GLAST Large Area Telescope: - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

GLAST Large Area Telescope:

Description:

GLAST Large Area Telescope: Manufacturing Preparation Design Engineering Meeting Jerry Clinton 1 April 2003 Stanford Linear Accelerator Center Stanford, CA – PowerPoint PPT presentation

Number of Views:94
Avg rating:3.0/5.0
Slides: 15
Provided by: Pet1164
Category:

less

Transcript and Presenter's Notes

Title: GLAST Large Area Telescope:


1
GLAST Large Area Telescope Manufacturing
Preparation Design Engineering Meeting Jerry
Clinton 1 April 2003 Stanford Linear Accelerator
Center Stanford, CA
2
Procurement Process Flow
3
Manufacturing Requirements
  • Drawings and specifications must be released
  • Parts and materials must be listed on PIL and
    must be approved by PCB or MPRB as appropriate
  • All parts and materials must be issued from
    flight stores
  • Completed flight assemblies must be kept in
    flight stores
  • Work must be authorized via an approved Assembly
    and Inspection Data Sheet (AIDS)

4
Manufacturing Process
  • Closed loop
  • Parts and materials issued in kits from stores
  • Kit is assembled, tested, and inspected
  • Delivery of assembled kit to stores closes the
    loop
  • Maintains clear traceability of parts, materials,
    and finished flight items
  • Approved AIDS is required to start the process
  • Applies to fabrication, assembly, test, and
    inspection
  • Does not apply to fabrication where supplier
    procures raw materials
  • If work is to be performed by a subcontractor,
    their travelers should be attached, or PO should
    require supplier to make them available for
    review by SLAC and Government personnel

5
Manufacturing Process - Continued
  • Stock room verifies item is ready for
    manufacturing prior to pulling kit
  • Drawings and/or specifications released
  • Test procedures released
  • Parts approved
  • Completed AIDS ends the process
  • Last step is to deliver to stores

6
Assembly and Inspection Data Sheets
  • AIDSs are LAT work orders
  • Authorize taking parts and materials out of
    stores and performing work to manufacture flight
    hardware
  • Defines operations executed to fabricate,
    assemble, and test LAT hardware items
  • Provide traceability from raw materials to
    finished flight items
  • Required for all LAT manufacturing activities
    including outside fabrication and assembly
  • LAT-MD-01624
  • AIDS preparation instructions
  • Provides some guidelines on work instruction
    preparation
  • Accessed from Quality Assurance web page

7
AIDS List Screen
8
AIDS Entry Screen (Top Portion)
9
AIDS Entry Screen (Bottom Portion)
10
Check Screen
11
AIDS List with New Record
12
Report Screen
13
Update Screen
14
Updated Report Screen
Write a Comment
User Comments (0)
About PowerShow.com