ECE 480 Gantt Charts Revisited - PowerPoint PPT Presentation

About This Presentation
Title:

ECE 480 Gantt Charts Revisited

Description:

ECE 480 Gantt Charts Revisited Keys to Successful Gantt Charts USE the default, finish-to-start, constraints obtained by specifying predecessors, unless you KNOW you ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 5
Provided by: good4
Learn more at: https://www.egr.msu.edu
Category:

less

Transcript and Presenter's Notes

Title: ECE 480 Gantt Charts Revisited


1
ECE 480Gantt Charts Revisited
2
Keys to Successful Gantt Charts
  • USE the default, finish-to-start, constraints
    obtained by specifying predecessors, unless you
    KNOW you need to do something else!!!
  • DONT put REPORTING tasks in the dependency
    chain, unless they are REALLY in the chain
  • If boss stops work unless approves report
  • If delaying report submission delays the
    completion of the project!

3
Keys, cont.
  • Dont block your critical path by making the last
    task scheduled be independent of other tasks
    you get NOTHING. Last task determines end of
    critical path, which works backwards from there.
  • TEST your critical path EVERY task that must be
    accomplished to avoid delaying successful project
    completion should appear in a dependency chain
    that leads to final demo of your project. Thats
    NOT interim reports and presentations! You can
    ALWAYS report progress e.g., There was none.
    Thats a progress report.

4
Keys, cont.
  • Use Tracking Gantt mode to see critical path
    and task completion/partial completion
  • Track (record) completion of tasks regularly,
    show your facilitator
  • Make sure your (operating) plan shows completion
    by the due date (last Thursday of semester, or
    earlier)
Write a Comment
User Comments (0)
About PowerShow.com