CASE STUDY - PowerPoint PPT Presentation

1 / 1
About This Presentation
Title:

CASE STUDY

Description:

There is a potential to shift more earth if truck numbers are adjusted to ensure excavators can continue at optimum output. If truck numbers had been increased, ... – PowerPoint PPT presentation

Number of Views:6
Avg rating:3.0/5.0
Slides: 2
Provided by: JaneSun
Category:
Tags: case | study | excavators

less

Transcript and Presenter's Notes

Title: CASE STUDY


1
DELIVERING LEAN INTERVENTION
  • CASE STUDY HIGHWAYS AGENCY A46 Widmerpool to
    Newark
  • HEADLINE
  • Lean intervention was undertaken on the A46
    project which identified future savings of
    between 0.88m and 7.73m for an investment of
    18k.
  • THE CHALLENGE
  • CWC were engaged by the Highways Agency to
    undertake a Lean Intervention on the A46
    Project. The project was a large design and
    build road widening project with a value of
    340m.
  • The main criteria were to ensure that the design
    was compatible with site activities , that no
    construction work was done without signed off
    design and to achieve maximum output in dry
    weather for earthworks.
  • THE APPROACH
  • A Steering Group and Core Improvement Team (CIT)
    was set up with members from CWC, The Highways
    Agency, Balfour Beattie, Scott Wilson and John
    Jones.
  • High level process mapping was undertaken by the
    CIT for Design and Earthworks.
  • Complexity of steps and potential bottlenecks
    were identified.
  • Workshops and brainstorming sessions were held
    to discuss issues.
  • Drawings status were established, tracked and
    compared with the construction programme
  •  
  • OUTCOME AND SAVINGS
  • It was identified that the design programme was
    not known to the site team. Collaborative
    planning would improve the sequencing of
    drawings, minimise rework on site and improve
    communication.
  • Excavator utilisation was identified as a key
    indicator of utilisation and performance. A major
    cause of downtime was insufficient trucks for
    excavators resulting in them being left idle.
    There is a potential to shift more earth if truck
    numbers are adjusted to ensure excavators can
    continue at optimum output.
  • If truck numbers had been increased, the same
    amount of earth could have been moved in less
    days resulting in a saving of 9 days and between
    70262 and 616262 depending on the amount of
    earthworks on the critical path.
  •  
  • FUTURE SAVINGS
  • For the remaining programme, if Truck
    Optimisation is undertaken, 113 days will be
    saved with potential savings of between 0.88m
    and 7.73m for an investment of 18k.
  • Excavator utilisation varied over days measured.
    Improved utilisation will reveal further
    savings. 
  • Addressing causes of delays in dumper truck will
    result in both time and financial savings.
  • Truck movement recording system tracked by GPS,
    and automatic data collection will reduce the
    need for data collection and manual manipulation
    of data.
  • THE DELIVERY TEAM
  • CWC team included Joe Dowling, Tony Ives and
    Emily Mitchell. 
Write a Comment
User Comments (0)
About PowerShow.com