Title: ABC Implementation Status
1ABC Implementation Status
2- Accomplished
- Established internal ABC Core Team (field and
central office representatives, budget, finance,
performance) - Brought in Contractor with ABC experience
- Adapted existing coding scheme (account string)
to improve alignment with ABC - Ground-truthed resulting activity coding with
field operations. - Internal Activities and Outputs developed
- Conducted presentations for leadership
- Distribution of ABC video and CD training
materials - Crosswalk completed
- Extract files being sent to DOI (Calibre)
3- On-going
- Integrating/coordinating Key metrics, Non-key
metrics, PART metrics, Outputs, and Activities - Developing additional ABC training to be included
with performance training for new Strategic Plan
and Operational Plans - Further re-alignment of existing coding
methodologies - Develop methodology for internal auditing (late
2004) - Assessment of methodology that is best fit for
entering time and attendance (mid 2004-2005) - Presentations to leadership
4Realignment of Existing Coding
- NPS has coded activities for over 30 years.
- The Primary Work Element (PWE) field contains NPS
Activity Information. - Currently, a budget source code is embedded in
the field containing Activity information. This
code forces permutations just like the DOI's
combination of activity and goal strategy coding. - Many of the existing codes are artifacts from
management initiatives over the past 30 years and
are being cleaned up. Over 270 PWEs eliminated
for 2004. - During 2004, a coding scheme that separates the
Activity code from the budget code will be
explored and implemented if possible.
5Construction and Grants
- Problems being worked out with coding of
Construction and Grants. - NPS currently has nearly 20 Activity codes that
are aligned on 3 funding sources related to
"Construction" funding. None of the codes
designate "why" the money is being spent. - DOI's coding scheme provides 28 different
Activity codes (15 maintenance, 13 construction)
that NPS Construction would need to be spread. - NPS begins about 130 "Construction" projects
annually carrying total costs of 200-300
million. - There are about 450 Multi-year projects in any
one year.
6FY 2004 Proposed Solution
- NPS plans to send FFS journal info to DOI on a
daily basis with no DOI Activity Code for
Construction and Grants. - This will cause an "exception" in the Caliber
system. - NPS will hand tool a quarterly report of
Construction and Grants costs that will minus out
the "exception" dollars and re-submit them as
totals and include the appropriate DOI Activity. - This way provides the daily extract using the
standardized extract script so that daily costs
can be traced while providing for a remapping of
dollars on a quarterly basis to the actual DOI
Activities that the Construction projects and
Grants contribute.
7FY 2004 Proposed Solution
FFS Extract File Transactions coded with direct
construction project PWEs will have a blank DOI
activity code
DOI Calibre system Unassigned cost X Unassign
ed cost -X DOI Activity X DOI Activity
X DOI Activity X
Net to zero
Periodic manual process to be automated Determine
direct construction project cost by DOI activity
using the following mapping IWPN gt FFS PWE Job
gt DOI activity
A construction project may relate to more than 1
DOI activity. NPS will trace to the best fit
Activity. Multiple job numbers in FFS for the
same project may facilitate mapping to more than
1 activity.
8- NPS will explore necessary changes to the scripts
that produce the extract files to automate the
tracing of a given Construction Project to a
specific DOI Activity code. - Grants will be handled in a similar fashion.
- Other Construction issues not resolved. Most
significantly, the dollar value forwarded for
capital projects.
9Problems Recommendations
- The justification for having the ABC model hard
coded in the accounting system was to eliminate
allocations. There is a perception that only
transactions entered into the accounting system
can be counted on to provide a tracing of dollars
to Activities and outputs. - However, the 11 rule forces an arbitrary
allocation of dollars. - In a service organization, there are few
activities that contribute to only one output and
few outputs that contribute to only one outcome.
Yet, our ABC infrastructure builds in an
automatic allocation of dollars to goals. The
effect of the allocation is hidden because the
allocation is forced to occur outside of the
process. It cannot be audited and the Bureaus
will not be able to reconcile their more accurate
dollar to goal models with the Department's. - Eliminate the rule.
10Problems Recommendations
- We are trying to code 3 or more perspectives into
the Activity code. For example - Activity Function
Strategy - how what
why - data coll. IT mgt.
PEO 1 - This makes the ABC system burdensome, inflexible,
and difficult to maintain. It creates a situation
that forces permutations across the 16
Mission-related Strategies this permutation
effect is why we chose ignore important
Activities such as those in the IT field, Safety,
Law Enforcement, and many others. - Eliminate function and strategy from the Activity
templates.
11Problems Recommendations
- We do not apply a standard definition for what an
Activity or Output is. - We created Activities that are supersets of
groups of Activities so that the term now
reflects functions and programs. - Consequently, certain Activities are included in
many such supersets so that a singular activity
(i.e. data collection) does not represent how
much that Activity actually costs. - While this "higher use" concept simplified the
rapidly growing number of Activities, it obscures
what Activities are actually performed and their
costs. - Adopt the industry-standard definitions
associated with ABC.
12Problems Recommendations
- There is a tension is between creating Activities
that are useful at the Department level and those
that are useful to the field managers in the
bureaus. - The perception that the Department can have
meaningful Department-wide, mission-related
Activities endures though the bureau missions
differ significantly as does the purpose for
which they apply an Activity. - Consequently, we tried to create Activities that
were both meaningful to the bureaus and were
Department-wide. The approach was to roll up many
of the bureau-specific Activities to a more
general Activity. We ended up creating many
Activities that do not have measurable outputs. - We proved that you can't have a top-down and a
bottom-up ABC effort. The Department must choose
one direction or the other.
13Problems Recommendations
- Placing all of our Activity codes into the
accounting systems makes the ABC system
burdensome, inflexible, and difficult to
maintain. - We are creating problems for the accounting
systems they were not designed to deal with. The
accounts should not be changing from year to
year, however, from the ABC perspective, the
codes will need to be flexible enough to change
on a regular basis to accommodate political
initiatives such as that of the Secretary or an
OMB request that we connect ABC to PART. - Because the Activity model is hard coded in the
accounting systems, we will see a continuing
shifting of accounts to accommodate initiatives. - Get the model out of the General Ledger.
14Problems Recommendations
- Currently, our accounting systems are aligned to
our budget structures which are aligned to the
appropriation process. Our account codes and our
accounting methodologies support the budget
formulation process. - Accounting systems (business and government) are
intended to demonstrate fiduciary responsibility
and are primarily for an audience outside the
organization. - Managerial cost accounting systems are meant to
provide managers a functional view of costs so
that efficiency can be managed. - Merging the two together adversely impacts the
functionality of both the new system will be
less useful for making budget decisions and
managing performance. In addition, it will
highlight situations were appropriations are
being spent in a manner not planned for (i.e.
initiatives). - Separate the Activity codes from the accounting
systems.
15Problems Recommendations
- The great concern expressed regarding the
validity of allocations and the unbounded faith
in the veracity of accounting system transactions
skews our perception of traceability and
accountability. This then requires us to ignore
the standard COTS ABC applications used by
business and nearly every other Federal
organization. - We are now building an expensive cost management
application that will place a significant
financial burden on the bureaus and will provide
little value to the field managers. - Standard ABC applications will allow each
organization within the Department to demonstrate
accountability, cost efficiencies and cost
effectiveness in terms that directly relate to
their missions and the jobs they perform. - Adopt a commercial off-the-shelf ABC application
suitable for government organizations.