Title: Assessment of Fish Entrainment and Fish Passage Issues
1Assessment of Fish Entrainment and Fish Passage
Issues
DeSabla-Centerville Relicensing Project
- FERC No. 803
- Relicensing Study Plan
2Proposed Goals
- Assess the feasibility and potential costs for
potential full mitigation measures, which include
fish screens and fish ladders (tier 3)
3Screens and Ladder Sites
4Screens Only Sites
Screen
5Sites not included in this presentation
- Toadtown Powerhouse - Screen
- DeSabla Powerhouse - Screen
- Little Butte Creek Diversion - Screen
- Helltown Ravine - Screen
- Round Valley Dam - Ladder
- Philbrook Dam - Ladder
6Screen Types Considered
- In Canal Screens
- Drum Screens
- Flat Plate Screens / Vertical
- Flat Plate Screens / Horizontal
- In-stream Screens
- Flat Plate Screens
- Perforated Curtains
- Coanda/Eicher Screen
- EPRI Modular Incline Screen (MIS)
7In Canal Considerations for Screens and Ladders
- Positives
- Flow is constant / controlled
- Bypass flows to the stream bed is utilized as
passing flows for the screen - Trash is removed by grizzly in a controlled
environment instead of in the stream - Negatives
- Fish are delayed in screen approach area with
possible predation problems - High velocity at intake requires second passage
if ladder exists at the site - Different water elevation in canal and intake
requires ladder with variable gates
8In-stream Considerations for Screens and Ladders
- Positives
- Provides cover for small fish
- Fish are not removed from their habitat
- Negatives
- Debris is highly destructive
- Maintenance is more difficult
- Bypass flows to the stream would be separated
from the canal flows requiring larger releases to
the stream than are presently permitted - Screen cleaning is difficult a grizzly would be
required upstream - Flows in stream vary greatly requiring larger
screen area and causing flow balancing
difficulties
9Butte Creek Diversion Dam Proposed Fish Ladder
and Screen
10Butte Creek Bypass and Canyon
11Butte Creek Bypass
12Butte Creek Downstream of Dam
13Butte Creek Diversion DamGeneral Description
- 44 high dam
- 5 x 6 gate to tunnel
- Long raised canal in steep terrain
- Present bypass flows drop at least 30 ft.
vertically out of canal - Fish passage required around tunnel
14Butte Creek Diversion DamProposed Fish Ladder
and Screen
15Butte Creek Diversion DamEngineering
Construction Challenges
- Very steep terrain with large spring turbulent
flows - Site has no power available
- Construction materials brought in by helicopter
- Long access for personnel
- Strict safety requirements for construction
workers would be necessary in the steep slopes,
and would greatly increase construction time - Construction should not interfere with operations
- Tunnel and headgate velocities are too high for
fish passage
16Butte Creek Diversion DamProposed Screen
Ladder Used
- Modular flat plate vertical screen would be
placed in canal at tunnel exit - Bypass flows to a fish ladder would consist of
denil ladders (Alaska Steeppass or equivalent)
and resting pools built into the mountain side - River discharge structure of concrete must
provide the minimum river release flows of 16 CFS
as attraction flow - Screen would require a substantial grizzly with
flush cleaning and hoisting capabilities - Screen cleaning would use sweeping brushes and
would require power from a propane fueled engine
generator - Screen area would be 300 ft2 minimum to meet Cal.
DFG requirements - Baffles behind screen would be used to balance
flows - Existing headgate and tunnel would require
extensive modifications to lower velocities for
fish migration upstream
17Hendricks Diversion DamProposed Fish Screen
Ladder
18Hendricks Canal Head Gate
19Hendricks Canal Grizzly
20Hendricks Canal Control Gate
21Hendricks Diversion DamGeneral Description
- 8.8 ft high dam
- 2 each 4.3 x 4.6 ft gates to canal dug into the
earth - A grizzly, a bypass and an abandoned fish screen
site exists about 200 yards down stream from the
headgates.
22Hendricks Diversion DamProposed Fish Screen
Ladder
23(No Transcript)
24Hendricks Diversion DamEngineering
Construction Challenges
- Site has no power available
- Construction should not interfere with operations
- Headgate velocities are too high for fish passage
- The abandoned fish screen was perpendicular to
flows and far smaller than current standards
(water driven drum screen) - Will require modifications of the gates and
portions of the canal to pass fish
25Hendricks Diversion DamProposed Screen Ladder
Used
- Modular flat plate vertical screen would be
placed in canal - 15 CFS of bypass flows would be directed to a
denil fish ladder (Alaska steeppass or
equivalent) near the original screen location,
which is about 100 yards from the West Branch
Feather River - River discharge structure of concrete must
provide the minimum river release flows of 15 CFS
as attraction flow - Screen would require a substantial grizzly with
flush cleaning and hoisting capabilities - Screen cleaning would use sweeping brushes and
would require power from a propane fueled engine
generator - Screen area would be 400 ft2 minimum to meet Cal.
DFG requirements - Baffles behind screen would be used to balance
flows - Existing headgate would require extensive
modifications to lower velocities or a ladder for
fish passage
26Lower Centerville Diversion Dam
27Lower Centerville Canal Grizzly
28Lower Centerville Dam Downstream (possible fish
ladder site)
29Lower Centerville Dam Downstream (creek flow
observation May 2006)
30Lower Centerville Dam Head Gate (discharge to
canal)
31Lower Centerville Dam Aerial View
32Lower Centerville Diversion DamGeneral
Description
- 12 ft. high dam
- 2 each 3 x 6 intake gates
- An existing pipe grizzly and hoist clean large
wood and debris (located about 100 yards down
stream from the intake structure) - An overflow is located about 50 yards downstream
- Road access is very poor and steep, but useable
33Lower Centerville Diversion Dam
34(No Transcript)
35(No Transcript)
36Lower Centerville Diversion DamEngineering
Construction Challenges
- Dam is inaccessible except along head gates and
canal - Large boulders move downstream during high flows,
even to the head gates - Terrain is extremely steep into the canyon
- Truck access is slow and steep with no shoulders
along road - Power is available from DeSabla power house but
limited - Large turbulent flows in spring (over 1200 CFS in
May 06) - Construction should not interrupt operations
37Lower Centerville Diversion Dam Proposed Screen
Ladder Used
- 550 to 600 ft2 flat plate vertical, modular
screen located in the canal would be placed just
downstream of the headworks - A new grizzly would protect the screen and be
located upstream of, or at the existing overflow - Bypass flows of 40 CFS would discharge into a
fish ladder consisting of concrete and boulder
ponds with v-notch weir passages - The headworks and a portion of the canal would be
modified to reduce flow velocities in the fish
ladder / screen approach channel - Other requirements would be hoisting sweeping
brush cleaning and baffles behind screens
38Long Ravine Diversion Dam Proposed Screens
39Long Ravine Dam
40Long Ravine Grizzly
41Long Ravine Radial Gate
42Long Ravine Access over Creek
43Long Ravine Diversion Dam General Description
- 6.5 high dam recaptures all 120 CFS of the
Hendricks canal - Canal flows are controlled by 6 x 10 radial
gate protected by a grizzly - In-stream releases are very low (1 CFS) and not
adequate for screen bypass flows
44Long Ravine Diversion Dam Proposed Screens
45Long Ravine Diversion DamEngineering
Construction Challenges
- Very steep terrain with large spring turbulent
flows - Site has no power available
- Construction materials brought in by helicopter
- Long access for personnel
- Strict safety requirements for construction
workers would be necessary in the steep slopes,
and would greatly increase construction time - Construction should not interfere with operations
- Velocities are too high for fish passage at the
radial gate - There is insufficient bypass flows for any screen
system as presently operated - Bypass flows to long ravine would place screened
fish into a steep gradient creek which would
possibly be detrimental to their survival
46Long Ravine Diversion DamProposed Screen Used
- A 400 ft2 modular flat plate vertical screen in
the canal downstream of the radial gate would
discharge at least 10 CFS to the long ravine
through a by-pass pipe - The 10 CFS loss would have to be made up from the
Cunningham or Little West Fork feeders - Modular flat plate vertical screen would be
placed in canal downstream from the radial gate - Screen would require a substantial grizzly with
flush cleaning and hoisting capabilities - Screen cleaning would use sweeping brushes and
would require power from a propane fueled engine
generator - Baffles behind screen would be used to balance
flows - Existing radial gate would require modifications
to lower velocities for fish migration upstream
47Inskip Diversion Dam
48Inskip Discharge Pipe
49Inskip Downstream of Dam
50Inskip Downstream of Dam
51Inskip Diversion DamGeneral Description
- Small diversion structure, about 1.5H x 2.0W
un-gated opening to flume - Very steep creek gradient with significant drop
to creek bed from dam - Bypass flows are about 0.25 CFS through two 2
pipes
52Inskip Diversion Dam
53Inskip Diversion Dam Engineering Construction
Challenges
- Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for a fish screen
- Very steep terrain
- Construction materials brought in by helicopter
- Strict safety requirements for construction
workers
54Inskip Diversion DamProposed Screens Used
- 180 ft2 screen located in the flume would be a
non self-cleaning vertical flat plate screen - Present requirements for bypass flows would have
to be increased to 1.5 CFS for full screen flows
of 15 CFS - a small bypass pipe would carry fish to the creek
bed below which would be modified to dissipate
the high discharge velocities without harming the
fish - Inflows to the screen would have to be protected
by a new grizzly trash rack that would require
manual cleaning
55Kelsey Diversion Dam
56Kelsey Creek Dam Discharge Pipe
57Kelsey Creek Discharge Pipe at Butte Canal
58Kelsey Diversion DamGeneral Description
- Small diversion structure, about 1.5H x 2.0 W
un-gated opening to flume - Very steep creek gradient with significant drop
to creek bed from dam - Bypass flows are about 0.25 CFS through two 2
pipes - Diversion has side spillway which discharges
vertically to creek bed below
59Kelsey Diversion Dam Engineering Construction
Challenges
- Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for fish screen
bypass flows - Very steep terrain
- Construction materials brought in by helicopter
- Strict safety requirements for construction
workers
60Kelsey Diversion DamProposed Screens Used
- 24 ft2 screen located in the flume would be a non
self-cleaning vertical flat plate screen - A small bypass pipe would carry fish to the creek
bed below which would be modified to dissipate
the high discharge velocities without harming the
fish - Inflows to the screen would have to be protected
by a new grizzly trash rack that would require
manual cleaning - see sketch for Inskip for additional information
61Cunningham Diversion Dam
62Cunningham Dam
63Cunningham Creek Access
64Cunningham Creek Down Stream of Dam
65Cunningham Diversion DamGeneral Description
- 4-2 diversion structure diverts water into a
16 diameter pipe - No grizzly or control gate
- Steep terrain and river gradient
- No electric power available
- Limited access by trail
66Cunningham Diversion DamEngineering
Construction Challenges
- Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for fish screen
bypass - Very steep terrain
- Strict safety requirements for construction
workers
67Cunningham Diversion DamProposed Screens Used
- 60 ft2 screen located in the flume/pipe would be
a non self-cleaning vertical flat plate screen - 0.5 CFS bypass flows through pipe to creek bed
with energy dissipater - New manual cleaned grizzly required
- see sketch for Inskip for additional information
68Little West Fork Diversion Dam
69Little West Fork Ditch to Canal
70Little West Fork Pipe
71Little West Fork Diversion DamGeneral Description
- 2-10 high by 10 wide diversion structure
- 16 diameter pipe
- No grizzly or control gate
72Little West Fork Diversion DamEngineering
Construction Challenges
- The grizzly and the flat plate screen would need
to be self-cleaning using the bypass flows - Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for fish screen
bypass - Very steep terrain
- Strict safety requirements for construction
workers
73Little West Fork Diversion DamProposed Fish
Screens Used
- 60ft2 self-cleaning/flushing flat plate vertical
screen - The grizzly and the flat plate screen would need
to be self-cleaning using the bypass flows - Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for fish screen
bypass - Very steep terrain
- Strict safety requirements for construction
workers - see sketch for Inskip for additional information
74Clear Creek Diversion Dam
75Clear Creek Dam Approach
76Clear Creek Dam Up Stream
77Clear Creek Dam Down Stream
78Clear Creek Diversion DamGeneral Description
- 7 high concrete dam diverts water through a
sloped grizzly - 4 x 4 slide gate
- Transition concrete structure to a 16 pipe with
a significant slope to the Butte canal
79Clear Creek Diversion DamEngineering
Construction Challenges
- Diversion is very remote
- Access by walk-in personnel only
- No electric power available
- Present bypass is not adequate for fish screen
bypass - Very steep terrain
- Construction materials brought in by helicopter
- Strict safety requirements for construction
workers - Major water falls upstream and downstream of dam
make fish passage highly unlikely.
80Clear Creek Diversion DamProposed Screens Used
- A 135 ft2 modular, flat plate, vertical fish
screen would be installed upstream of the 16
pipe - The entire screen system would be constructed on
a raised steel structure - Bypass flows would have to be increased to clear
creek to 4 CFS minimum - The bypass pipe and discharge area would be
designed to dissipate the high energy of the fall
without harming fish - Screen cleaning would be mechanical brushes
powered by propane fueled engine generator - Cleaning should occur on pressure differential
across screen - Low voltage battery power would be used for
instrumentation.
81Estimated Cost of Screens and Ladders
82Estimated Cost of Screens and Ladders