Title: D
1DØ Silicon Microstrip Tracker
DØSMT
- Design
- Production
- Assembly
- Readout
- Installation
- Commissioning
- Conclusions
- Eric Kajfasz (CPPM/FNAL) - Breese Quinn (FNAL)
- Como, October 15, 2001
- presented by Alice Bean (Kansas/FNAL)
2SMT Design
12 F Disks
4 H Disks
6 Barrels
- 4-layer barrel cross-section
SMT Statistics
72 ladders 12 cm long
6192 R/O chips 792,576 channels gt 1.5
million wire bonds
3SMT Design
4High Density Interconnect
- Kapton based flex circuits with0.2 mm pitch for
chip mounting - Laminated to Beryllium substrateand glued to
Silicon sensor - Connects Sensor to SVXII chips and SVXII chips to
flex circuit via wire bonds(Al wedge bonding) - Connects to a Low Mass Cable which carries the
signals out of the interaction region
5SVXIIe chip
- 1.2 um CMOS amplifier/analog delay/ADC chip
fabricated in the UTMC rad hard process - Designed by LBL/FNAL
- Some features
- 128 channels
- 32 cell pipeline/channel
- 8-bit Wilkinson ADC
- Sparsification
- 53 MHz readout
- 106 MHz digitization
- 6.4 x 9.7 mm2
- About 85,000 transistors
6SVXIIe chip
- Externally programmed to achieve optimal
performance for 132 or 396ns beam crossings and
detector capacitances from 10 to 35pF (preamp
bandwidth adjustment) - Chip noise490e 50e/pFi.e. 1200e ENC for
C15pF1 MIP gt 4fC gt 25,000egt S/N 20 - Max dealy in analog pipeline32 x 132ns 4.2us
7Production 3-chip ladders
- 72 single-sided axial ladders
- 2 sensors/ladder
- Located on 1st and 3rd layer of 2 outer barrels
- Be substrate, HDI and rohacell foam/carbon fiber
rails glued on Silicon sensor
8Production 6-chip ladders
N-side
P-side
- 144 double-sided double-metal axial/90 ladders
- 1 sensor/ladder
- Located on 1st and 3rd layer of 4 inner barrels
- Be substrate, HDI and rohacell foam/carbon fiber
rails glued on Silicon sensor
9Production 9-chip ladders
N-side
P-side
- 216 double-sided axial/2 ladders
- 2 sensors/ladder
- Located on 2nd and 4th layer all 6 barrels
- Be substrate, HDI and rohacell foam/carbon fiber
rails glued on Silicon sensor
10Production F-wedges
N-side
P-side
- Silicon sensor glued on HDI
- 144 double-sided 15 strips
- 6 (n) and 8 (p) readout chips
- 1 sensor/wedge
- Located on 12 F-disks
11Production H-wedges
- 96x2 back to back single-sided, 7.5 strip
angles - 6-chip readout per side
- 2 sensors/wedge
- Be substrate and HDI glued on Silicon sensor
- Located on 4 H-disks
12Production Sensor problems
- Sensor lithography defects
- A silicon manufacturing problem produced p-stop
isolation defects in the 90 stereo ladders.
This resulted in a 30 yield from the
manufacturer.
- Micro-discharge effect
- With negative p-side bias on double-sided
detectors, we observed micro- discharges
producing large leakage currents and noise above
a certain breakdown voltage. - The effect occurs along the edges of the p
implants, where large field distortions and
charge accumulations result from misalignment of
electrodes with implants.
13Production Testing
- Functional Test
- Debug bad strips (broken capacitors), bonds,
chips, etc. - Determine the V-I characteristics of the sensors
- Measure V-max p-side breakdown voltage
(micro-discharge effect) - Burn-in
- Bias the ladder or wedge and test the readout for
72 hours - Measure pedestals, noise, gain and check sparse
readout - Laser
- Expose biased detectors to a narrow laser scan
- Measure the depletion voltage and leakage
currents and identify dead channels - Readout tested again after the detector is
mounted on a barrel or disk
V-max
Fail
14Production Rates
Production mainly paced by problems with HDIs and
Silicon sensors (yields, delivery delays )
15Production Vop
L6
L3
Vop (V)
Vop (V)
FW
L9
Vop (V)
Vop (V)
16Production V-max
L6
L9
V-max (V)
V-max (V)
FW
V-max (V)
17Production Detector Quality
- Detector classification
- Dead channel lt 40 ADC count response to laser
- Noisy channel gt 6 ADC count pedestal width
- Grade A less than 2.6 dead/noisy channels
- Grade B less than 5.2 dead/noisy channels
- Only used mechanically OK Grade A and B detectors
Channel Fractions ()
18Production dead channels
L3
dead strips
L6-p
L6-n
dead strips
dead strips
L9-p
L9-n
dead strips
dead strips
FW-p
FW-n
dead strips
dead strips
19Assembly Barrel alignment
- Ladders placed on barrels using an insertion
fixture - Internal alignment done using a CMM(touch probe)
20Barrel2 alignment - rotations
In the plane of the ladder
Around ladder short axis
Around ladder long axis
10um
48um
48um
?
(mm)
?
(mm)
(mm)
s(d)
48um induces a 3um error
48um induces a 2um error
s(g)
10um induces a 3um error
s(D)
21Assembly Barrel-Fdisk mating
22Assembly End Fdisks mating
23Assembly Hdisk
24Assembly Radiation monitors
25Assembly ½-cylinder
HDI connection to low-mass cable
South Half Cylinder
26SMT Readout Data Flow
HV / LV
I,V,T Monitoring
8 Low Mass Cable
19-30 High Mass Cable (3M/80
conductor)
25 High Mass Cable (3M/50 conductor)
3/6/8/9 Chip HDI
KSU Interface Board
CLKs
CLKs
Adapter Card
SEQ
SEQ
SEQ
Sensor
SEQ Controller
Optical Link 1Gb/s
Detector volume
Platform
Serial Command Link
VRB
VRB
VRB
VBD
PwrPC
1 5 5 3
VRB Controller
VME
L3
VRC
Counting House
SDAQ
27SMT Readout Electronics
- Interface Boards
- 8 crates (144 boards) located inside the detector
volume - Regenerates signals
- SVX monitoring and power management
- Bias voltage distribution
- SEQuencers
- 6 crates (120 boards) located on the detector
platform - Use SVX control lines to actuate acquisition,
digitization and readout - Convert SVX data to optical signals
- VRBs (VME Readout Buffers)
- 12 crates (120 boards) located in counting house
- Data buffer pending L2 trigger decision
- Input _at_ 5-10 kHz L1 accept rate 50 Mb/s/channel
- Output _at_ 1 kHz L2 accept rate 50 Mb/s
28Installation
Fiber Tracker
- Cylinder installation was completed on 12/20/00
- A ½ cylinder of 3 barrels and 6 F disks was
inserted into each end of the CFT bore - H Disk installation was completed on 2/6/01
- The cabling (15,000 connections) and electronics
installation was completed in May 2001
Calorimeter
Low Mass Cables
SMT
High Mass Cables
Interface Boards
29Commissioning Status
- The entire detector has been connected and
powered - The 30 glycol water coolant is refrigerated at
10 degC (gt detectors run between 5 and 0 degC) - 15 of the devices are not in the readout
- 10 ladders, 18 F wedges, 20 H wedges
- Problems could be with boards, cables,
connectors, chips, etc. We will debug each of
them during the October/November shutdown, and
expect to recover at least half of them. - Currently collecting calibration, alignment and
commissioning data
30Commissioning Event Display
31Commissioning Monitoring
- Online event monitoring program
32Commissioning Charge Collection
- A cluster is defined as a contiguous sequence of
strips with - Each strip ? 6 ADC counts
- Cluster ? 12 ADC counts
- 1 MIP 25 ADC counts
- One can play on
- Timing settings, i.e. the delay of the
integration window w.r.t. the beam crossing - Preamp bandwith (pabw)
33Commissioning Timing and S/N
- Higher preamp bandwith does not significantly
reduce noise on n-side
4x132ns 1x18ns 0x2ns
Highest value ? smallest bandwith
34Commissioning Calibrations
- SMT pedestal, noise and gain measurements are
taken using SDAQ. - Pedestal and noise measurements are used to
calculate the threshold per chip to be used in
sparse read out
35Barrel cluster charge vs eta
MC
data
366-chip ladder n-side cluster size fraction vs eta
37SMT CFT Track Matching
- Tracks were found separately in the SMT and the
Central Fiber Tracker (CFT) - SMT tracks were extrapolated to the CFT at which
point the track offsets were measured - Magnet off data
?r? -3 ? 36 ?m
38SMT-CFT primary tracks
39Conclusions
- Design/Production
- Experience with double-sided detectors has led to
the decision to use single-sided silicon for the
upgrade. - Should work towards simpler designs in the
future. For example, using 6 different sensor
types resulted in extensive logistical
complications. - Had to overcome numerous vendor related problems
for HDIs, Silicon Sensors, jumpers, low mass
cables - Assembly/Installation
- First alignment results show that the DØ SMT was
assembled and installed very well. - The installation in the D0 detector went rather
smoothly. The biggest challenge to overcome was
the lack of real estate. The D0 detector, when
first designed, was unfortunately not designed
with a Silicon detector in mind
40Conclusions
- Commissioning
- The SMT was the first major DØ Upgrade detector
system fully operational for Run 2a. More than
85 of the channels were available for readout on
startup, and most of the remaining channels will
be debugged and recovered by November. - Calibrations and first look at physics show that
we understand our detector. - The offline software is debugged at the same time
as the hardware. Now that they are both
reasonably stable, we can start systematic
studies. - The detector should be commissioned by the end of
the year. - We are eager to start doing good physics with it.
- General
- Construction and commissioning of the SMT has
been an adventure full of challenges. But thanks
to the relentless efforts of many physicists,
engineers and technicians, D0 has now a vertex
detector to play with. - We had so much fun building this detector for run
2a that we are already planning to build a
completely new Silicon Microstrip detector for
run 2b (see Alices talk)