Title: Project Management Introduction to Microsoft Project 2000
1Project ManagementIntroduction to Microsoft
Project 2000
- Building the Project Schedule - Tasks and
Dependencies - Assigning Resources and Costs
- Project Tracking
- Generating Project Reports
- Other
2Simplified ExampleComputer Hardware Installation
- Three Major Tasks
- Prepare the Facility
- Move the Computers Into Place
- Hook-up and Test Computers
3Enter Project Start Date
Click Here
4Click Here and Select Start Date
Note You can enter the project start date -
finish date will be calculated. Or
you can enter the project finish date
and the required start date will be calculated.
5Define Calendar
Click Here
6(No Transcript)
7Enter Major Project Tasks
- Make sure Gantt Chart View is up
- VIEW
- Gantt Chart
- Enter Major Tasks
- Prepare the Facility
- Move the Computer
- Hook-up and Test
8Enter Major Project Tasks
Defaults
9Enter Task Durations
Enter Full or Fractional Times
Enter Full or Fractional Times
10Defining Inter-Relationships
- Link Major Tasks
- Method 1 click on the first task
- hold the Ctrl key down
- click on the task to be linked
- click on the link button (chain symbol)
- continue with the remaining tasks
- To un-link - repeat but click on the un-link key
(broken chain symbol. - Method 2 click on the first bar-dont release
the mouse button - drag to the next bar --
release when you get to the next bar.
11Linking Tasks
12Identify Sub-TasksWork Breakdown Tree
Prepare the Facility
Top Level
Remove Existing Computers
Remodel Lab
Level 2
- Remove Monitors
- Remove Computers
- Unbolt Desks
- Transport to Salvage
- Remove Carpet
- Paint Room
- Install Electrical Conduit
- Install New Carpet
- Install Desks
Level 3
13Sequence Level 2 Tasks
Remove Existing Computers
Remodel Lab
14Entering Sub-Tasks
- Enter Sub-Tasks Under Each Major Task
- Start with Prepare the facility
- Click on the line after Prepare the Facility
- Click in INSERT button
- Click on INSET TASK (blank line should appear)
- Type Remove Existing Computers (see work
breakdown) - Touch the ENTER key
- Repeat this process and enter Remodel Lab
- Block and click on Right Arrow Button to indent
15Project Tasks Have Been Linked
16Hey! We can start a day early - 8/25/98
17Project Now Scheduled to Start Tuesday 8/25/98
18Develop Sub-Task SequencePrepare the Facility -
Remove Existing Computers
- Remove Monitors
- Remove Computers
- Unbolt Desks
- Transport to Salvage
Remove Monitors
Unbolt Desks
Transport to Salvage
Remove Computers
19Enter Additional Sub-Tasks)
- Now go to next level sub-tasks
- Click on the line after Remove Existing
Computers - Click in INSERT button
- Click on INSET TASK (blank line should appear)
- Type Remove Monitors (see work breakdown)
- Touch the ENTER key
- Repeat until all sub-tasks are entered for
Remove - Existing Computers
- Block and click on Right Arrow Button to indent
- Insure links established
20Sub-Tasks Entered, Times Entered, Task Linkages
Established
21Time to Organize Tasks in Outline Form
Double Click -- Then Select Outline Number
22Alternative Outlining Approach
- Numbering tasks in Outline Form
- Click on TOOLS
- Click on OPTIONS
- Click on VIEW
- Click on SHOW OUTLINE NUMBER
23Alternative Approach to Outlining
Outline Numbers Now Included With Task Name
24Develop Sub-Task SequencePrepare the Facility -
Remodel the Lab
- Remove Carpet
- Paint Room
- Install Electrical Conduit
- Install New Carpet
- Install Desks
Remove Carpet
Paint Room
Install New Carpet
Install Desks
Install Conduit
25Enter Additional Sub-Tasks
- Click on the line after Remodel the Lab
- Click in INSERT button
- Click on INSET TASK (blank line should appear)
- Type Remove Carpet (see work breakdown)
- Touch the ENTER key
- Repeat until all sub-tasks are entered for
Remodel - the Lab
- Block and click on Right Arrow Button to indent
26Note Analysis indicates that Moving Computers
will take 4.5 days rather than 2.5 days
Sub-tasks and Times Entered Linkages Established
27Identify Sub-TasksWork Breakdown Tree
Install Computers Test
Load Software
Test
De-bug
Note No Lower level tasks identified.
28Include Remaining Sub-Tasks
Links in Place
Project Scheduled to Finish September 22
29View Different Information
Slide screen to left to expose less information -
30Modify Work Calendar - Labor Day
- Modifying Our Work Calendar
- Click on TOOLS button
- Click on CHANGE WORKING TIME
- hit Page Down (or click down arrow)to go to
September - We will not work on Monday, September 7
- Leave Working times at default settings
- 8-12 and 1-5
- 8 hours a day
Will This Impact the Finish Date?
31Closed on Labor Day
Finish Date - Now September 23
32Project Critical Path
- Determine Critical Path
- Click on FORMAT button
- Drag down to TEXT STYLES and click
- at ITEM TO CHANGE go To CRITICAL TASKS
- under FONT STYLE select ITALIC
- under COLOR select RED
33Identify Critical Path
Non-critical tasks
Critical Path In Red (Italic)
34Seeing More Information
- To See Schedule with Slack times and other key
information - Click on View
- Click on Tables
- Click on Schedule
- Drag the Gantt Chart divider to the right if
needed
35Expanded Schedule Information
Free Slack Amount of Time a task can be delayed
without delaying another task
36Viewing the PERT Chart
- To Look at PERT Chart
- Click on View (or use Icons on left of screen)
- Click on PERT Chart
- To Adjust View, click on FORMAT
- then click on BOX STYLES for various options
37PERT Chart - Entire Project View
To get entire project view (or other size
views click View -- then click Zoom
38Changing Text Box Information
Click on a Box - Then Click Format - Then
Click on Text Boxes
39Calendar View
40Modifying Calendar View
- Click on any bar in the calendar
- Click Format
- Click Bar Styles
- make desired changes
41Changing Critical Tasks on Calendar View
42Critical Tasks Now in Red
43Incorporating Resources - People - Equipment -
Materials
- Groups - resources can be assigned to groups -
then you can filter to see only tasks belonging
to a group. Tasks are not assigned to groups. - Max Units - percent of available time this
resource is available for this project. (Note,
if a resource is actually several people - max.
units people x 100) - St. Rate - non overtime rate of pay - hourly
- Ovt. Rate - overtime pay rate - hourly
- Cost/Use - fixed cost per use (Truck Rental) -
also used to assign materials cost per unit - Accrue At - determines at what point in task the
costs will be assigned.
44To Enter Resources Click -- View
Click -- Resource Sheet
Allocating 100 of resources time to this
project
45Assigning Resources to Tasks
- Assigning Resources to Tasks
- select Gantt Chart
- Double Click on the desired task
- Click on RESOURCE Tab
- enter resource assignment information and click
on ASSIGN
This process is repeated for all tasks that need
resources.
46100 indicates that the resource will work full
time on this task during the task duration.
47Alternative Approach for Resource Assignment
Click Task - Click Tools - Click Resources
-Click Assign Resources - Select Resources to
be assigned.
48Resource Allocations
- Remove Monitors - Technicians 1 2
- Remove Computers - Technicians 1 2
- Unbolt Desks - Carpenters 1 2
- Transport to Salvage - Technicians 1 2, Moving
Truck - Remove Old Carpet - Carpet Team
- Paint Room - Painters 1 2
- Install Electrical Conduit - Electrician
Carpenter 1 - Install New Carpet - Carpet Team
- Install Desks - Carpenters 1 2
- Move Computers - Technicians 1 2, Moving Truck
- Load Software - Technicians 1 2
- Test Systems - Technicians 1 2
- De-bug - Technicians 1 2
49Changing a Resource's Availability
- Click on TOOLS
- select CHANGING WORKING TIME
- in the FOR box select the desired resource
- For example Technician 2 is on vacation the week
of Labor Day - change him to Not Working that week
Does this impact the schedule?
50Technician 2 on vacation
Set as non-working time
51Project Finish Delayed until 9/30/98
52Vacation Impacts Move the Computers Task will
now cross the weekend --- 7.7 days Actual Work is
still 4.5 days
53Review Planned Resource Usage
- Click on View
- Click on Resource Usage
- or Click on Resource Usage Icon on left side of
screen
54Resource Usage
Week of August 23, 1998
Thursday - Get started moving computers
36 work hours required 2 people x 4.5 days
55Technician 1 finished 36 hours Stops working!
Technician 2 on Vacation
56Week of September 13, 1998
Technician 2 continues to Move Computers until
his 36 hours on that task is complete. Technician
1 is not assigned.
57Modifying the Schedule
Microsoft Project Assumes that once the workload
is assigned (work hours per task) that the
resources must do their work even if it means
delaying the project. However, if the situation
allows, the schedule can be modified by altering
a resources work hours on a task. Assume we want
Technician 1 to keep helping Technician 2 until
Moving Computers is completed. Total Work
Hours required 4.5 days x 8 hrs x 2 Techs. 72
hours Solution Through Friday, 9/4/98 each Tech
was scheduled to work 10.4 hours on
this task for a total of 20.8 hours. During
the week of 9/7/98, Tech 1 is scheduled for 25.6
hours (1.6 on Friday) giving 46.4 total hours
worked leaving (72 - 46.4 25.6 ) Tech 1 is
given 6.4 to fill out his 9/4/98 day. This
leaves 19.2 hours left on the task. The 19.2
hours is split in half for the week of 9/13/98.
Tech 1s total hours 10.425.66.49.6
52.0 Tech 2 will be scheduled for 10.49.6 20
hours
58Revised Week of 9/6/98
Note 8 hours
Enter New Work Hours
59Revised Week of 9/13/98
Tech 1 now Moves Computers this week
Note Move Computers can finish Tuesday AM
60Move Computer Elapsed Time Drops from 7.7 days to
6.5 days --- Project Finishes 9/25/98
61Assume Todays Date is 8/30/98Current Status
- All sub-tasks under Remove Existing Computers are
100 complete - The Old Carpet has been removed - 100
- The room is 25 painted
- Electrical Conduit (Finished 8/29/98) enter
actual finish date
62Tracking the Projects Progress
- Click on Tracking Gantt
- Select Tools
- Select Tracking
- Select Update Project
63Current Date
Selected Tasks
64Update Percentage Completion
Task is 100 Complete
65Gantt Chart Automatically Updated
Task 100 Completed
66All tasks for Removing Existing Computers
Completed
Progress on Remodel
67Create Desired Columns - Include Actual Finish
Electrical Work Finished 8/29/98
68Examining Task Costs
- Click on VIEW
- Click on Gantt Chart
- choose TABLE
- choose COST
- scroll right or drag divider bar to see Total Cost
See the next page for the Project Cost Table
69Project Cost Table
Could Enter Budget - Baseline Cost
70Project Cost Summary
See the next page for an example
Also FILE SUMMARY INFORMATION STATISTICS
71Summary Table View
72Viewing Costs by Resource
- View
- Resource Usage
- View
- Tables - Cost
73Cost Analysis by Resource Type
74Lets Look at Some Reports