Title: Collaborative Procurement
1Collaborative Procurement
- Dr Neil Crundwell
- Consultant Radiologist ESHT
2Collaborative Procurement
- Why
- How
- Lesions learnt
- Implementation
- Immediate and distant futures
3Why
- Why did we need a new PACS
- Legacy system (AGFA). Contract due to expire mid
2012. - Initial local enquiries suggested refreshing
system very expensive.
4Local drivers
- Contract ends in 2012- need to progress
procurement activities - Image Sharing needs linked with BSUH/WSHT for
Trauma and MDT - Community access to images post merger?
- GP Access to Images?
- Refine storage procurement installation
responsibilities
5Why
- Why did others need a new PACS
- LSP contract due to end mid 2013
- At time very unclear how future provision would
be co-ordinated. - Series of meetings arranged by local HIS late
2010, early 2011 to assess awareness of impending
end of service and plans deal with this.
6Possible Procurements
- Individual within CFH Framework, NHS Supply
Chain, own procurement process - Collaborative Sussex procurement for joint
supplier PACS, RIS and/or VNA (archive) - Collaborative Sussex procurement within the CfH
framework with options to choose individual or
joint supplier for PACS, RIS and/or VNA (archive) - BSUH and/or WSHT extend current contracts with
CSC individually not a confirmed option at time
7Why
- Local PACS community highlighted a collaborative
approach as the desired way forward - Joint approach involving ESHT, BUSH, and WSHT for
procurement of PACS/RIS/VNA
8Perceived Benefits
- Cost Efficient shared resource/expertise
- Sharing of key outputs e.g. OBS, OBC,FBC
- Procurement buying power
- Compliments future proof technology plans
- Robust governance and use of existing networks
- Common standards enabling ease of service
transfer and image sharing.
9How
- February 2011 HIS Board agreed to set up a
programme for a Pan Sussex PACS / RIS - May 2011 Strategic Executive Group approved
programme but requested case for collaboration
submitted and approved August 2011 - Stakeholder engagement by Programme lead in May
Trusts keen to explore possible areas of
collaboration on procurement and organised
meetings to explore options - remembering that
ESHT needed to progress their procurement.
10How- possible procurement routes
- Option 1 OJEU notice for a framework service,
with ESHT as contracting authority and WSHT BSUH
as participating authorities - Outcome A single service provider however
individual trusts have their own contract with
the service provider. - Pros Greatest flexibility and collaboration,
shared procurement costs, common OBS, doesnt
preclude local configuration, single set of
evaluation criteria, single contract, all
participants can pull out at any time, no
sanctions for not signing a contract, trusts can
still engage with suppliers independently? - Cons If ESHT pull out then the whole process
closes, if BSUH or WSHT drop out then lose
economies of scale - Competitive Dialogue or Restricted Procedure
11How- possible procurement routes
- Option 2 ESHT, BSUH and WSHT publish joint
notice for PACS RIS Service - Outcome A single service provider however
individual trusts have their own contract with
the service provider. - Pros Shared procurement costs, common OBS,
doesnt preclude local configuration, single set
of evaluation criteria - Cons Complicated way of doing a framework. If
one trust pulls out then the whole process closes
12How- possible procurement routes
- Option 3ESHT contractual organisation and sells
on services under SLA to WSHT and BSUH - Outcome A single service provider however
individual trusts have service agreement with
ESHT for services. - Pros Difficult to define any but done as a needs
must e.g. Community Systems for ESHT from SCT. - Cons Complicated and requires much greater level
of collaboration.
13How
- Option one chosen with ESHT as Trust to issue
OJEU notice. - Competitive dialogue
14Governance
Sponsoring SRO Programme Manager Business Users
Consultant Radiologist Radiology
Service Manager PACS Manager GP
Commissioner Advisory Finance
PACS/RIS Expert Community SHA Lead
PACS/RIS (Project team when relevant) Business
Suppliers Technical Infrastructure
Current LSP Supplier New PACS/RIS Supplier
Sussex Executive Group
SHA, SPfIT CfH
Sussex IMT Programme Board
PACS/RIS Programme Board
CSUG-Clinical Service User Group for Southern
Cluster
Main Projects in the Programme
Options/Business Case
Procurement
Surrey Sussex PACS/RIS Local Network Groups
ESHT
Implementation
BSUH
WSHT
Other Partners
15How
- Queen Victoria Hospital East Grinstead joined
August 2011 - East Surrey Hospitals joined September 2011
16Procurement Strategy
- The Procurement strategy was based upon best
practice as described in POISE and under EC
Directives. Due to the expected whole life time
costs of the project the procurement was via an
OJEU notice. - The specific procedure selected was competitive
dialogue as this route allowed the Trust to work
with suppliers during the evaluation phase and
jointly understand and finalise the
specification. This route is recommended for new
innovative systems or where the solution will be
bespoke. - The Collaborative used an external procurement
specialist to assist and advise.
17Who
-
- Radiologists / Radiographers
- PACS managers
- Service managers
- Trust and Network IM T
- Trust procurement staff
- IG
- Representation from Community and acute trusts
- (other specialities)
18Assistance
- Central Project manager funded through HIS
- Independent PACS expert for outline and full
business cases and OBS - Independent procurement advice for OJEU/PQQ,
documentation and assessment sessions and
competitive dialogue - Independent legal advice as required
19Procurement Process
- Outline business case for each trust approved Oct
2011 - Procurement project established and OEJU notice
published November 2011 by ESHT on behalf of
multiple Trusts. - Initial assessment against financial criteria and
if actually supplying a PACS system - PQQ assessment and long list to 8
- ITPD published early Jan 2012.
- Product demonstrations by each bidder and
evaluation workshop against criteria to reduce
shortlist of 3 Jan 2012 -
20Procurement Process
- 1st competitive dialogue sessions February 2012
- Reference Site visits February 2012
- Product demonstrations (open invite) March 2012
- 2nd competitive dialogue sessions March 2012
- Final evaluation and preferred bidder May 2012
21Complications
- East Surrey left collaborative after Sectra
(their current provider) left the procedure
although selected for the 8 long list - Royal Surrey County and Ashford and St Peters
joined in March 2012
22Procurement Process
- Preferred bidder agreed May 2012
- Philips as prime contractor Philips PACS, HSS
RIS and Acuo VNA - Full business case approval May- June 2012
- Implementation Sept 2012 July 2013.
23Key Contract Clauses
- Service Agreement main points
- One supplier contact for the service 5 year fully
managed service revenue and therefore VAT
recoverable - Option to extend to 10 years at same price
- No implementation costs from Supplier
- No double running costs
- Based on volumes of studies with 10 compound
increase - Performance 99.99 uptime with lt2s image
retrieval local, lt6s VNA - No software licensing therefore unlimited use of
applications
24Benefits of joint procurement
- Shared procurement costs saved each Trust in the
region of 65,000 compared to estimated single
cost. - Previous LSP trusts made a 35 saving on cost of
managed service. - Increased cost for managed service at ESHT from
120k to 490k but no further hardware costs
-320k in 2011 alone.
25What is against a collaborative approach
- Increased complexity particularly around
organisation of meeting / events - Tensions with group
- Different expectations of outcome
- Different desired outcomes
- Personalities and local politics
- Remembering you are not a consortium!
26Long term Benefits
- Difference between outcome and benefit
- Measures to assess benefit
- So what?
27Potential benefits
- Improved patient care and experience
- Improver referrer experience
- Improved efficiency and quality
- Cash releasing
- Cash generating
28Expected long term outcome and benefit
- Outcome Fully Managed PACS RIS VNA Service
- Benefit Continued ability to deliver patient
care beyond March/June 2013
29Potential outcomes and benefits
- Outcome Redesigned workflow utilizing new
functionality to be able to track abnormal
results and ensure action taken by referring
clinician. - Benefit Improved Patient Safety, Reduced
Litigation
30Potential outcomes
- Multidisciplinary Diagnosis Team processes
redesigned to utilise new functionality - Provision of instantaneous reformatting of images
by consultants including 5 years online data. - Images instantly available from referring
organisation in collaboration - Store other images on the VNA eg
gastroenterology, pathology
31Potential outcomes
- Electronic Requesting
- Joint Booking System
- Joint reporting (Voice recognition reporting)
- Joint Radiologists On-Call
- Interfacing with other specialities eg regional
neurosurgery and Cardiology - Remote Working
32Summary
- It takes much longer than you think initial
discussions to full implementation late 2010 to
mid 2013 - Robust project management essential
- Clarity and precision around OBS
- Use expert resources and learn from others
- Procurement in a box
33- Contact neil.crundwell_at_esht.nhs.uk