Title: CON MINE CLOSURE
1- CON MINE CLOSURE RECLAMATION PLAN OVERVIEW
- February 22nd, 2007
2- Current Status of the Closure Reclamation Plan
- All sections of the plan (with the exception of
the reclamation cost estimate) have been reviewed
by the Con Mine AR Working Group set up by the
MVLWB in 2003 - The Working Group has met 20 times over the
past 4 years to discuss technical details of the
proposed reclamation plan for the Con Mine site - The Working Group provided recommendations on
each section of the Plan that led to Miramar
revising each section prior to submission to the
MVLWB
3- Status of the Con Mine Closure Reclamation Plan
- Three public information sessions (open house
style) were held in 2005/06 to present the
content of each Section to the public and to
elicit feedback - In December of 2006 the MVLWB completed their
review of all sections of the Reclamation Plan
(except the reclamation cost estimate) - The Board has given conditional approval to each
section indicating what changes were needed to
satisfy the MVLWB. - Miramar has revised the Plan to incorporate these
changes and formally re-submitted the Plan to the
MVLWB at the end of January 2007 for final Board
approval
4- Status of the Con Mine Closure Reclamation Plan
- The MVLWB Board staff have indicated that this
revised version of the Plan will be sent to the
Working Group for one final review to confirm
that the Boards conditions have been met this
meeting. - Once the Plan is approved, Miramar will implement
the Plan starting in 2007, with most physical
reclamation work completed by the end of 2009.
Water treatment and post closure monitoring and
maintenance will continue at least through 2031. - Leased land held by Miramar can be returned to
the GNWT starting in 2007.
5- Status of the Reclamation Cost Estimate
- Miramar submitted a revised reclamation cost
estimate to the MVLWB in December of 2007. - Revised cost estimate is 12.5 million, not
including work completed through 2006. - 60 of this cost is direct physical reclamation
while 40 is for ongoing water treatment and post
closure monitoring and maintenance. - MVLWB has asked INAC to review this cost estimate
and provide the Board advice regarding any
revision to reclamation security levels.
6- Status of the Reclamation Cost Estimate
- Miramar currently has 10.0 million in security
set aside for reclamation of the Con Mine - 9.0 million in an environmental trust set aside
for reclamation from the sale of the Bluefish
hydro facility pledged to INAC under the Water
License - 1.0 million in a second trust set aside for
reclamation from the sale of the Bluefish hydro
facility - Miramar estimates that it will spend an
additional 4 million on final reclamation in
2007. Consequently by the end of 2007, the amount
held in two reclamation trusts will exceed the
remaining estimated reclamation liability - Final clean up and treatment of the remaining
arsenic sludges through the autoclave is
scheduled for completion by September of 2007
leading the way for mill demolition in late 2007
early 2008.
7- Structure of the Con Mine Closure Reclamation
Plan - Table of Contents
- Introduction and History
- Site Infrastructure and Facilities
- Underground Workings
- Rat Lake
- Con Pond and Negus Pond
- Tailing Containment Areas (TCAs)
- Contaminated Soils
- Water Management
- Closure and Post Closure Site Monitoring
- Cost Summary and Schedule
8- Public Information Session 1 - Held - June
15th, 2005 - Sections Covered
- Introduction and History
- Site Infrastructure and Facilities
- Underground Workings
- Rat Lake
-
- Public Information Session 2 -Held October
26th, 2005 - Sections Covered
- Con Pond and Negus Pond
- Tailing Containment Areas (TCAs)
- Historic Areas
- Recently Active Areas (Upper and Middle Pud)
- Public Information - Session 3 - Held March
16th, 2006 - Sections Covered
- Contaminated Soils
- Water Management
9- The key reclamation objective is to return the
minesite to a viable, and wherever practicable,
self-sustaining ecosystem - End land use objective is a mix of land suitable
for industrial use mixed with open space - Areas not impacted by mining could be used for
other purposes pending appropriate setbacks - There will be three sites designated as hazardous
sites (Con and Negus Ponds and the hazardous
materials storage site) that will be capped and
thus not available for future land use
10- Specific Reclamation Objectives
- Progressive Reclamation activities started in
2002 - Mill area to be reclaimed to a standard suitable
for future industrial land use - Similarly the Shops/Office/Roads/Parking areas to
be reclaimed to industrial land use standard - Historic Tailing Areas to be drained, contoured
and revegetated 35 hectares - Upper and Middle Pud TCAs to be covered with 50
to 60 cm of rock and vegetated 50 hectares
11- Section 1 - Introduction
- History and Reclamation Objectives
- No Comments received from MVLWB and the Working
Group.
12- Section 2 - Infrastructure and Facilities
- All buildings on Site are to be removed, with
potentially 3 exceptions - Masonic Lodge
- One private residence
- Recreation Hall
- Exceptions subject to approval of the land owner
(GNWT) - copies of letters from these 3
interested parties have been submitted to Water
Board. - A procedure has been added that deals with the
assessment of concrete foundations for
contaminants. - A procedure covering the removal of the timber
and concrete crib at the boiler house at the Con
dock has been added (Section 2.7). This procedure
references DFO guidance to monitor the work to
protect fish and commits to obtaining DFO
approval of the detailed work plan prior to
proceeding.
13Mill Complex July 2005
Mill complex at present.
14Mill Complex 2008 Projection
Mill complex removed - 2008
15- Section 3 - Underground
- Mining ceased September 2003. Monitoring of
water level and quality in mine has been carried
out twice since then. - In 2006, a procedure was developed to monitor
minewater (level and quality) on an annual basis.
This procedure is set out in detail in Sections
8 and 9. Initially the minewater will be
monitored at a minimum frequency of once each
year, with the results reported to MVLWB and
INAC. Information will be made public. - In the summer of 2006 water was measured to at
the 4700 foot level. At current flooding rates
water is expected to equalize near surface in
2014. - Capping of shafts and raises in progress.
16- Section 4 - Rat Lake
- The majority of the Rat Lake sediments were
evaluated in 2003. - A further 2,000 cubic meters were removed in
2005. - The Rat Lake Work Plan that detailed what was
done and what results were obtained to the end of
2005, has been submitted to the MVLWB (January
2007). - The last 100 cubic meters of contaminated
material was removed in September 2006 and the
tests results from that work are pending (report
to be submitted to the MVLWB in March 2007). - The Reference to the YASRC is added.
- MCML has included in the Plan commitments 10,16
and 17. Section 4.1 and 4.2.
17- Section 5 - Con and Negus Ponds
- Arsenic sludges have been removed and stockpiled
in the Blend Plant for treatment in the
Autoclave. The Autoclave will be commissioned in
April 2007 and remain in service until all of the
arsenic sludges have been treated. - Con Pond has been cleaned and power washed to
recover the remaining arsenic sludges. - Cleaning of the Negus Pond will be completed in
2007. As the gravel and boulders are removed,
they will be washed and the wash water will go to
the Autoclave as feed for the treatment of the
arsenic sludges. Any gravel or boulders that
have total arsenic over 340 mg/kg on the surface
of the rock will be placed in the hazardous waste
disposal site for permanent care and storage.
18- Section 5 - Con and Negus Ponds
- The cleaned areas will be graded to direct
surface runoff to the Middle Pud TCA - Low permeability engineered cover has been
designed for these two ponds with the objective
of reducing infiltration to lt 2. - Cover will include a Geosynthetic Clay Liner (low
permeability liner) which has a clay core. As
such, it is expected to have a long life (100
years) as compared to synthetic liners (plastic /
HDPE). - The water quality of groundwater down gradient of
the capped ponds will be assessed by monitoring
wells.
19- Section 5 - Con and Negus Ponds
- The GCL liner will be capped with a coarse gravel
/ cobble material that is both physically and
chemically stable. As set out in Section 5.3.1,
the gravel will be tested to confirm that the
upper layer will have arsenic levels less than
340 mg/kg of total arsenic. - If needed, a quarry would be developed north of
the water treatment plant to provide cover
material. The quarry would be closed in a manner
consistent with the Closure guidelines
established by INAC for open pits or quarries
(end of Section 5.3.1). - A large boulder barrier will be constructed and
maintained to prevent inadvertent access to these
areas by motorized vehicles.
20Con Pond July 2005
Con Pond in center of photograph
21Con Pond at Closure in 2008
Con Pond with rock cover at closure
22Negus Pond July 2005
23Negus Pond at Closure in 2008
Negus Pond with rock cover. Large rock barrier
not shown for clarity.
24Calcine Storage Area July 2005
- Calcine storage area cleaned out for waste
storage
25Hazardous Waste Storage Site September 2008
- Rock cap on hazardous waste storage site. Mill
complex is removed from area at bottom of photo.
26Hazardous Waste Site Cap Design
- Cover System for Hazardous Waste Disposal Site
and Hazardous Waste Sites
27- Section 6 - Tailing Containment Areas (TCAs)
Historic and Recently Active - Historic Negus, Neil Lake, Lower Pud Lake and
Crank Lake TCAs will be drained, contoured and
revegetated. - Recently Active Upper Pud and Middle Pud TCAs
will be capped with a minimum 50 to 60 cm layer
of broken rock and then seeded and fertilized.
Soil will be imported to create islands on the
surface of the TCA to enhance the rate and
success of vegetation establishment on the rock.
28- Section 6 - Tailing Containment Areas (TCAs)
Historic and Recently Active - A section has been added to the Closure Plan to
detail how vegetation success will be measured
and what criteria will be used to determine when
additional contingent measures are needed. - Section 6.5.1. sets out a series of contingency
plans that describe additional measures that will
be taken by MCML if the vegetation cover is not
successful within 4 to 5 years.
29- Section 6 - Tailing Containment Areas (TCAs)
Historic and Recently
Active - The details for the engineered cover to be placed
on the Upper and Middle Pud TCA have been
included in Section 6.5.1. - The details outline the initial modeling used to
check the design and present the material
specifications that will needed to achieve the
target infiltration (lt 7) for the cover. - A test pad was developed in 2005 and is being
monitored for physical stability. It was seeded
at that time and is being used to evaluate
vegetation success on the rockfill. Further
studies are planned in 2007 to confirm the
modeling used in the design. - With the exception of rock outcrops, the surface
area will be vegetated. Fertilizer will be added
and the area over-seeded for the first several
years to enhance success.
30Neil Lake July 2005
31Neil Lake 2010 Projection
- Neil Lake as revegetated in 2008, Kam Lake in
background. Note Water Treatment Plant still in
place.
32Upper Pud - July 2005
33Upper Pud - July 2010 Projection
- Upper Pud, capped with waste rock and gravel.
- Note vegetation starting to show.
34Upper Pud 2015 Projection
- Vegetation cover now established on Upper Pud TCA
35Cover Test Pad on Upper PudJune 2006
36Test Pad for Vegetation on Mine Rock Cover
37- Section 7
- Contaminated Soils
- Minesite has been impacted by 65 years of mining
- Areas of impact have been identified
- Site has been divided into 4 zones to facilitate
closure and reclamation. - The Zones are
- Zone 1 - Blend Plant/Negus Pond, Con Pond,
Hazardous Waste Disposal Site - Zone 2 Tailing Areas Upper Pud, Middle Pud,
Lower Pud, Neil Lake, Negus Tailing, and Crank
Lake - Zone 3 Main mine lease with mill area,
Robertson headframe, and area around tailing
areas to north, west and south - Zone 4 Rat Lake, Tin Can Hill, Con Camp and
Dock, and Mosher Island.
38- Section 7
- Contaminated Soils
- Closure plan for Zone 1 is discussed in Section
5. - Closure plan for Zone 2 is discussed in Section
6. - Closure plan for Zones 3 and 4 are discussed
here. - The closure plan for Zone 3 is considered in 2
parts. - Area 1. Mill and headframe buildings will be
removed. Impacted soil will be placed in the
hazardous waste disposal site or the
non-hazardous waste site as determined by
testing. Area will be reclaimed to the NWT
industrial use standard. - Area 2. Soil in the areas to the north, west and
south of Zone 2 (active tailing basins) will be
tested. Site specific plans to close these areas
will be developed based on the results of
testing.
39- Section 7
- Contaminated Soils
- The closure plan for Zone 4 (Rat Lake, Tin Can
Hill and Con Dock) started with testing of soil
at 8 sites identified as having arsenic
contaminated soil. In addition to arsenic, all
metals on the GNWT contaminated sites list were
included in the testing program. - If any metal on the list is exceeded and
determined not to be naturally occurring, then
the sites will be evaluated to determine if clean
up is necessary. Data to date suggests, once the
arsenic contaminated soils are removed or cleaned
up, the other metals of concern are removed. - The test results indicated that arsenic at 5 of
the sites is naturally occurring mineralization
not a result of mining. The others sites will
be further investigated. - The rest of Zone 4 was inspected and no other
contaminated sites were identified. If
additional sites are found in the next 4 years, a
site specific closure plan will be developed for
each area.
40- Section 7
- Contaminated Soils
- In 2007, sites away from the main mine area
mill and Robertson Headframe - will be tested to
confirm the extent and type of arsenic that may
be present in the soil. - Water that collects in the excavations at the
mill will be directed to construction sumps in
the excavation area. These sumps will be pumped
and the water directed to the Middle Pud TCA. - Section 7.4 details the plan to clean up the mill
site and clean the depressions in the rock
surface once the mill is removed.
41- Section 8
- Water Management
- Since the early 1980s surface water on site has
been collected and directed to the Middle Pud TCA
and then to the Water Treatment Plant. - Water treated at the plant, and at nine sampling
stations around the site, has been monitored
under the Water License since the early 1980s. - Regulatory limits for these contaminants are set
out in the Water License and in federal MMER
regulations. These will continue to be applied
following Closure and will apply to minewater
once it nears the surface. If the limits are
exceeded, the minewater would be pumped to the
Middle Pud TCA for treatment.
42Map of Current SNP Sites
43- Section 8
- Water Management
- Engineered structures control site surface
drainage. The Closure Plan provides further
improvement to the system. - Offsite flows not directed to Middle Pud are
minimal and have not been in contact with
impacted areas. - These flows are currently monitored by the
Surveillance Network Program (SNP) under the NWT
Water License. - Rat Lake clean up is complete and a final report
will be submitted in March 2007. The report
includes the results of the speciation tests. -
44- Section 8
- Water Management
- The Closure Plan creates additional surface water
monitoring stations and will monitor the quality
of the minewater as it approaches the surface. - Six groundwater monitoring wells have been
installed and several more are included in the
Closure Plan, including 2 deep wells adjacent to
mine workings. - Monitoring at these additional stations will
continue and be required under future Water
Licenses.
45- Section 8
- Water Management
- Minewater and mine flooding.
- URS sampled underground minewater in 2004
- MCML sampled underground minewater in 2006.
- Mine flooded to 4700 Level as of September 2006.
- Minewater is expected to reach surface in late
2014, thus Con Mine will take 11 years to flood. - Water quality testing indicates minewater is
relatively clean Zinc is only parameter above
Water License limit. - Closure Plan calls for installation of access
points in the concrete caps at Robertson Shaft,
C-1 Shaft, and 204Q Stope to allow for
installation of pumps should it be necessary to
pump and treat the minewater when it reaches
surface.
46- Section 9
- Closure and Post-Closure Monitoring
- Monitoring of the site is detailed in Section 9.1
and includes geotechnical inspections of the
tailing dams, closed hazardous sites, and water
management facilities. The cost estimate
(Section 10) anticipates that environmental
monitoring would continue for 50 years, but the
frequency of inspections would be reduced over
time. - Post-Closure monitoring is anticipated to
continue unchanged for at least 25 years, or
until water quality satisfies the Water License
discharge limits and water treatment can be
discontinued. The MMER and EEM programs would
also continue to apply during that period.
47- Section 9
- Closure and Post-Closure Monitoring
- The annual geotechnical inspection of the
minesite includes the chemical and physical
stability of the TCAs, plus all dams, dykes and
drainage channels. - The inspection will be expanded to include caps
on the openings to surface, and the results of
groundwater monitoring. - A report of each inspection, and a plan outlining
any required action, would be sent to the MVLWB,
the INAC Inspector, and Environment Canada.
48- Section 9
- Closure and Post-Closure Monitoring
- Federal Environmental Effects Monitoring (EEM)
has been in effect since June 2002. - Numerous parameters, including 36 metals, are
routinely monitored. - Post-Closure monitoring includes EEM and this
will continue at least for the next 6 to 9 years. - Other than arsenic, EEM has not detected any
other metals at levels of concern. - In addition to contaminants, EEM monitors the
environmental effects of treated effluent on the
receiving water, including fish and other biota.
49- Section 10 Cost Summary Schedule
- Submitted to MVLWB in December 2006
- Remaining closure costs estimated at 12.5
million
50- 2007 Planned Reclamation
- Complete treatment of all remaining arsenic
sludges. - Decommission and start to remove Blend Plant
structure. - Begin dismantling and removal of remaining
surface structures, including mill complex and
headframes. - Perform cycle 3 of minewater sampling
- Install remaining groundwater wells.
51- 2008 Planned Reclamation
- Complete demolition and removal of remaining
surface structures. - Begin reclamation of Upper Pud TCA.
- Cap 204Q stope opening.
- Cap Robertson / C-1 Shaft openings.
- Perform cycle 4 of minewater sampling.
- Begin reclamation of Middle Pud TCA.
- Continue closure monitoring.
52- 2009 Planned Reclamation
- Complete reclamation of Upper Pud TCA.
- Continue reclamation of Middle Pud TCA.
- Perform cycle 5 of minewater sampling.
- Complete any remaining tasks.
- Commence Post-Closure monitoring.
53- 2010 Planned Reclamation
- Complete reclamation of Middle Pud TCA.
- Over seed and fertilize revegetated areas.
- Perform cycle 6 of minewater sampling.
- Complete any remaining tasks.
- Continue Post-Closure monitoring.
54- Status of Con Mine Water License
- Current license expires on January 30th 2008
- Miramar will ask that the Water License be
renewed to cover the period from January 2008
thru December 2014 i.e. thru the 4 year
physical reclamation period and into the start of
the post closure monitoring period. - The renewed license will allow for reclamation,
ongoing water treatment and post closure
monitoring and maintenance (no further mining or
milling). - This license period will allow the reclaimed site
conditions to become stable. Subsequent Water
Licenses will address the long term monitoring
and maintenance requirements. - Miramar will submit the application in 2007 once
the Closure Plan has been approved. -
55