Title: ATLAS ID Upgrade
1ATLAS ID Upgrade
- Scope RD Plans for ATLAS Tracker
- First thoughts on Schedule and Cost
-
2Detectors General Considerations
3Inner Tracking
- Assumption is that the inner tracker will need to
be re-built using higher granularity detectors in
a harder radiation environment in order to
preserve the current pattern recognition,
momentum resolution, b-tagging capability. - a Radiation increase by 10.
- a To keep Occupancy constant granularity has to
increase by a factor 10. - Small Radius Region Vertex detector (r lt 20cm)
-
- aim for a pixels size factor 5-8 smaller than
today - (50x400 mm2 g 50 x 50 mm2) g benefit
b-tagging, t-tagging - RD
- Pixels Sensor Technologies
-
- Super rad-hard electronics to achieve small
pixel size
4Inner Tracking
- Intermediate Radius 20ltrlt60 cm
- Aim for cell sizes 10 times smaller than
conventional Si strip - detectors.
- benefit momentum-resolution and pattern
recognition - RD
- Lower cost/channel compared to present Si strip
detectors - Si macro-pixels of an area 1mm2 pads or
shorter strips ? - Single sided two dimensional readout (new
concepts) - Large Radius 60ltr
- Large area Si detectors.
- Could use present day radiation resistant
strip technology, - or new single sided technology
- RD
- Similar to intermediate radius less demanding
except for cost.
5Inner Tracking
Engineering/Integration Aim at a factor of 10
more channels but with less material. This means
that the System aspects have to be integrated and
understood from the start. RD new light
weight materials for stable structures. Power
Power distribution. Multiplexing of
readout. cooling. alignment. installation and
maintenance aspects. (replacement of existing
infrastructure) Activation 250 mSv/h
implications for access and maintenance Timescale
Need 8-10 years from launch of RD
4-6 years of RD and prototyping , 4 years to
build,
6RD Scope
- Simulation Detector geometry, readout
granularity. - Support Structure Integrated Support of the ID,
Mass less. - Cooling Thermal management of the system.
- Si Detector Technology, Contact with industry.
- Readout Technology,Power, Connections.
- Module Layout Technology, Integration at the
module level. - System InfrastructureCabling, Multiplexing,
- Optical Links Power consideration,multiplexing,
Rad hard. - 9. Power Supplies Location, distribution,
Cabling. - Radiation Hardness Radiation hardness of ALL
components. - 11. Assembly/InstallationAssembly and
installation above ground and in pitt. - 12. System Tests Validation of the performance
at the system level. -
7Simulation
- Tracker configuration Overall optimization of
the tracker. Number of layers in the inner ,
middle and outer radius. - Sensor geometry For each layer determine the
detector granularity, readout
geometry. - Optimal readout Analog.vs. digital, speed of the
readout. - Data Compression Study possible data compression
schemes. -
8Space Boundary Conditions
- Â Â Simulation
- detector geometry, readout granularity
TRT
SCT
Pixel
92. Support Structure
- Conceptual design
- beam pipe support
- Vertex detector support
- Intermediate Si tracker support
- Outer Layer Support
- Assembly
-
- Technology
- Materials
- Optimal Configuration
- Assembly
- FEA Calculations
- Services/Cooling interface
- Integration of the Support structure and the
services/cooling. - Interface to the Thermal Shield.
- Â Â Â Â Â Â Â Â Â Â Â Â Â
103. Thermal Management
- Conceptual Design
- Cooling capacity
- Cooling method
- Evaporative Cooling
- Binary ICE
- Operating temperature
- Pixels and SCT run at 70C
- Thermal enclosures
- Heat Shields and thermal divisions
- Cooling Control
-
- Prototype Cooling System
-
114. Si Detector - I
- Issues
- Cost Detector /Readout
- Connectivity
- Radiation hardness
- Optimal temperature operation
- Detector Technology
- Inner Radius Candidate Technologies
- 3D readout
- Integrated readout and Pixel in one wafer
- Cryogenics detectors
- Middle and Outer Radius
- 2D Single sided detectors
- Macro pixel Detectors
- Si Strips
- Wafer Size
- Wafer Size aim to go to higher Wafers to reduce
cost as well as number of detectors. Presently 6
are used should be able to go to 8 and possibly
12. Â Â Â Â Â Â Â Â Â
125. Readout
- Issues
- Multiplexing
- Technology
- ATLAS SCT readout used the DMILL process will
not be available to upgrade - PIXEL has used IBM deep sub-micron need to
investigate the limit of the radiation hardness
of this process. - New readout chip development
- Tools
- Â Â Â Â Â Â Â Â Â
136. Module Layout - I
- Issues
- Module layout and interface to readout
electronics. - Interface to services.
- Production Cost.
- Industrial Solution vs. Assembly at inst.
- Technology
- Â Â Â Â Â
- Â Â Â Â
147. Cabling/ Multiplexing/ Grounding.
- Issues
- Cable routing.
- Multiplexing.
- Production Cost.
- Industrial Solution.
- Â Â Â Â Â Â Â Â Â Â Â
158. Optical Links
- Issues
- Development of new fast optical Links Power.
- New technology Industrial solution.
- Production Cost.
- Â Â Â Â Â Â Â Â Â
169. Power Supplies
- Issues
- Location of power supplies.
- Optimal Multiplexing of power and implication on
Noise, Cable, cost etc. - New readout technology moves toward low voltage,
implication is that we will need very large
currents unless we can Ladder the power. - Â Â Â Â Â Â Â Â Â Â Â Â
1710. Radiation Hardness
- Issues
- Testing of all components to new levels.
- Â Â Â Â Â Â Â
1811. Assembly /Installation
- Issues
- Replacing present ID with new one while the
rest of the experiment stay in tact more or less.
- E.g Cable routing when the Muon chambers are in
place? Do we need to remove BIL, BIS Chambers? - Max amount of cables services we can route?
- Â Â Â Â Â Â Â Â Â Â
1912. System Tests
- Issues
- Ideas on multiplexing, power dist. Etc. all need
to be confirm in a realistic condition. - Cooling systems need to be tested and developed.
- Combine test of the whole system needs to be done
to validate both the concept and the system
aspects. - ATLAS was (is) very weak on this point.
- Â Â Â Â Â Â Â Â Â Â
20Tracker Upgrade Schedule
- ATLAS will start running in 07 and for the first
5 years will operate with the present ID. - After 5 years the LHC Luminosity will be
upgraded and a new and improved ID will be
needed. - Even if there is no Luminosity upgrade we expect
that the ID will need to be upgraded. - The time scale is
- Formal proposal 04
- Identify Collaborators in the US and outside.
- RD directed Generic 04-09
- Proposal for ATLAS Upgrade 09-10
- Production of New ID Tracker 10-13
- Installation of new ID Tracker 14
21Tracking Cost estimate
- The estimate is very preliminary and is based on
the following assumptions The active components
of the tracker are all Si. The inner radius has
upgraded Si Pixel detectors, followed by Si Strip
detectors, in the outer radius we use single
sided 2-D Si detectors. - The estimate was done by scaling the cost of the
ATLAS Si detector as well as information from
CMS, and the CDF/D0 upgrade cost. - In scaling the costs we had to make assumptions
on how the main cost drivers will scale with the
number of channels, the area and the expected
time evolution. - The RD and final design will have to be driven
by optimizing the cost to performance of the
overall system.
22Tracking Cost estimate
- Mechanics The mechanics does not scale with the
number of channels. - One has to keep the services and the total
weight to a minimum. - The cost estimate assumes there is added
complexity due to light weight - Si Detectors Scale with the detector area.
- The optimization of the number of layers and
exact location has not been finalized. The total
amount of Si will be factor of 5-10 greater
than the present ATLAS detector. -
- Possible cost reduction
- Si detectors Cost is driven largely by wafer
size. Industry is moving toward larger wafers. - Minimize the the amount of Si by using
advances in detector technology. For example
single sided 2D readout can be used in the
medium and larger radii where the segmentation
needs are dominated by tracking accuracy rather
than occupancy. -
23Tracking Cost estimate
- On detector read out electronics
- The readout electronics cost is driven by the
number of channels. - Take advantage of the reduction in the feature
size of the electronics. (ATLAS design used
ATMEL/DMILL rad hard technology that has a
conservative feature size of 1.2 Micron in the
Strips. CMS and ATLAS pixels are using sub micron
technology of 0.25 micron) - Present industry standard is 0.18 moving
toward 0.13 microns. - Expect that by the time we go into production
the standard feature size will be as low as 0.08
microns. Allowing for a substantial reduction in
the power and space needed for the electronics
and allowing for finer granularity without an
increase in power and space needed. - The reduction in power has important
implication also on the cooling and services that
will be needed. -
-
24Tracking Cost estimate
- Module integration
- Module integration costs include costs of
Hybrids and the components assembly. - In the case of the Pixel detectors the cost of
bump bonding Si is a significant part of the
module integration. - Significant cost reductions are possible
assuming one of the integrated developments
matures in time. They integrate the readout and
the active detector on the same wafer
eliminating the need for individual bonds. -
- Cables Data Links
- Assumed a higher level of multiplexing compared
to the present solutions. In particular the
amount of power cables that need to be reduced
for physics (reduced mass), space and cost
reasons. -
- Power Supplies
- Power supplies will need to be optimized and
serve a larger number of modules. This has
implication on coherent noise and very detailed
system integration will be needed to achieve
this. -
25Tracking Cost estimate
- Cooling (Additional) The needed cooling capacity
will scale with the number of channels, but we
have taken advantage of the lower power
requirements of the lower feature size
electronics. A large part of the external cooling
can be reused. -
- Off detector electronics (Read out Drivers) We
have to take advantage of advances and reduction
in the cost of electronics. We assume that a
factor of 10 more data 10 years from now will
cost factor of 1.5 more than present cost. -
- The Tracker cost for one detector thus estimated
to be between - 150-180 M. (assuming the full detector is built
in the US) - These numbers are only given as a rough
estimate. We are not ready for an engineering
estimate, which will have to be done after RD
has progressed and better optimization done. - What should be the US part?
26Conclusions
- Tracker Upgrade is a complex technical problem.
- The RD plan needs significant effort in many
areas. - An ATLAS wide collaboration will need to be
established for the execution of the project. - U.S. should plan a significant role in the ATLAS
Tracker upgrade. - With ATLAS detector still not completed and
installed. Preparations for Physics on going we
need to find the right balance for this effort.
27ATLAS