Project Management - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Project Management

Description:

Title: PRODUCTIONS/OPERATIONS MANAGEMENT Author: Bethany Stubbe Last modified by: wcosgrove Created Date: 4/8/1998 10:12:42 PM Document presentation format – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 39
Provided by: Bethany45
Category:

less

Transcript and Presenter's Notes

Title: Project Management


1
  • Project Management
  • Chapter 17

2
Projects
Unique, one-time operations designed to
accomplish a specific set of objectives in a
limited time frame.
3
Project Management
  • How is it different?
  • Limited time frame
  • Narrow focus, specific objectives
  • Less bureaucratic
  • Why is it used?
  • Special needs
  • Pressures for new or improves products or services

4
Project Management
  • What are the Key Metrics
  • Time
  • Cost
  • Performance objectives
  • What are the Key Success Factors?
  • Top-down commitment
  • Having a capable project manager
  • Having time to plan
  • Careful tracking and control
  • Good communications

5
Project Management
  • What are the Major Administrative Issues?
  • Executive responsibilities
  • Project selection
  • Project manager selection
  • Organizational structure
  • Organizational alternatives
  • Manage within functional unit
  • Assign a coordinator
  • Use a matrix organization with a project leader

6
Project Management
  • What are the tools?
  • Work breakdown structure
  • Network diagram
  • Gantt charts
  • Risk management

7

Summary of Key Decisions
  • Deciding which projects to implement
  • Selecting a project manager
  • Selecting a project team
  • Planning and designing the project
  • Managing and controlling project resources
  • Deciding if and when a project should be
    terminated

8
Project Manager
  • Responsible for

Work Quality Human Resources Time Communicat
ions Costs
9
Project Life Cycle
Management
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
Planning and Scheduling
Gantt Chart
15
PERT and CPM Networks
  • PERT Program Evaluation and Review Technique
  • CPM Critical Path Method
  • Graphically displays project activities
  • Estimates how long the project will take
  • Indicates most critical activities
  • Show where delays will not affect project

16
The Network Diagram
  • Network (precedence) diagram diagram of project
    activities that shows sequential relationships by
    the use of arrows and nodes.
  • Activity-on-arrow (AOA) a network diagram
    convention in which arrows designate activities.
  • Activity-on-node (AON) a network diagram
    convention in which nodes designate activities.
  • Activities steps in the project that consume
    resources and/or time.
  • Events the starting and finishing of
    activities, designated by nodes in the AOA
    convention.

17
The Network Diagram (contd)
  • Path
  • Sequence of activities that leads from the
    starting node to the finishing node
  • Critical path
  • The longest path determines expected project
    duration
  • Critical activities
  • Activities on the critical path
  • Slack
  • Allowable slippage for path the difference the
    length of path and the length of critical path

18
Network Conventions for PERT and CPM Networks
(AOA)
19
Project Network
20
Project Network with Activity Times and
Activities Labeled
21
Example
22
Example Solution
Critical Path
23
Computing Algorithm
  • Network activities
  • ES earliest start
  • EF earliest finish
  • LS latest start
  • LF latest finish
  • Used to determine
  • Expected project duration
  • Slack time
  • Critical path

24
Project Management Software
  • Computer aided design (CAD)
  • Groupware (Lotus Notes)
  • CA Super Project
  • Harvard Total Manager
  • MS Project
  • Sure Track Project Manager
  • Time Line

25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
Advantages of PM Software
  • Imposes a methodology
  • Provides logical planning structure
  • Enhances team communication
  • Flag constraint violations
  • Automatic report formats
  • Multiple levels of reports
  • Enables what-if scenarios
  • Generates various chart types

30
Summary
  • Projects are a unique set of activities
  • Projects go through life cycles
  • PERT and CPM are two common techniques
  • Network diagrams
  • Project management software available

31
Advantages of Gantt Charts and Networks
  • Forces managers to organize
  • Provides graphic display of activities
  • Identifies
  • Critical activities
  • Slack activities

32
Limitations of Networks
  • Important activities may be omitted
  • Precedence relationships may not be correct
  • Estimates may include a fudge factor

142 weeks
33
Ethical Issues
  • Temptation to understate costs
  • Withhold information
  • Misleading status reports
  • Falsifying records
  • Comprising workers safety
  • Approving substandard work

34
Homework Problem
Do problem 5 (part a only) on p. 819. While
thesolution is given in the following slides, be
sure that you take the time to try to solve this
problem prior to looking at the solution.
35
Problem 5a
Network before doing the critical path method
5
9
2
8
2
3
4
7
6
10
5
6
4
36
Network after doing the critical path method
5a.
(Activity slacks are given in the table on the
next slide)
5
26 18
7
4
Key?
9
2
12 4
28 21
11 4
8
2
3
4
7
19 12
6
10
5
6
4
37
5a (continued)
38
End of slides for Project Management
Write a Comment
User Comments (0)
About PowerShow.com