Title: The Replanting of Lochaber Hydro Power Station
1 - The Replanting of Lochaber Hydro Power Station
by Andrew Thick
2Topics to be covered today
- Scheme modelling
- Operating capability of Lochaber
- Turbine selection
- Penstock works.
3Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
4Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
5Spey Dam
6Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
7Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
8Laggan Dam
9Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
10Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
11Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
12Loch Treig and Dam
13Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
14Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
15Schematic of the Lochaber Scheme
Gravity Inflows
Surge Chamber
Gravity Inflows
Spill
Spill
Spill
tunnel
Power-house
tunnel
tunnel
Tailrace
Penstocks
Loch Laggan reservoir
Spey reservoir
Loch Treig
Loch Linnhe
16Penstocks, Powerhouse and Smelter
17Simplified Lochaber Scheme Model
Gravity Intake Flows are combined with Reservoir
Inflows
Qintakes
Qintakes
QLin
QLspill
QTin
QTspill
QLin
QTunnel
QLin
QP/H
QTin
Treig
Laggan
18Energy Modelling Results
Trial 1 2 3 4 5 6 7
Installed Cap. (MW) 65 80 60 70 80 90 100
Overall Efficiency () 75 87 87 87 87 87 87
Headloss Coeff. (k) 0.021 0.0172 0.0172 0.0172 0.0172 0.0172 0.0172
Operating rule Ext Ext Max E Max E Max E Max E Max E
Laggan Spill (mcm) 2,034 1,794 4,160 1,709 1,227 1,074 801
Treig Spill (mcm) 154 121 857 201 54 10 7
Ave. Energy (GWh/yr) 467 569 523 574 581 583 580
19Scheme Operating Capability Diagram
Average Operation
9.3 Q
90.7 Q
No Gravity Inflows
0 Q
100 Q
Max. Gravity Inflows
100 Q
0 Q
20Operating Capability in terms of Loch Treig Level
Note 90.7 of water from Loch Treig9.3 of
water from gravity intakes
21Scheme Operating Capability Diagram
Average Operation
9.3 Q
90.7 Q
No Gravity Inflows
0 Q
100 Q
Max. Gravity Inflows
100 Q
0 Q
22Operating Capability in terms of Surge Shaft
Water Level
Note 90.7 of water from Loch Treig9.3 of
water from gravity intakes
Penstock Limitation
23Scheme Operating Capability Diagram
Average Operation
9.3 Q
90.7 Q
No Gravity Inflows
0 Q
100 Q
Max. Gravity Inflows
100 Q
0 Q
24Operating Capability in terms of Surge Shaft
Water Level
Note All water from Loch Treig
25Scheme Operating Capability Diagram
Average Operation
9.3 Q
90.7 Q
No Gravity Inflows
0 Q
100 Q
Max. Gravity Inflows
100 Q
0 Q
26Operating Capability in terms of Surge Shaft
Water Level
Note All water from gravity intakes
27Scheme Operating Capability Diagram
Average Operation
9.3 Q
90.7 Q
No Gravity Inflows
0 Q
100 Q
Max. Gravity Inflows
100 Q
0 Q
28Example Operation exceeding Penstock Pressure
Rise Limit
29Turbine Selection
- The steps towards to turbine selection were
- Analysis of historical data of scheme operation
- The number of generating units was selected 5
- Analysis of operating data from scheme model
- Performance data from tendering suppliers was
fed into the scheme model
30Scheme Operation Frequency Plot
31Turbine Selection
- The steps towards to turbine selection were
- Analysis of historical data of scheme operation
- The number of generating units was selected 5
- Analysis of operating data from scheme model
- Performance data from tendering suppliers was
fed into the scheme model
32(No Transcript)
33Turbine Selection
- The steps towards to turbine selection were
- Analysis of historical data of scheme operation
- The number of generating units was selected 5
- Analysis of operating data from scheme model
- Performance data from tendering suppliers was
fed into the scheme model
34(No Transcript)
35Turbine Selection
- The steps towards to turbine selection were
- Analysis of historical data of scheme operation
- The number of generating units was selected 5
- Analysis of operating data from scheme model
- Performance data from tendering suppliers was
fed into the scheme model
36(No Transcript)
37Penstock works
- Key aspects of the penstock works were
- Need to undertake the works minimising shutdown
of generation. - Existing penstock system was very complex.
- In order to maintain double isolation, the
penstocks needed to be dewatered sequentially. - The works were complex with poor access.
- Decision with RTA to laser scan the penstock
system and create a 3-D model.
38Multiple buspipes
Numerous Valves
Bifurcations
39Penstock Area difficult terrain!
40Penstock works
- Key aspects of the penstock works were
- Need to undertake the works minimising shutdown
of generation. - Existing penstock system was very complex.
- In order to maintain double isolation for the
penstocks needed to be dewatered sequentially. - The works were complex with poor access.
- Decision with RTA to laser scan the penstock
system and create a 3-D model.
41Survey Point Cloud Data
42AutoCAD 3-D Model
43Project Summary
- The generating plant has been replaced to give
25 years life extension. - The water to wire efficiency has been improved
from 75 to 90. - Energy production increased from 460 GWh/yr to
600 GWh/yr. - The schemes capability is better understood and
limitations identified. - The scheme was completed ahead of schedule and
is operating successfully with minimal disruption
to Smelter operations during construction
44(No Transcript)
45Contact Details
Thank you for your kind attention
- Andrew Thick BEng CEng MIMechE
- URS Infrastructure and Environment UK Limited
- International House, Dover Place
- Ashford
- Kent TN23 1HU
- United Kingdom
- Tel 44 (0) 1233 658200
- hydropower_at_urs.com