Title: Project Execution Planning for Earned Value Management
1Project Execution Planningfor Earned
ValueManagement
- LSST Directors Review
- SLAC
- March 8-9, 2006
- Theodore L. Lavine
- LSST Group at SLAC
- and
- Thomas L. Frey
- LSST Corporation and Triad Project Management
Services, Inc.
2Earned Value Management (EVM)
- DOE and NSF both demand this quality-oriented
standard for management of scope, cost, and
schedule. - The budgeted value of scheduled elements of the
work-scope is earned as those elements are
completed. - EVM process is transparent and systematic
- First, plan the work.
- Manageable WBS
- Activity schedule
- Time-phased cost and resource budgets
- Objective measures of performance
- Integrated Performance Measurement Baseline (PMB)
plan - Then, work the plan.
- Track actual cost and effort.
- Analyze variances from the PMB.
- Forecast cost at completion and completion date.
- Revise and control the plan as necessary.
3LSST Earned Value Planning Process
- Camera, Telescope, and Data Management Systems
are planning for implementation of EVM - LSST has strong leadership and experience in
project control - Thomas Frey, Project Controls Specialist, is
assigned to the LSST PMO full-time from Triad
Project Management Services, Inc. - Theodore Lavine at SLAC is the Camera Project
Control Manager. - Charles Butehorn is the Financial Planner for
BNLs Camera Team. - The LSST Subsystem Teams have working versions
of - WBS and Dictionary
- Detailed Activity Schedule starting in FY07
- Target Cost Allocations
- Activity-Based Cost Estimates
- These are living documents that are evolving as
we develop the LSST Project Execution Plan.
4Camera WBS Status
5LSST Schedule Status
- LSST project schedule
- 1154 activities and 1862 logic relationships
- Camera subsystem schedule
- 710 activities, 1212 logic relationships
- Camera Schedule Drivers
- Project Engineering Design in FY0708
- Preliminary Design Review at end of FY07
- Detailed Design Review at end of FY08
- Line-Item Construction starts in FY09
- DOE-HEP FY09 budget request to OMB is due in June
2007. - First Light in December 2012.
6Cost Estimating Status
- Cost Estimates created for 240 separate
activities, so far, predominantly between 30k
and 500k. - More detailed, task-based estimates will follow
for all subsystems from March through August,
2006. - Starting in March, the cost estimating database
will incorporate - Relational database for cost resource estimates
- Automated table of direct and indirect resource
rates - Standardized datasheets for capturing the cost
resource basis-of-estimate for each activity - Standardized methodology for risk-based
contingency estimation (technical-, cost-,
schedule-risk) by activity - as described in the LSST Cost Estimating Plan.
7Distribution of 240 Cost Items Estimated
8Camera Sensors Rafts WBS/Schedule/Cost
9Zoom-in Sensor Acquisition Testing
10Camera Integration WBS/Schedule/Cost
Cryostat Integration
Camera Integration
Cost
Recent cost estimate was 4.5M, fully loaded
without contingency.
11Zoom-in Camera Integration
12Time-Phased Camera Cost Estimate
- Integrating cost estimates with the schedule
facilitates resource usage analysis. - We are working toward subsystem plans that will
be manageable and executable.
13Time-Phased Planning - Future Steps
- Implement EVM in stages
- Identify the Earned Value measurement tasks
and/or milestones for each subsystem. - Establish actual effort accounting, by task and
institution. - Start doing EVM during Detailed/Final Design work
(FY08). - Reconcile acquisition strategy with schedule and
budget authority for funding the multi-M
procurements. - For the camera, these major procurements are the
sensor prototype, production sensors, lenses and
filters
14LSST EVM System Development Summary
- Uniform approach is being applied to the Camera,
Telescope, and Data Management Systems - Centralized, integrated database and tools
- Strong Project Control experience at LSST PMO,
SLAC, and BNL - Subsystem Managers are involved in implementation
- Fully supported by Project Manager