1
SRIPADASAGAR PROJECT (YELLAMPALLY
PROJECT) AYACUT MAP
2
(No Transcript)
3
(No Transcript)
4
(No Transcript)
5
SRIPADA SAGAR PROJECT
PKG No. Description Awarded Bid Amount Rs. in Crs.
1 Construction of Sripada Sagar Project acress Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt. (Stage-I) SCANSKA Cementation Ltd. 408.85
2 Excavation of approach channel Construction of pump house, Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations, Pressure mains Supply and layers of pipelines from Barrage to NTPC Balancing Reservoir. M/s.Subhash Projects Marketing(P) Ltd. 98.92
3 Stage-II, Phase-I of Sripada Sagar Project- supply, installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) M/s. IVRCL-SEW- Navayuga (JV) 1737
TOTAL TOTAL 2244.77
6
SRIPADASAGAR L. I. SCHEME
1 Project Profile Project Profile Construction of Sri Padasagar Project across river Godavari (St-I) Ph-I Supply of 8.5 TMC of water to NTPC (St-I, Ph-II) Lifting 12 TMC to irrigate 2 Lakh Acres (St-II, Ph-I)
2 Administrative Sanction Administrative Sanction G. O. Ms. No. 71, I CAD (PW) GVI, Dt 16-7-2004 for Rs. 900 Crores
3 No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos. No. of EPC Packages 3 Nos.
4 Agt. Value of 3 Pkgs Rs. 2244.77Crs.
5 Budget Provision for 2006-07 (For GWUA) Budget Provision for 2006-07 (For GWUA) Rs. 1240 Crs.
6 Expenditure of the Project
2004-05 2004-05 Rs. 20.44 Crs.
2005-06 2005-06 Rs. 202.07 Crs.
TOTAL Rs. 222.51 Crs.
7 Utilisation ( Stg-I, Ph-I, Ph-II Stg-II,Ph-I) Utilisation ( Stg-I, Ph-I, Ph-II Stg-II,Ph-I) 20.5 TMC
Ultimate 180.50 TMC
8 Ayacut New Ayacut 2,00,000 acres
7
SRIPADASAGAR L. I. SCHEME
9 Lift-I Lift Height 96 M
No. of Pumps 4 Nos.
Total pumps capacity 10.8 MW
10 Lift-II
Lift Height 120 M
No. of Pumps 4 Nos.
Total pumps capacity 13 MW

11 Lift-III Lift Height 80 M
No. of Pumps 4 Nos.
Total pumps capacity 5,25 MW x 2, 8.26 MW x 2

12 Lift-IV
Lift Height 50 M
No. of Pumps 2 Nos.
Total pumps capacity 0.50 MW
13 Power required (Stg-I, Ph-II) water supply to NTPC Power required (Stg-I, Ph-II) water supply to NTPC 9 MW
14 Power required (Stg-II, Ph-I) Irrigation 2L Acs Power required (Stg-II, Ph-I) Irrigation 2L Acs 137 MW
8
SRIPADASAGAR L. I. SCHEME
15 Land Acquisition
Required 15,981 acres
Acquired 430 acres
Requisitioned 15,981 acres
16 Est. Cost for LA Rs. 222.00 Crores
17 Est. Cost for R R Rs. 500.00 Crores
18 Mobilisation Advance Paid Recovered
2004-05 Rs. 20.44 Crs.
2005-06 Rs.106.05 Crs. 3.31 Crs.
Total Rs. 126.49 Crs. 3.31 Crs.
19 Target date for completion 10/2007
9
SRIPADASAGAR PROJECT
Name of the Contractor ITD Cementation India
Ltd. Agreement Amount Rs. 408.85Crs. Agreement
Date 07-11-2004/17-2-2005 Period of
Completion 36 Months(10 milestones) Date of
completion 06-11-2008
Package No. 1 (Stg-I Ph-I) Construction of
Sripada Sagar Project across Godavari river at
Yellampally (V), Ramagundam(M), Karimnagar Dt. to
store 20 TMC at FRL 148M.
  • Survey work Completed
  • Designs Alignment of barrage - FINALISED
  • Earth bunds approved by CE/CDO
  • Spillway under approval in CE/CDO
  • Execution
  • Drilling of exploratory bore holes
  • in river for spill way earth bund Completed
  • Excavation of Cutoff trenches for
  • right side left side earthen
  • bunds Completed
  • Exc. of Cutoff trenches for spillway In
    progress
  • Qty. of Earthwork done 2.43 L Cum against
    3.062 L Cum.
  • Expenditure Rs. 63.59 Crores. (including Mob.
    Advance Rs.36.04Crs.)
    against Rs. 408.85 Crores.
  • Land Acquisition Required 8745 Acres
    Acquired225 Acres Requisitioned 8456
    Acs.

10
SRIPADASAGAR PROJECT

Water Supply to NTPC
Name of the Contractor M/s.Subhash Projects
Marketing(P) Ltd. Agreement Amount Rs.
98.92 Crs. Agreement Date 07-04-2005 Period of
Completion 18 Months (6 milestones) Date of
completion 06-10-2006
  • Package No.2 (Stg-I Ph-II)
  • Excavation of approach channel
  • Construction of pump house
  • Supply and commissioning of pumping machinery to
    lift 8.5 TMC, Transformers, sub-stations
  • Pressure mains
  • Supply and laying of pipelines to NTPC Reservoir
  • Survey work Completed
  • Designs Designs for pressure mains submitted
    to CE/CDO are under scrutiny
  • Designs for pump houses, pumps etc. to be
    submitted by Agency
  • Designs of pipelines Yet to be furnished by
    the Agency.
  • Execution Fabrication Unit erected at site
    for manufacture of pipes
  • Alignment of pressure mains, location

  • of approach channel and intake well under
    approval by CE/CDO
  • Expenditure Rs.12.48Crs. (incl. Mob. Adv.)
    against Rs.98.92Crs.
  • Land acquisition Required 70 Acres,

11
SRIPADASAGAR PROJECT (Stg-I, Ph-II)

Water Supply to NTPC

1 Expenditure
2005-06 Works Rs. 7.53 Crs.
Mob. Adv. Rs.4.95 Crs.
Total Rs. 12.48 Crs.
2 Land Acquisition
Total Required 55 acres
Acquired Nil
Requisitioned 15 Acres
3 Utilization 8.5 TMC
4 Lift-I Lift-I
Lift Height 50 M
No. of Pumps 4
Total pumps capacity 3300 HPs.
5 Power required Power required Power required 9 MW
12
SRIPADASAGAR PROJECT STAGE-II, PHASE-I
(Irrigation)
SALIENT FEATURES SALIENT FEATURES
1 PROJECT PROFILE Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.) Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.)
2 Admn. Sanction G. O. Ms. No. 149, I CAD, Dt 16-8-2005 for Rs. 1688.86 Crores
3 Expenditure
2005-06 Rs.146.44 Crs.
4 Land Acquisition
Total Required 15,000 acres
Acquired Nil
Requisitioned 407 Acres
13
SRIPADASAGAR PROJECT STAGE-II, PHASE-I
5 Forest Land Forest Land 285 Acres
6 Utilisation 12 TMC
7 Ayacut New Ayacut 2 Lakhs acres
Stabilisation
8 Lift-I
Lift Height 96 M
No. of Pumps 4 Nos.
Total pumps capacity 10.8 MW
9 Lift-II
Lift Height 120 M
No. of Pumps 4 Nos.
Total pumps capacity 13 MW
10 Lift-III
Lift Height 80 M
No. of Pumps 4 Nos.
Total pumps capacity 5,25 MW x 2, 8.26 MW x 2
14
SRIPADASAGAR PROJECT STAGE-II, PHASE-I
11 Lift-IV
Lift Height 50 M
No. of Pumps 2 Nos.
Total pumps capacity 0.50 MW
12 Power required Power required 137 MW
13 Mobilisation Advance 2005-06 Mobilisation Advance 2005-06 Paid Recovered
Rs. 85.50Crs Rs. 3.31Crs.
15
SRIPADASAGAR PROJECT
Package No.3 Stage-II, Phase-I of Sripada Sagar
Project- supply, installation and commissioning
of pumping machinery, transformers, sub-stations,
pressure mains including construction of pump
house all civil structures to irrigate 2.00 Lakh
acres in upland areas of Karimnagar (Dist.)
Name of the Contractor M/s. IVRCL-SEW-
Navayuga (JV) Agreement Amount Rs.
1737Crs. Agreement Date 03-04-2005 Period of
Completion 30 Months(10 milestones) Date of
completion 02-10-2007
  • Utilization 12 TMC (Lifting)
  • Power Required 137 MW
  • Investigation Pressure mains completed
  • Pump house gravity canal under progress
  • Designs Designs of pressure mains and
    alignment submitted to CE/CDO for approval
  • Mobilization Advance paid 85.50 Crores
  • Mob. Advance recovered Rs. 3.31 Crs.
  • Land Acquisition Required 2000 Acres
    Requisitioned 437 Acres.
  • (Rs. 5.00 Crores deposited with Revenue
    Authorities)