Title: Tertiary Oil Recovery Project Advisory Board Meeting
1Tertiary Oil Recovery Project Advisory Board
Meeting
- CO2 Project Field Activities
University of Kansas Burge Union October 19,
2001 Rich Pancake
2CO2 Project Field Activities
- CO2 1 Well Work
- Colliver 7 Well Work
- Planned Colliver 10 Well Work
- Preliminary CO2 Facilities Design
- Arbuckle Efforts
- Ethanol Plant Construction
3Colliver 7
CO2 1
Colliver 10
Courtesy of the Kansas Geological Survey
4CO2 1 Well Work
- Drilled Well Sept. Oct. 2000
- Discussed at last years Board Meeting
- Ran CBL October 2000
- Excellent bond
- TOC 1590
- Completed Well Dec. 2000 Jan. 2001
- Perfed well 2891-99
- No stimulation
- IPd at 0.83 BOPD 82 BWPD
- Stabilized at 0.8 BOPD 39 BWPD
5CO2 1 Well Work
- Pump Stuck Jan. Feb. 2001
- Pump scaled up 2 weeks after putting on
- Reran, stabilized at 0.2 BOPD 8.5 BWPD
- Build-up Test 1 April 2001
- Wanted to determine LKC C kh skin
- Conducted 91-hour build-up test using Echometer
(4/12 to 4/16) - Well remained SI, measured static FLs 5/11,
5/24, 6/8, 6/27 (1825 hrs SI) - 809 psia reservoir pressure
- Difficult well to interpret
- tight matrix rock (2 md), no skin
6TORPs remote fired Echometer gun used for the
1st build-up test on CO2 1
7TORPs Echometer equipment and laptop used for
the 1st build-up test on CO2 1
8CO2 1 Well Work
- Acidized Well July 2001
- Attempted to use PPI tool tool malfunctioned
- 1st acid job, slow matrix stimulation
- Occurred as a result of failed PPI tool
- 400 gals 15 NE
- Surface pressure did not exceed 200 psig
- 0.2 BPM rate
- 2nd acid job, slow matrix stimulation
- 1000 gals 15 NE
- Surface pressure did not exceed 200 psig
- 0.5 BPM rate
- Prod. stabilized at /- 6 BOPD /- 110 BWPD
9X-pert Service Tools PPI Tool (Pin Point
Injection) being RIH prior to CO2 1 acid job
10Oilmans Acid, Inc. on location for CO2 1 acid job
11CO2 1 Well Work
- Build-up Test 2 Aug. Sept. 2001
- Wanted to verify LKC C kh skin
- Conducted 237-hour build-up test using Echometer
(8/30 to 9/9) - Well remained SI, measured static FLs 9/14,
9/21, 9/28, 10/11 (1001 hrs SI) - /- 800 psia reservoir pressure
- Still difficult well to interpret
- Non-radial flow
- Multiple layer
- no skin
12Comparison of Build-up Tests
13TORPs Echometer setup used for the 2nd build-up
test on CO2 1
14Colliver 7 Well Work
- Ran Tracer Survey September 2001
- Needed to determine if a cement plug between LKC
C G held - (whether C G communicating)
- First had to knock out a CIBP separating LKC from
upper zones - Set packer and tubing at 7 casing shoe (2893)
- Ran tracer survey
15Colliver 7 Well configuration as of 1989
16Colliver 7 Current Well Configuration (2001)
17Colliver 7 Current Well Configuration
(2001) Showing Lansing Stratigraphy
18Colliver 7 Well Work
- Ran Tracer Survey September 2001
- Needed to determine if a cement plug between LKC
C G held - (whether C G communicating)
- First had to knock out a CIBP separating LKC from
upper zones - Set packer and tubing at 7 casing shoe (2893)
- Ran tracer survey
- LKC A B did not communicate w/ C
- LKC G did not communicate w/ C
19The Rosel Company on location to run Colliver 7
tracer survey
20Rosel Company technician fills survey tool with
tracer material
21Colliver 7 Well Work
- Pressure Transient Test October 2001
- Wanted to determine LKC C kh
- Tried to conduct both a build-up and fall-off
test by injecting water into well - Laid injection line from Colliver 10
- Needed clean injection water, installed tandem
inline filters of 25 10 microns - Had packer set at 7 csg shoe (2893)
- Ran bottom hole pressure bomb on slickline to
mid-hole (2899)
22Colliver 7 Well Work
- Pressure Transient Testing October 2001
- Injected 450 BWPD for 48 hours, no pressure at
surface - SI well for 96 hours
- Pulled pressure bomb, tool had malfunctioned,
only recovered build-up data (first 47 hours) - 604 psia reservoir pressure
- Build-up data was interpretable
- Reservoir appears to have linear flow
- Matrix rock kh appears to be 308 md ft
- More interpretation needs to be done
23Injection line ran from Colliver 10 to Colliver 7
24Inline filters installed at Colliver 7
25Planned Colliver 10 Well Work
- Clean out junk fill
- Has plastic pipe and fill in hole
- Hope to clean out to mid-point of LKC C G
(2925) - Check for communication between C G
- C G received small frac job in 1960
- Set packer near casing shoe
- Run tracer survey, check for near wellbore
communication between C G - Perform remedial work if necessary
- Need to isolate G from C
- May cement squeeze entire LKC
26Colliver A-10W Before Workover
27Colliver A-10W After Workover
28Colliver A-10W After Workover Depicting the
Lansing Stratigraphy
29Preliminary CO2 Facilities Design
- Preliminary Study June 2001
- Production Facilities
- Murfin hired River City Engineering for study
- Study objectives
- Develop high level design and cost estimate for
new CO2 production facilities - Investigate instrumentation and control options
- Manual control vs. basic automation
- Major design criteria
- Peak production 85 BOPD, 850 BWPD, 420 MCFD
- CTB operating pressure between 25 100 psig
- 5 to 10 year material life with emphasis on
chemical treatment for protection, vessels
internally coated
30River City Engineerings preliminary production
facilities design for CO2 Project
31Preliminary CO2 Facilities Design
- Preliminary Study June 2001
- Control Options
- Manual control/Local operations
- Information gathered by operator making rounds
(strip charts, pressure gauges) - Regulators and mechanical linkages used
- Advantage
- Simple, little to no special training required
- Cheap, least expensive option
- Disadvantage
- Requires human intervention to collect relay
data - May provide less accurate data
- No alarm features, no record of what caused
shut-ins
32Preliminary CO2 Facilities Design
- Preliminary Study June 2001
- Control Options
- Basic automation
- Metering and other critical data (pressures, tank
levels) tied into a PLC - PLC or PC trending and archiving of data
- Possible remote access
- Advantage
- Continuous logging of data
- Alarm capabilities
- Setpoints can be change on fly, no shut-down
required - Disadvantage
- Cost, more expensive than manual control
- Requires special training to operate maintain
33Preliminary CO2 Facilities Design
- Preliminary Study June 2001
- Production Facilities Cost
- Manual control option
- 236,500 (/- 30)
- Basic automation option
- 296,500 (/-30)
- 60 M incremental for automation
34Preliminary CO2 Facilities Design
- CO2 Supply Options January 2001
- CO2 from ethanol plant, 1.0 MMCFD
- Low-pressure pipeline (8.5 miles) 1.17/MCF
- High-pressure pipeline 1.28/MCF
- Liquefaction trucking 1.80/MCF
- CO2 from ethanol plant, 3.5 MMCFD
- Low-pressure pipeline (8.5 miles) 0.71/MCF
- High-pressure pipeline 0.67/MCF
35Arbuckle Efforts
- Sampled Bemis-Shutts Wells January 2001
- Collected oil gas samples from low-pressure
region of Arbuckle - Gas collected from annulus, oil collected using
miniature gun-barrel - Sampled 4 Vess and 8 Murfin wells
- Gas contained /- 60 N2, little CH4 (/- 3)
- Oil composition still being analyzed by CORE Lab
- Recombined Sample June 2001
- Collected oil gas sample from Murfins Peavy
B-1 to be used for PVT analysis and a
recombination MMP
36Courtesy of the Kansas Geological Survey
37(No Transcript)
38Arbuckle annular gas collected by Precision
Wireline
39Miniature gun-barrel used to collect Arbuckle oil
sample
40Miniature gun-barrel courtesy of John O. Farmer,
Inc.
41(No Transcript)
42Ethanol Plant Construction
- Start-up November 2001
- CO2 available Spring 2002
- ICM negotiating w/ FloCO2 of Midland, TX to build
and operate liquefaction equipment at the ethanol
plant - ICM exploring food-grade CO2 market
- Most likely scenario has liquefied CO2 being
trucked and stored at the CO2 pilot site
43Ethanol Plant Construction, Russell, KS
44Ethanol Plant Construction, Russell, KS