CON MINE CLOSURE - PowerPoint PPT Presentation

1 / 55
About This Presentation
Title:

CON MINE CLOSURE

Description:

All sections of the plan (with the exception of the reclamation cost ... Calcine storage area cleaned out' for waste storage. Calcine Storage Area July 2005 ... – PowerPoint PPT presentation

Number of Views:299
Avg rating:3.0/5.0
Slides: 56
Provided by: nicole140
Category:
Tags: closure | con | mine | calcine

less

Transcript and Presenter's Notes

Title: CON MINE CLOSURE


1
  • CON MINE CLOSURE RECLAMATION PLAN OVERVIEW
  • February 22nd, 2007

2
  • Current Status of the Closure Reclamation Plan
  • All sections of the plan (with the exception of
    the reclamation cost estimate) have been reviewed
    by the Con Mine AR Working Group set up by the
    MVLWB in 2003
  • The Working Group has met 20 times over the
    past 4 years to discuss technical details of the
    proposed reclamation plan for the Con Mine site
  • The Working Group provided recommendations on
    each section of the Plan that led to Miramar
    revising each section prior to submission to the
    MVLWB

3
  • Status of the Con Mine Closure Reclamation Plan
  • Three public information sessions (open house
    style) were held in 2005/06 to present the
    content of each Section to the public and to
    elicit feedback
  • In December of 2006 the MVLWB completed their
    review of all sections of the Reclamation Plan
    (except the reclamation cost estimate)
  • The Board has given conditional approval to each
    section indicating what changes were needed to
    satisfy the MVLWB.
  • Miramar has revised the Plan to incorporate these
    changes and formally re-submitted the Plan to the
    MVLWB at the end of January 2007 for final Board
    approval

4
  • Status of the Con Mine Closure Reclamation Plan
  • The MVLWB Board staff have indicated that this
    revised version of the Plan will be sent to the
    Working Group for one final review to confirm
    that the Boards conditions have been met this
    meeting.
  • Once the Plan is approved, Miramar will implement
    the Plan starting in 2007, with most physical
    reclamation work completed by the end of 2009.
    Water treatment and post closure monitoring and
    maintenance will continue at least through 2031.
  • Leased land held by Miramar can be returned to
    the GNWT starting in 2007.

5
  • Status of the Reclamation Cost Estimate
  • Miramar submitted a revised reclamation cost
    estimate to the MVLWB in December of 2007.
  • Revised cost estimate is 12.5 million, not
    including work completed through 2006.
  • 60 of this cost is direct physical reclamation
    while 40 is for ongoing water treatment and post
    closure monitoring and maintenance.
  • MVLWB has asked INAC to review this cost estimate
    and provide the Board advice regarding any
    revision to reclamation security levels.

6
  • Status of the Reclamation Cost Estimate
  • Miramar currently has 10.0 million in security
    set aside for reclamation of the Con Mine
  • 9.0 million in an environmental trust set aside
    for reclamation from the sale of the Bluefish
    hydro facility pledged to INAC under the Water
    License
  • 1.0 million in a second trust set aside for
    reclamation from the sale of the Bluefish hydro
    facility
  • Miramar estimates that it will spend an
    additional 4 million on final reclamation in
    2007. Consequently by the end of 2007, the amount
    held in two reclamation trusts will exceed the
    remaining estimated reclamation liability
  • Final clean up and treatment of the remaining
    arsenic sludges through the autoclave is
    scheduled for completion by September of 2007
    leading the way for mill demolition in late 2007
    early 2008.

7
  • Structure of the Con Mine Closure Reclamation
    Plan
  • Table of Contents
  • Introduction and History
  • Site Infrastructure and Facilities
  • Underground Workings
  • Rat Lake
  • Con Pond and Negus Pond
  • Tailing Containment Areas (TCAs)
  • Contaminated Soils
  • Water Management
  • Closure and Post Closure Site Monitoring
  • Cost Summary and Schedule

8
  • Public Information Session 1 - Held - June
    15th, 2005
  • Sections Covered
  • Introduction and History
  • Site Infrastructure and Facilities
  • Underground Workings
  • Rat Lake
  • Public Information Session 2 -Held October
    26th, 2005
  • Sections Covered
  • Con Pond and Negus Pond
  • Tailing Containment Areas (TCAs)
  • Historic Areas
  • Recently Active Areas (Upper and Middle Pud)
  • Public Information - Session 3 - Held March
    16th, 2006
  • Sections Covered
  • Contaminated Soils
  • Water Management

9
  • The key reclamation objective is to return the
    minesite to a viable, and wherever practicable,
    self-sustaining ecosystem
  • End land use objective is a mix of land suitable
    for industrial use mixed with open space
  • Areas not impacted by mining could be used for
    other purposes pending appropriate setbacks
  • There will be three sites designated as hazardous
    sites (Con and Negus Ponds and the hazardous
    materials storage site) that will be capped and
    thus not available for future land use

10
  • Specific Reclamation Objectives
  • Progressive Reclamation activities started in
    2002
  • Mill area to be reclaimed to a standard suitable
    for future industrial land use
  • Similarly the Shops/Office/Roads/Parking areas to
    be reclaimed to industrial land use standard
  • Historic Tailing Areas to be drained, contoured
    and revegetated 35 hectares
  • Upper and Middle Pud TCAs to be covered with 50
    to 60 cm of rock and vegetated 50 hectares

11
  • Section 1 - Introduction
  • History and Reclamation Objectives
  • No Comments received from MVLWB and the Working
    Group.

12
  • Section 2 - Infrastructure and Facilities
  • All buildings on Site are to be removed, with
    potentially 3 exceptions
  • Masonic Lodge
  • One private residence
  • Recreation Hall
  • Exceptions subject to approval of the land owner
    (GNWT) - copies of letters from these 3
    interested parties have been submitted to Water
    Board.
  • A procedure has been added that deals with the
    assessment of concrete foundations for
    contaminants.
  • A procedure covering the removal of the timber
    and concrete crib at the boiler house at the Con
    dock has been added (Section 2.7). This procedure
    references DFO guidance to monitor the work to
    protect fish and commits to obtaining DFO
    approval of the detailed work plan prior to
    proceeding.

13
Mill Complex July 2005
Mill complex at present.
14
Mill Complex 2008 Projection
Mill complex removed - 2008
15
  • Section 3 - Underground
  • Mining ceased September 2003. Monitoring of
    water level and quality in mine has been carried
    out twice since then.
  • In 2006, a procedure was developed to monitor
    minewater (level and quality) on an annual basis.
    This procedure is set out in detail in Sections
    8 and 9. Initially the minewater will be
    monitored at a minimum frequency of once each
    year, with the results reported to MVLWB and
    INAC. Information will be made public.
  • In the summer of 2006 water was measured to at
    the 4700 foot level. At current flooding rates
    water is expected to equalize near surface in
    2014.
  • Capping of shafts and raises in progress.

16
  • Section 4 - Rat Lake
  • The majority of the Rat Lake sediments were
    evaluated in 2003.
  • A further 2,000 cubic meters were removed in
    2005.
  • The Rat Lake Work Plan that detailed what was
    done and what results were obtained to the end of
    2005, has been submitted to the MVLWB (January
    2007).
  • The last 100 cubic meters of contaminated
    material was removed in September 2006 and the
    tests results from that work are pending (report
    to be submitted to the MVLWB in March 2007).
  • The Reference to the YASRC is added.
  • MCML has included in the Plan commitments 10,16
    and 17. Section 4.1 and 4.2.

17
  • Section 5 - Con and Negus Ponds
  • Arsenic sludges have been removed and stockpiled
    in the Blend Plant for treatment in the
    Autoclave. The Autoclave will be commissioned in
    April 2007 and remain in service until all of the
    arsenic sludges have been treated.
  • Con Pond has been cleaned and power washed to
    recover the remaining arsenic sludges.
  • Cleaning of the Negus Pond will be completed in
    2007. As the gravel and boulders are removed,
    they will be washed and the wash water will go to
    the Autoclave as feed for the treatment of the
    arsenic sludges. Any gravel or boulders that
    have total arsenic over 340 mg/kg on the surface
    of the rock will be placed in the hazardous waste
    disposal site for permanent care and storage.

18
  • Section 5 - Con and Negus Ponds
  • The cleaned areas will be graded to direct
    surface runoff to the Middle Pud TCA
  • Low permeability engineered cover has been
    designed for these two ponds with the objective
    of reducing infiltration to lt 2.
  • Cover will include a Geosynthetic Clay Liner (low
    permeability liner) which has a clay core. As
    such, it is expected to have a long life (100
    years) as compared to synthetic liners (plastic /
    HDPE).
  • The water quality of groundwater down gradient of
    the capped ponds will be assessed by monitoring
    wells.

19
  • Section 5 - Con and Negus Ponds
  • The GCL liner will be capped with a coarse gravel
    / cobble material that is both physically and
    chemically stable. As set out in Section 5.3.1,
    the gravel will be tested to confirm that the
    upper layer will have arsenic levels less than
    340 mg/kg of total arsenic.
  • If needed, a quarry would be developed north of
    the water treatment plant to provide cover
    material. The quarry would be closed in a manner
    consistent with the Closure guidelines
    established by INAC for open pits or quarries
    (end of Section 5.3.1).
  • A large boulder barrier will be constructed and
    maintained to prevent inadvertent access to these
    areas by motorized vehicles.

20
Con Pond July 2005
Con Pond in center of photograph
21
Con Pond at Closure in 2008
Con Pond with rock cover at closure
22
Negus Pond July 2005
23
Negus Pond at Closure in 2008
Negus Pond with rock cover. Large rock barrier
not shown for clarity.
24
Calcine Storage Area July 2005
  • Calcine storage area cleaned out for waste
    storage

25
Hazardous Waste Storage Site September 2008
  • Rock cap on hazardous waste storage site. Mill
    complex is removed from area at bottom of photo.

26
Hazardous Waste Site Cap Design
  • Cover System for Hazardous Waste Disposal Site
    and Hazardous Waste Sites

27
  • Section 6 - Tailing Containment Areas (TCAs)
    Historic and Recently Active
  • Historic Negus, Neil Lake, Lower Pud Lake and
    Crank Lake TCAs will be drained, contoured and
    revegetated.
  • Recently Active Upper Pud and Middle Pud TCAs
    will be capped with a minimum 50 to 60 cm layer
    of broken rock and then seeded and fertilized.
    Soil will be imported to create islands on the
    surface of the TCA to enhance the rate and
    success of vegetation establishment on the rock.

28
  • Section 6 - Tailing Containment Areas (TCAs)
    Historic and Recently Active
  • A section has been added to the Closure Plan to
    detail how vegetation success will be measured
    and what criteria will be used to determine when
    additional contingent measures are needed.
  • Section 6.5.1. sets out a series of contingency
    plans that describe additional measures that will
    be taken by MCML if the vegetation cover is not
    successful within 4 to 5 years.

29
  • Section 6 - Tailing Containment Areas (TCAs)
    Historic and Recently
    Active
  • The details for the engineered cover to be placed
    on the Upper and Middle Pud TCA have been
    included in Section 6.5.1.
  • The details outline the initial modeling used to
    check the design and present the material
    specifications that will needed to achieve the
    target infiltration (lt 7) for the cover.
  • A test pad was developed in 2005 and is being
    monitored for physical stability. It was seeded
    at that time and is being used to evaluate
    vegetation success on the rockfill. Further
    studies are planned in 2007 to confirm the
    modeling used in the design.
  • With the exception of rock outcrops, the surface
    area will be vegetated. Fertilizer will be added
    and the area over-seeded for the first several
    years to enhance success.

30
Neil Lake July 2005
31
Neil Lake 2010 Projection
  • Neil Lake as revegetated in 2008, Kam Lake in
    background. Note Water Treatment Plant still in
    place.

32
Upper Pud - July 2005
33
Upper Pud - July 2010 Projection
  • Upper Pud, capped with waste rock and gravel.
  • Note vegetation starting to show.

34
Upper Pud 2015 Projection
  • Vegetation cover now established on Upper Pud TCA

35
Cover Test Pad on Upper PudJune 2006
36
Test Pad for Vegetation on Mine Rock Cover
37
  • Section 7
  • Contaminated Soils
  • Minesite has been impacted by 65 years of mining
  • Areas of impact have been identified
  • Site has been divided into 4 zones to facilitate
    closure and reclamation.
  • The Zones are
  • Zone 1 - Blend Plant/Negus Pond, Con Pond,
    Hazardous Waste Disposal Site
  • Zone 2 Tailing Areas Upper Pud, Middle Pud,
    Lower Pud, Neil Lake, Negus Tailing, and Crank
    Lake
  • Zone 3 Main mine lease with mill area,
    Robertson headframe, and area around tailing
    areas to north, west and south
  • Zone 4 Rat Lake, Tin Can Hill, Con Camp and
    Dock, and Mosher Island.

38
  • Section 7
  • Contaminated Soils
  • Closure plan for Zone 1 is discussed in Section
    5.
  • Closure plan for Zone 2 is discussed in Section
    6.
  • Closure plan for Zones 3 and 4 are discussed
    here.
  • The closure plan for Zone 3 is considered in 2
    parts.
  • Area 1. Mill and headframe buildings will be
    removed. Impacted soil will be placed in the
    hazardous waste disposal site or the
    non-hazardous waste site as determined by
    testing. Area will be reclaimed to the NWT
    industrial use standard.
  • Area 2. Soil in the areas to the north, west and
    south of Zone 2 (active tailing basins) will be
    tested. Site specific plans to close these areas
    will be developed based on the results of
    testing.

39
  • Section 7
  • Contaminated Soils
  • The closure plan for Zone 4 (Rat Lake, Tin Can
    Hill and Con Dock) started with testing of soil
    at 8 sites identified as having arsenic
    contaminated soil. In addition to arsenic, all
    metals on the GNWT contaminated sites list were
    included in the testing program.
  • If any metal on the list is exceeded and
    determined not to be naturally occurring, then
    the sites will be evaluated to determine if clean
    up is necessary. Data to date suggests, once the
    arsenic contaminated soils are removed or cleaned
    up, the other metals of concern are removed.
  • The test results indicated that arsenic at 5 of
    the sites is naturally occurring mineralization
    not a result of mining. The others sites will
    be further investigated.
  • The rest of Zone 4 was inspected and no other
    contaminated sites were identified. If
    additional sites are found in the next 4 years, a
    site specific closure plan will be developed for
    each area.

40
  • Section 7
  • Contaminated Soils
  • In 2007, sites away from the main mine area
    mill and Robertson Headframe - will be tested to
    confirm the extent and type of arsenic that may
    be present in the soil.
  • Water that collects in the excavations at the
    mill will be directed to construction sumps in
    the excavation area. These sumps will be pumped
    and the water directed to the Middle Pud TCA.
  • Section 7.4 details the plan to clean up the mill
    site and clean the depressions in the rock
    surface once the mill is removed.

41
  • Section 8
  • Water Management
  • Since the early 1980s surface water on site has
    been collected and directed to the Middle Pud TCA
    and then to the Water Treatment Plant.
  • Water treated at the plant, and at nine sampling
    stations around the site, has been monitored
    under the Water License since the early 1980s.
  • Regulatory limits for these contaminants are set
    out in the Water License and in federal MMER
    regulations. These will continue to be applied
    following Closure and will apply to minewater
    once it nears the surface. If the limits are
    exceeded, the minewater would be pumped to the
    Middle Pud TCA for treatment.

42
Map of Current SNP Sites
43
  • Section 8
  • Water Management
  • Engineered structures control site surface
    drainage. The Closure Plan provides further
    improvement to the system.
  • Offsite flows not directed to Middle Pud are
    minimal and have not been in contact with
    impacted areas.
  • These flows are currently monitored by the
    Surveillance Network Program (SNP) under the NWT
    Water License.
  • Rat Lake clean up is complete and a final report
    will be submitted in March 2007. The report
    includes the results of the speciation tests.

44
  • Section 8
  • Water Management
  • The Closure Plan creates additional surface water
    monitoring stations and will monitor the quality
    of the minewater as it approaches the surface.
  • Six groundwater monitoring wells have been
    installed and several more are included in the
    Closure Plan, including 2 deep wells adjacent to
    mine workings.
  • Monitoring at these additional stations will
    continue and be required under future Water
    Licenses.

45
  • Section 8
  • Water Management
  • Minewater and mine flooding.
  • URS sampled underground minewater in 2004
  • MCML sampled underground minewater in 2006.
  • Mine flooded to 4700 Level as of September 2006.
  • Minewater is expected to reach surface in late
    2014, thus Con Mine will take 11 years to flood.
  • Water quality testing indicates minewater is
    relatively clean Zinc is only parameter above
    Water License limit.
  • Closure Plan calls for installation of access
    points in the concrete caps at Robertson Shaft,
    C-1 Shaft, and 204Q Stope to allow for
    installation of pumps should it be necessary to
    pump and treat the minewater when it reaches
    surface.

46
  • Section 9
  • Closure and Post-Closure Monitoring
  • Monitoring of the site is detailed in Section 9.1
    and includes geotechnical inspections of the
    tailing dams, closed hazardous sites, and water
    management facilities. The cost estimate
    (Section 10) anticipates that environmental
    monitoring would continue for 50 years, but the
    frequency of inspections would be reduced over
    time.
  • Post-Closure monitoring is anticipated to
    continue unchanged for at least 25 years, or
    until water quality satisfies the Water License
    discharge limits and water treatment can be
    discontinued. The MMER and EEM programs would
    also continue to apply during that period.

47
  • Section 9
  • Closure and Post-Closure Monitoring
  • The annual geotechnical inspection of the
    minesite includes the chemical and physical
    stability of the TCAs, plus all dams, dykes and
    drainage channels.
  • The inspection will be expanded to include caps
    on the openings to surface, and the results of
    groundwater monitoring.
  • A report of each inspection, and a plan outlining
    any required action, would be sent to the MVLWB,
    the INAC Inspector, and Environment Canada.

48
  • Section 9
  • Closure and Post-Closure Monitoring
  • Federal Environmental Effects Monitoring (EEM)
    has been in effect since June 2002.
  • Numerous parameters, including 36 metals, are
    routinely monitored.
  • Post-Closure monitoring includes EEM and this
    will continue at least for the next 6 to 9 years.
  • Other than arsenic, EEM has not detected any
    other metals at levels of concern.
  • In addition to contaminants, EEM monitors the
    environmental effects of treated effluent on the
    receiving water, including fish and other biota.

49
  • Section 10 Cost Summary Schedule
  • Submitted to MVLWB in December 2006
  • Remaining closure costs estimated at 12.5
    million

50
  • 2007 Planned Reclamation
  • Complete treatment of all remaining arsenic
    sludges.
  • Decommission and start to remove Blend Plant
    structure.
  • Begin dismantling and removal of remaining
    surface structures, including mill complex and
    headframes.
  • Perform cycle 3 of minewater sampling
  • Install remaining groundwater wells.

51
  • 2008 Planned Reclamation
  • Complete demolition and removal of remaining
    surface structures.
  • Begin reclamation of Upper Pud TCA.
  • Cap 204Q stope opening.
  • Cap Robertson / C-1 Shaft openings.
  • Perform cycle 4 of minewater sampling.
  • Begin reclamation of Middle Pud TCA.
  • Continue closure monitoring.

52
  • 2009 Planned Reclamation
  • Complete reclamation of Upper Pud TCA.
  • Continue reclamation of Middle Pud TCA.
  • Perform cycle 5 of minewater sampling.
  • Complete any remaining tasks.
  • Commence Post-Closure monitoring.

53
  • 2010 Planned Reclamation
  • Complete reclamation of Middle Pud TCA.
  • Over seed and fertilize revegetated areas.
  • Perform cycle 6 of minewater sampling.
  • Complete any remaining tasks.
  • Continue Post-Closure monitoring.

54
  • Status of Con Mine Water License
  • Current license expires on January 30th 2008
  • Miramar will ask that the Water License be
    renewed to cover the period from January 2008
    thru December 2014 i.e. thru the 4 year
    physical reclamation period and into the start of
    the post closure monitoring period.
  • The renewed license will allow for reclamation,
    ongoing water treatment and post closure
    monitoring and maintenance (no further mining or
    milling).
  • This license period will allow the reclaimed site
    conditions to become stable. Subsequent Water
    Licenses will address the long term monitoring
    and maintenance requirements.
  • Miramar will submit the application in 2007 once
    the Closure Plan has been approved.

55
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com