Title: Monitoring and Information Systems
1Monitoring and Information Systems
- Project monitoring defined
- The plan-monitor-control cycle
- Designing the monitoring system
- Behavioral aspects of monitoring
- Earned value analysis
- Earned value examples
2Project Monitoring Defined
- Collecting, recording, and reporting information
concerning any and all aspects of project
performance that the project manager or others
wish to know
3Effective Monitoring Precedes Control
- In Chapter 11, well look at Project Control
- Ensuring that actuals mesh with the plan
- But effective control requires good information
- Such pertinent and timely information comes from
an accurate monitoring system
4Monitoring Has Several Uses
- Project Monitoring has secondary uses
- Project auditing
- Lessons learned
- Reporting to client and senior management
- But the primary use is project control
- Ensuring that decision-makers have timely
information enabling effective control over the
project
5The Planning-Monitoring-Controlling Cycle
- Effective monitoring and control begins with good
project planning - What are the critical areas?
- How and when can progress be measured?
- Who gathers and reports info, to whom?
- The plan-monitor-control cycle continues through
the entire project
6Project Control Information Flow, Figure 10-1
7Designing the Monitoring System
- 1. Start with the key factors to be controlled
- Pareto analysis a relatively few activities
determine most of the projects success - Use the project plan to identify items to be
monitored - Although other areas might be added also
8Designing the Monitoring System (contd)
- 2. Develop measurement systems
- Measure results, not activity outputs, rather
than inputs - Extract performance, time and cost goals from
project plans - Avoid tendency to focus on that which is easily
measurable
9Designing the Monitoring System (contd)
- 3. Collecting Data Most data falls into one of
five categories, as follows (with examples) - Frequency counts tally of occurrences . . .
- Raw numbers dates, dollars, percents, specs .
. . - Subjective ratings numerical ranking,
red-yellow-green assessments . . . - Indicators surrogate measures of merit . . .
- Verbal measurement oral or written
characterizations . . .
10Designing the Monitoring System (contd)
- 4. Reporting on Data Collected To turn data
into information, it must be contextualized - Reporting must be timely
- Data must be analyzed
- Trends Getting better or worse?
- Comparables Performance compared to specs, past
performance, standard hours, etc. - Statistical analysis
- Causation and correction
11Reporting and Information Flows, Figure 10-5
12Some Behavioral Aspects of Monitoring Systems
- Effective monitoring reduces surprises, and this
can increase trust, morale - Some reporting bias is inevitable, but dishonesty
is unacceptable - Shooting the messenger today just creates
concealment tomorrow
13Earned Value Analysis (EVA)
- Needed An objective way to measure overall
project performance - The problem comparing actual expenditures to
baseline plan is that it ignores the amount of
work actually completed - Thus, Earned Value Analysis
- A sort of cost accounting for projects
14Five Important Terms
- BCWS The plan, integrating schedule and budget
- BCWP What you planned to spend for work
actually done - ACWP Actual dollars spent at a point in time,
for the work actually done - STWP Time scheduled for work performed
- ATWP Actual time for work performed
15More Terms
- BAC Budget at completion
- EAC Estimated cost at completion
- ETC Estimated cost to complete
16Five Relationships
- Cost Variance (CV) BCWP - ACWP
- Schedule Variance (SV) BCWP - BCWS
- Time Variance (TV) STWP - ATWP
- Estimated Cost to Complete (ETC) (BAC
BCWP)/CPI - Estimate Cost at Completion (EAC) ACWP ETC
17Indices Help Visualize Performance
- Projects on cost, on schedule will have indices
1.0 - Indices below 1.0 are unfavorable
- Cost Performance Index (CPI) BCWP/ACWP
- Schedule Performance Index (SPI) BCWP/BCWS
- Cost-Schedule Index (CSI) CPI X SPI
18Possible Arrangements, Figure 10-8
19Example
- Assume a work package expected to be finished
today, at cost of 1500. But youre only 2/3
complete, and youve spent 1350. - CPI BCWP/ACWP 1000/1350 .74
- SPI BCWP/BCWS 1000/1500 .67
- CSI CPI/SPI .74 X .67 .49
20Example (contd)
- Then you can calculate the estimated cost to
complete the project (ETC) and the estimated cost
at completion (EAC) - ETC (BAC BCWP)/CPI (1500
1000)/.74 676 - EAC ACWP ETC 1350 676
2026
21Another Earned Value Example
- A 10-day project, today is day 7
Activity Predecessor Duration(Days) Budget() Actual Cost(s) Complete
a - 3 600 680 100
b a 2 300 270 100
c a 5 800 80
d b 4 400 25
e c 2 400 0
22PERT AON Diagram, Figure 10-9
23Example Baseline Budget Using 50-50 Rule, Figure
10-10
24Example Status at Day 7, Figure 10-11
25Example Earned Value Chart Day 7, Figure 10-12
26MSP Budget Sheet, Figure10-13
27Case Earned Value at Texas Instruments
28Case Earned Value at Texas Instruments (contd)
- Graphic presentation clearly depicts projects
history - More crucial, though, is using EVA as a
management tool. This requires - Timely, accurate data collection
- Expeditious data analysis
- Appropriate and efficient corrective action