PGRR 18 - PowerPoint PPT Presentation

1 / 4
About This Presentation
Title:

PGRR 18

Description:

PGRR 18 PURPOSE Increase the credibility of new generation capacity additions considered in the ERCOT models used for planning assessments and in the calculation of ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 5
Provided by: sga78
Category:
Tags: pgrr

less

Transcript and Presenter's Notes

Title: PGRR 18


1
PGRR 18
  • PURPOSE
  • Increase the credibility of new generation
    capacity additions considered in the ERCOT models
    used for planning assessments and in the
    calculation of the CDR report.
  • Under the present process, counting on proposed
    Generation Resources with only a signed IA can
    negatively impact the planning studies which
    could lead to future reliability problems.

2
PGRR 18
Requirements for inclusion in ERCOT planning models and CDR Report PRESENT PGRR18
SGIA from TSP v v
IE notifies ERCOT that it has received a TCEQ-approved air permit v
IE demonstrates that it has obtained water rights sufficient for plant operation v
Notice to proceed v
Financial Security v
If necessary
3
PGRR 18
  • FINANCIAL SECURITY OPTIONS
  • OPTION 1
  • A signed Standard Generation Interconnection
    Agreement (SGIA) from the Transmission Service
    Provider (TSP) and a written notice from the TSP
    that the Interconnecting Entity (IE) has
    provided
  • a notice to proceed with the construction of the
    interconnection and
  • the financial security required to fund the
    interconnection facilities or
  • OPTION 2
  • A signed Standard Generation Interconnection
    Agreement (SGIA) from the Transmission Service
    Provider (TSP) and one of the following
  • a written notice from the TSP that the
    Interconnecting Entity (IE) has provided a notice
    to proceed with the construction of the
    interconnection and the financial security
    required to fund the interconnection facilities
    or
  • an affidavit from the IE to ERCOT confirming that
    a financially binding agreement to construct the
    Generation Resource (i.e. an engineering,
    procurement, and construction contract) has been
    executed.

4
PGRR 18
  • STATUS
  • 3/29/12, PLWG did not reach consensus on PGRR018,
    but was in agreement to forward PGRR018 as
    amended by the 3/27/12 Oncor Electric Delivery
    comments and as revised by PLWG, including
    options in paragraph (1)(a) of Section 6.9, to
    ROS.
  • 4/26/12, it was agreed that both options should
    be presented to ROS for consideration.
  • Scheduled for consideration by ROS at June 14
    meeting