FORMWORK - PowerPoint PPT Presentation

About This Presentation
Title:

FORMWORK

Description:

FORMWORK Formwork Forms are molds to receive concrete in its plastic form. Formwork is a temporary structure; as such, it is not normally shown on the drawings. – PowerPoint PPT presentation

Number of Views:4438
Avg rating:3.0/5.0
Slides: 28
Provided by: AlanOn5
Category:

less

Transcript and Presenter's Notes

Title: FORMWORK


1
FORMWORK
2
Formwork
  • Forms are molds to receive concrete in its
    plastic form.
  • Formwork is a temporary structure as such, it is
    not normally shown on the drawings.

3
Formwork for Beams and Slabs
4
Formwork Materials
  • Wood
  • Either all-wood or some wood components
  • Plywood
  • Aluminum
  • Steel
  • Plastics

5
Lumber
  • Designated by Cross Sections, Nominal Dimensions
    (prior to finishing)
  • After cut length wise, finishing operations
    reduces actual dimensions
  • 2 x 4 Plank 1 1/2 x 3 1/2 ? 2 by 4 in S4S
  • Lengths are multiples of 2 ft (8, 10, 12, 14,
    16,)
  • Specified by type and grade
  • Type pine, oak, fir
  • Grade Selected (A, B, C, D) and Common (1, 2, 3,
    4)
  • Selected (A best, D poor quality)
  • Cost ? Kind, grade, size, length, milling,
    quantity, freight

6
Plywood
  • 4 ft wide - 8, 10, 12 ft long
  • 1/4, 3/8, 1/2, 5/8, 3/4 inch thick

7
Plywood Orientation
Weak Orientation of Plywood (Face grain parallel
to span)
Strong Orientation of Plywood (Face grain
perpendicular to span)
Face Grain Direction
Face Grain Direction
8
Aluminum
  • Pure aluminum chemically attacked by wet concrete
  • Light weight allows larger forming units
  • High reuse value

Aluminum beam nailer - type
9
Steel
  • For heavy concrete work
  • With reasonable care will last indefinitely
  • High initial cost and high handling cost

10
Estimating Issues
  • Normally, the forms are used more than once
  • More usage of forms reduces the price
  • Wood forms have less usage potential than
    aluminum or steel forms
  • Complicated shapes of concrete are more expensive
    because of labor cost and reuse of forms.

11
Estimating Issues (cont.)
  • Majority of cost is _____?? Not ____??
  • You have to have a construction plan to determine
    the reuse cycle
  • Number of reused largely controls _____?? Cost.

12
Effect of Reuse on Concrete Formwork Cost
13
Estimating Issues (Formwork)
  • Do not deduct
  • Intersection of beams
  • Intersection of beams columns walls
  • Any opening lt 100 sq. ft.

14
Formwork
  • Unit of Measurement
  • Square Foot Contact Area
  • SFCA
  • Measure just contact area, not area of formwork
  • Contact Area
  • 2h(LB)

h
Concrete
B
L
15
  • Wood normally measured
  • Linear feet of one size
  • Board Feet
  • FBM (Foot Board Measure)
  • 1x12x1(long) or 144 cubic inches
  • example 2x8 x 16ft long
  • 1.33 BF/LF x 16 21.28 FBM

2 x 8 12
16
Additional Costs
  • Nails
  • For first use, 10 - 20 lb. Per 1000 fbm
  • Additional used, 5 - 10 lb. Per fbm
  • Form Oil
  • 300 - 500 ft2/gal
  • Ties
  • Ties keep forms apart and resist bursting
    pressure of concrete
  • Stay in concrete, pull out
  • Types
  • Steel bands
  • Rods
  • Threaded
  • w/ Nuts and clamps

17
Design and Estimating of Forms
  • Design determines Sheathing thickness, stud
    size, wale size, tie size
  • Use of design tables
  • Watch for
  • 1. Rate of pour
  • 2. Temperature and weather
  • 3. Proportions of mix and consistency
  • 4. Method of placement and vibration

18
Workshop Example
  • Estimate the cost of formwork for concrete wall
    (96 x 254)
  • The rate of placing concrete 4 ft/hour
  • Maximum temperature of concrete 70ºF

19
(No Transcript)
20
Design of Forms for concrete Walls
21
(No Transcript)
22
  • The wall is 9-6 high and 25-4 long.
  • From design table
  • Max. pressure, 664 lb/ft2
  • Max. spacing of studs, 19 in, use 18 in
  • Max. spacing of wales, 25 in, use 24 in
  • Max. spacing of form ties, 31 in
  • The 3/4 plywood sheathing will be placed with
    the 4 ft wide in the vertical direction and the 8
    ft length in the horizontal direction.
  • The total quantity of sheathing will be
  • No. sheets in vertical direction, 9-6? 4/sheet
    2.37, use 3 sheets
  • No. sheets in horizontal direction, 25-4?
    8/sheet 3.16, use 4 sheets
  • No. sheets required per side, 3 x 4 12
  • No. sheets required for wall, 12 x 2 24

23
  • Studs required
  • Length of wall, (25 x 12)4 304 in
  • Spacing of studs, 18 in
  • No. studs required per side, (304/18)1 18
  • No. studs required for wall, 2 x18 26
  • Lumber required, 36 pc, 2 x4 x 10 ft 240 fbm
  • Wales required
  • Height of wall, 114 in
  • Spacing of wales, 24 in
  • No. required per side, 114/24 4.75, use 5
    wales
  • For each wale, use 2 pc of 2x4 x 12 ft
  • and 2 pc of 2x4 x 14 ft lumber
  • Lumber required
  • 20 pc, 2x4 x 12 ft 160 fbm
  • 20 pc, 2x4 x 14 ft 187 fbm

24
  • Total lumber 240 160 187
  • 587 fbm
  • Add 10 to 20 for misc. (sills, spliceetc)
  • Total quantity of lumber
  • 587 0.2 x 587
  • 704 fbm

25
  • Number of ties needed
  • If we use 4000 lb ties
  • Number of ties
  • 51 ties

644 x 9.5 x 25.3 4000
26
  • Quantity of Nails
  • 704 x 10 lb/1000fbm
  • 7.04 lbs

27
Summary of Materials to Build forms
  • Plywood required 24 sheets
  • Lumber required 704 fbm
  • Nails required 7 lbs
  • Ties required 51
Write a Comment
User Comments (0)
About PowerShow.com