Assistance, ADA
- Phase I, Start up initial Inventory - 2002/2003
- Phase II, Follow up, Consolidations design -
2004 - Phase III, Implementation in UNPOs - 2005
2 Strategic Plan for a Common ServicesUNPOs
Digital Archives Programme DAP
- Problem Statement
- Project Phases
- Project Benefits
- Project Overview
- Status/Next Steps
- Annexes
- UNDP, UNFPA, UNICEF, UNOPS, UN Secretariat
3DAP Problem Statement
- Digital Records are not captured, managed or
appropriately preserved in a consistent and
business-like manner. This creates significant
risk since critical organizational knowledge
assets may be lost, not accessible or only
recovered at a high cost.
4DAP Project Phases
- Start up - SOW, RFI, RFP, Contract Award
- Phase I - DAP Strategic Plan will identify
requirements and specifications, define standards
and establish an Implementation Plan - Phase II - DAP Implementation will implement the
framework and begin the necessary technical and
operational activities to develop digital
archiving.
5DAP Project Benefits
- Address business problem concerning the
management and preservation of digital records - Minimize UNPO duplication of efforts, cost
avoidance - Leverage experiences and knowledge, community of
practice - Promote good business and record keeping
practices.
6Strategic PlanProject Overview
- Develop Standards and
- Requirements,
- Identify Architectures,
- Preservation Strategies
- and Functional Models
Collect and analyse current policies, systems,
platforms and initiatives
Assessment
Design
Plan
- Road map for implementation
7DAP Status/Next Steps
- Status
- Start up, SOW, RFI, RFP, Contract negotiations
- Immediate Next Steps
- Contract award
- UNPO to designate DAP Coordinators as well as
support commitment required (see Annex for more
info) - WGARM to brief coordinators
- Circulate introductory letter to UNPO staff
announcing project and reinforcing
cooperation/commitment required.
8Next Steps (cont.)
- 2003 (Deliverable 1)
- Project Deliverable Work Plan and Time Table
agreed by UNPO DAP Coordinators - 2004 (Deliverables 2-7)
- Policy and Information System survey completed by
contractor and validated by UNPO - Digital Archive Standards and IT Specifications
identified and DAP framework designed - Implementation Plan
- Presentations
- Work plan/TOR for Implementation (DAP Phase II)
9Annexes
- DAP Definition
- DAP Scope
- DAP UNPO Focal Point/Co-ordinator Functions and
Skills/Expertise - Project Management
- Project Milestones
- Project Deliverables
- Appraisal Decision Assistance, ADA, Phases I, II
and III - Other WGARM projects on hold
10Digital Archives Programme, DAP Definition
- The Digital Archives Programme is a combination
of policies, procedures and technologies that
will facilitate the proper management,
appraisal/retention and preservation of digital
records and provides for the long term access and
use of materials with archival value. - Preservation requires active management that
begins with record creation.
11Digital Archive ProgrammeDefinition
Provides for the long term access and use of
materials
Facilitate the appraisal retention and
preservation of digital records
Combination of Policies, Procedures and
Technologies
Policy Procedures
Technologies
Management
Requires active management throughout record
lifecycle
12Project Scope
- Digital records created or received in UNPO NY
offices and identify issues related to digital
records created away from NY that may impact on
DAP effectiveness. - Digital records of archival value but contains
elements that interact with all records identify
Electronic Document Management System, (EDMS),
and Electronic Record Management System, (ERMS),
issues that effect DAP performance.
13Scope
DAP NY
Dig. Rec. Other Loc.
EDMS NY
ERMS NY
14UNPO DAP Co-ordinatorFunctions
- Serve as a UNPO central DAP focal point to
co-ordinate between UNPO staff, WGARM members,
DAP Project Manager and vendor - Attend and comment on key presentations
- Ensure UNPO DAP requirements and work units are
represented - Validate all UNPO information collected and
representative - Verify Vendor Deliverables
15UNPO DAP Co-ordinatorSkills/Expertise
- Knowledge of corporate and business practices
- Familiarity with UNPO organizational structure
- Awareness of information systems as well as
record keeping issues - Willingness to commit
- Authority to solicit and validate information
- Networking and people skills.
16Project Management
- Finalise SOW
- Develop EOI, RFI and RFP documents
- Develop RFI and RFP evaluation criteria/weights
- Assist and support UN Procurement on issuing RFP,
prepare documentation materials related to HCC
presentation, assist in drafting contract - follow up on RFP issues including vendor
questions, vendor references and related issues - Conduct and co-ordinate RFI and RFP Evaluation
meetings - Complete SOW annexes, follow up missing
information - Compile and make accessible project documents and
related materials, digitise where appropriate - prepare indicative budget documents for 2005/06
17Project Management (cont.)
- Develop presentation materials, overviews and
introductory materials concerning project - Develop and maintain project filing scheme
maintain all paper and electronic records related
to project - Register electronic copy of all project materials
in Trim, digitise documents whenever necessary - Maintain regular communication with UNPO
representatives/IT focal point attend meetings
and make presentations to representative groups - Make presentations and update UNPO related groups
such as UNSec Knowledge-Sharing,, ICTB - Provide progress updates to WGARM and co Chairs
- Develop DAP Deliverable Certification documents
- support related activities, such as WGARM
Appraisal Decision Assistance project and RAMP
IRDAM.
18DAP Project Milestones
- EOI/RFI - Sept.-November 2002 .
- RFI evaluated, shortlist created, SOW finalised -
mid Dec. 2002 - RFP issued by UN Procurement - 15 March - 9 May
2003 - Technical Evaluations - May/June 2003 (WGARM)
- Financial Evaluation/HCC Recommendation- July
2003 (UNPD) - Contract negotiations - September 2003
19DAP Project Deliverables
- Project Start up - October 2003 (anticipated)
- Deliverables - 10-12 Month projected timeline
- Work Plan Phase I (20 days),
- Administrative Survey (32 days),
- Technical Inventory/Assessment (35 days),
- DAP Design/Specs (57 days),
- Implementation Plan (32 days),
- DAP Presentations (23 days),
- Work Plan Phase II (39 days).
20 Appraisal Decision Assistance
ADA
- ADA Phase I - Start up Initial Inventory
(2002/03) - External Organisations 7
- Record Series Retention Schedules
- UNPOs 5 in NY
- Some Record Series from 110? Work-units and
- Some Retention/destruction schedules Rules
- Initial Result as of Sep 2003
- UNPO Main Functions 10 and Generic Series
Matrix - Generic Series linked to various multiple
retention periods - Preliminary ADA Database Tool in MS Access
21WGARM Appraisal Decision Assistance
ADA
- Phase II - Follow up, Consolidate Design
(2004) - UNPOs certify and CSTF review next steps
- UNPOs validate list of their organization work
units. - Provide GAP Analysis, Identify/Collect missing
UNPO Record Series - Consolidate Generic Record Series
- Standardise, justify apply appraisal values to
generic record series - retention schedules - Refine the ADA software tool for updates
presentation
22WGARM Appraisal Decision Assistance
ADA
- Phase III Implementation - by UNPO (2005)
- Confirm UNPO Record Series in all workunits
storage - Match UNPO Records Series to GRS Schedules
- Seek approvals and carry out retention
recommendations for each UNPO - Prioritise Record series for follow up actions.
E.g vital records protection, digitisation,
disposal. - Make GRS updates available via the ADA software
tool with internet access
23WGARM Appraisal Decision Assistance
ADA
1. Record Type
9. Business Model Systems
2. Importance of Activity
- Classical
- Appraisal
- Values
- Primary
- - Reason
- created or
- received
- Secondary
- - Evidence
- of Action
- or
- decision
- Tertiary
- - Ongoing
- informa-
- tional
- use
Appraisal Values Components
3. Subjects
8. Classical Appraisal Values
4. Level of Office
7. Form and Format Media of Storage
5. Practical consider- ations
6. Research Consider- ations discovery
24ADA Project Scope Components Appraisal
Values Identified and retention schedule
assigned for records created or received in NY
UNPOs
5 UNPOs UNDP, UNFPA, UNICEF, UNOPS UN
Secretariat
Main Functions or Business Processes
UNPO Record Series
Appraisal Values Criteria
UNPO Policy rules reflect or imply Appraisal
Values
Generic Records Series
UNPO Retention Schedules
Generic Retention Schedules
Managers Apply retention schedules to specific,
dated, Record Series in work units or storage
Areas
25WGARM Appraisal Decision Assistance
ADA
UNPOs 10 Main Functions - Sub Functions Link to
Record Series
26Other WGARM Projects(on hold pending DAP and ADA)
- Archive Research Centre CS-ARC as Common
Depository - Harmonization of Archives and Records policies
and procedures - Other important projects which would require
funding to expedite - Vital Records Protection
- Disaster Recovery Plans
- Prioritisation of digital scanning initiatives
- Plan for Integrated Records, Documents and
Archives - Field Advice