Title: IV


1
IVV Lessons Learned Mars Exploration Rovers
andthe Spirit SOL-18 AnomalyNASA IVV
InvolvementAugust 2004
Kenneth Costello Senior IVV ManagerNASA IVV
Facility 100 University Dr Fairmont, West
Virginia 26508 Kenneth.A.Costello_at_nasa.gov 304
367 8343
2
Introduction
  • Purpose
  • This is an information presentation to provide a
    quick overview of IVV and provide some lessons
    learned for IVV from the Mars Exploration Rover
    project
  • Agenda
  • Overview of NASA IVV
  • Background on IVV involvement with the MER
    program
  • IVV issues related to the system memory and file
    system
  • IVV Lessons Learned
  • Summary

3
What is NASA IVV?
  • NASA IVV is a program managed by the Safety and
    Mission Assurance Office
  • The program is delegated to the Goddard Space
    Flight Center and is managed from the NASA IVV
    Facility in Fairmont, West Virginia
  • Facility was dedicated in 1994
  • Focus on unmanned missions began around 2000
  • The program has two main roles for the Agency
  • The first role is to provide an Independent VV
    capability and ensure mission software readiness
    for critical projects focused around risk and
    safety
  • The second role is to enhance software readiness
    by providing IVV domain expertise to Projects to
    identify issues/defects and propose possible
    solutions

4
Scope DeterminationSoftware Integrity Level
Assessment Process
For each Software Component
Final values plotted on a 5x5 matrix for
reference. Values are also used to
cross-reference a task matrix.
Criticality
Rating
Category
Human Safety
1-5 score where 5 is highest
Criticality
Asset Safety
Performance





Each factor has an associated weight applied
before being combined into a final value
Error Potential
Rating
Category
Development Organization
E1
1-5 score where 5 is highest
Error Potential
Development Process
Software Characteristics
Task selection is from a standardized list of
tasks. Allocation is based on criticality value
and on error potential value individually.
5
IVV Lifecycle Flow
Focused activity at the earliest point System
requirements and software role important Issues
are introduced at lowest level
Concept Phase
Verification
Covers all levels of testing Ensure that system
meets the needs of the mission
System Requirements
Software Planning
Verification
Verification
IVV in phase with development (not testing only)
Validation Testing
Software Requirements
Verification
Design
Verification
Simulator/ Environment/ Hardware
Implementation
Verification
Maintenance
Later life cycle activity still important Issues
are still introduced at lowest level Focused more
on individual components
IVV support continues over initial operational
phase
6
IVV Activities for MER
  • Initial assessment of the MER project performed
    in June 2001
  • Results of assessment noted that the file system
    was a very critical portion of the FSW, however,
    the scores for the technology being used and the
    maturity of the software indicated low risk
  • Some portions were rated as high complexity
  • Overall the file system software was within the
    IVV scope though at a low level
  • Initial estimate of the IVV resources was 9-10
    FTEs
  • The MER Project had not budgeted for that level
    of IVV resources
  • Final IVV resources were 4-5 FTEs
  • Reduction in resources necessitated changes in
    the approach to IVV
  • Goal was to cover the MER FSW to a reasonable
    depth so that the IVV Team could feel
    comfortable supporting launch and operational
    readiness reviews for the project
  • Tasking was pulled up to a higher level than
    normal analysis applied at a complete FSW level
    rather than at a software component level
  • Additional issue in regards to a limited number
    of FSW requirement artifacts

7
Summary of Spirit Sol-18 System Memory Consumption
  • Sol 18
  • 900 LST The planned DTE HGA communication
    session began.
  • 911 LST Event Reports were received
    indicating uplink errors were occurring. Downlink
    was spotty.
  • 916 LST The signal was lost. This was 14
    minutes earlier than expected
  • 1120 LST Commanded a 30-minute high priority
    HGA communication session. No signal was seen.
  • 1245 LST Commanded an LGA beep. The beep
    occurred as predicted (start and duration).
  • 1618 LST Odyssey UHF pass over Spirit, no
    carrier seen
  • Sol 19
  • 145 LST The MGS UHF communications session
    lasted only 2 minutes and 20 seconds. It did
    start at the correct time but only a repeating
    PsuedoNoise code was present in the data.
  • 439 LST No early morning UHF communication
    session with the Odyssey spacecraft (no signal or
    data).
  • 900 LST No morning HGA DTE communication
    session. No signal or data were detected.
  • 1100 LST Looked for 10 bps LGA DTE
    communication session initiated by a system fault
    protection response. No signal was seen.
  • 1440 LST Commanded beep at 7.8125 bps. Beep
    was seen!
  • 1524 No afternoon UHF communication session
    with the Odyssey spacecraft (no signal or data).
  • 1527 Attempted to command an LGA DTE
    communication session. No signal or data was
    received.
  • A system level fault had occurred on Sol 19 that
    put the rover in a degraded communication state
    and allowed some commanding
  • Eventually, JPL was able to determine that FSW
    was in a continuous delayed reset loop. The first
    reset seemed to occur during the Sol 18 morning
    DTE session coincident with an actuator checkout
  • Both commanded and autonomous shutdowns were
    failing and the vehicle probably had not shutdown
    in a while

8
Root Cause
  • The root cause was traced to two configuration
    parameters in the VxWorks operating system
  • Configuration parameters of the dosFsLib module3
    permitted the unbounded consumption of memory
    from the system memory heap as the FLASH file
    system was populated with an increasing number of
    files
  • The configuration parameters of the memPartLib
    module4 were set so that the logic would suspend
    the execution of any task that requested memory
    when no additional memory was available
  • This had the undesirable effect of suspending a
    critical task when the memory space was exhausted
  • Other effects included memory corruption,
    inability to turn vehicle off (due to task
    deadlock), repeating system resets
  • Contributing factors included the compressed
    development schedule, unanticipated behavior of
    the FSW, incomplete development (analysis of the
    effects of the dosFsLib parameters was never
    fully completed), test program was not equivalent
    to operational use, and inadequate telemetry

9
IVV Findings Related to the System Memory
  • Requirement and test completeness
  • IVV Risk 1 on Requirements (and extended to
    include test) was remaining risk in Significant
    Concern status at time of upload
  • Chief concern was that software requirements
    discovery was not complete and that software had
    not been adequately tested at the time of the
    upload
  • Specific TIMs
  • Specific TIMs were written against the
    insufficient unit tests for portions of the file
    system using the system memory
  • Project asserted testing was complete but without
    documentation
  • These TIMs were still in Open state at the time
    of the final upload
  • Code Complexity
  • Portions of the file system using the system
    memory was consistently reported to be very
    complex
  • Modules were reported to have poor testability
    and poor maintainability
  • Code Stability
  • File system modules were being worked on until
    the last release (R8.1d, 11/20/03)
  • File Meta Engine had 10 of its total code
    changed as late as Release 8.0, and had 9 of its
    total code changed for Release 8.1
  • Note that the file system was not the cause of
    the problem, but brought the lack of memory to
    light and created the task deadlock

10
IVV Concerns over Requirements Test
  • Upload Readiness Review (11/25/03)
  • Plans were to upload final FSW on 12/2/05 review
    was to determine readiness
  • IVV recommended further testing before upload,
    delaying upload past Dec 2
  • Operational Readiness Review (12/5/03)
  • Aggregate of requirement and test issues
    represent a risk being tracked in IVV Risks
  • Final Requirements Risk status was Significant
    Concern (middle of three possible levels)
  • IVV Concern There remains an IVV concern
    about the possibility of requirements-related
    surprises during operations. IVV has a less
    optimistic view of the requirements discovery
    than does the project.
  • Potential Consequence for Surface ops Possible
    loss of science return (Possible loss of
    science return means the situation we are
    currently seeing significant time to detect,
    understand, and correct problems on the surface)
  • Reiteration of 11/25/03 IVV recommendation for
    further testing before upload (which by 12/5/03
    had already occurred, the project having
    proceeded with planned upload on 12/2/03)
  • Recommendation to Continue testing to the extent
    possible
  • Recommendation to Ensure test results are
    adequately reviewed
  • Project emphasis on test as you fly (vs. formal
    unit and requirements-based tests) didnt find
    the problem

11
IVV Lessons Learned
  • Resources
  • The low level of resources being applied to such
    a large and complex project was not sufficient
  • The goal of analyzing the software at a depth
    that would allow the IVV Team to feel confident
    when supporting project readiness reviews had to
    be maintained
  • Forced a shift from a software component approach
    to a more whole system approach
  • Resources for IVV should be such that a software
    component approach can be maintained throughout a
    project SDLC
  • Lack of Artifacts
  • Current IVV Facility processes are very
    requirements driven
  • The lack of FSW requirements artifacts on the MER
    Project affected the IVV work being performed
    and also helped to move the approach away from a
    component level analysis
  • Additionally projects are not generally required
    to follow a standardized software development
    life cycle
  • The IVV Facility needs to examine its
    requirements driven approach and generate some
    alternative approaches to performing IVV on
    projects lacking software artifacts

12
IVV Lessons Learned
  • Pursuing Risks
  • Early on the IVV Team documented the
    requirements risk
  • Project would only address specific problems that
    were realization of the risk not the risk itself
    with the IVV Team
  • Otherwise, the planned testing program mitigated
    the risk in the projects eyes
  • The IVV Team was still concerned, but the lack
    of FSW requirements made it difficult to fully
    examine the consequences and likelihood of the
    risk
  • The IVV Team eventually accepted the test
    program as a mitigation to the risk
  • However as milestone reviews neared, the testing
    in some cases had not been completed
  • The project continued testing up to the last
    minute
  • Additionally, the lack of requirements artifacts
    placed the MER Project into the position of
    testing with incomplete requirements
  • Testing was driven more by scenarios generated by
    system engineers such that they felt that the
    system was fully exercised IVV had no insight
    into how the scenarios were developed
  • The IVV Team needs to be more proactive in
    assessing mitigation efforts early in the SDLC so
    as to more effectively support projects
  • Additionally projects should enforce and follow
    good software engineering practices that includes
    good requirements development to support a mature
    test program

13
IVV Contributing Factors
  • The IVV Team needs to be intimately involved
    with the development team
  • The MER projects compressed schedule created a
    schedule risk from outside parties
  • The IVV team was not able to work directly with
    the developer
  • Additionally there was no access to the
    development issue database or the low level
    testing artifacts that would allow IVV to
    perform a more in-depth analysis
  • Projects need to integrate the IVV process into
    the development process in order to gain maximum
    advantage of the resources being offered
  • Need to monitor relationship to ensure that
    independence is not lost
  • More specific attention to COTS products
  • The root cause in this case was the incorrect use
    of a COTS product
  • The IVV team usually analyzes the use of and
    interfaces between COTS and developed code since
    the content of most COTS products is not visible
  • The IVV team was not able to perform that level
    of analysis on this mission due to resource
    constraints

14
Summary
  • The IVV approach was modified based on various
    project specific factors that caused the analysis
    approach to be elevated to a full system approach
    rather than the normal software component
    approach
  • Even at the full system approach, the IVV team
    identified potential troubling areas involving
    the system memory usage risk tracking, issue
    tracking, code analysis, requirements analysis,
    test analysis, code complexity, and code
    stability
  • However, the lack of complete requirements
    documents and testing documentation, both
    identified by IVV as project deficiencies,
    hindered finding the specific problem prior to
    upload
  • The IVV Facility is examining the lessons
    learned to determine what actions to take to
    ensure better service on other IVV projects