The ODV Draft Handbook - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

The ODV Draft Handbook

Description:

Valuations based on ODV for their 'opening' positions ... excludes assets that are required to deliver the electricity conveyance service ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 15
Provided by: stuarts98
Category:

less

Transcript and Presenter's Notes

Title: The ODV Draft Handbook


1
The ODV Draft Handbook
  • Submisssion to the Commerce Commission on behalf
    of the
  • Electricity Networks Association
  • Stuart Shepherd
  • 14 April 2004

2
Context
  • The Commission has made a draft decision to allow
    lines businesses to use
  • Valuations based on ODV for their opening
    positions
  • Either valuations based on ODV or DHC thereafter
    (but not the option to change from one to the
    other)
  • The Commission has also stated it intends to use
    the valuations derived from the application of
    the ODV Handbook
  • For the information disclosure regime (subpart 1,
    Part 4A)
  • For the targeted control regime, which includes
    investigating post breach if control should be
    imposed (subpart 3, Part 4A)
  • It appears such valuations may also be used to
    determine price levels for goods and services
    that are controlled (Part 5)

3
Context (contd)
  • When evaluating valuation methods in 2002 the
    Commissions analysis assumed each method would
    be implemented consistent with that methods
    principles
  • And the Commission based its draft decisions on
    that analysis
  • Thus a key test for the ODV draft Handbook is
    whether or not it would implement the ODV method
    as assumed in the Commissions original analysis
  • I therefore consider whether the draft Handbook
    would implement the ODV method consistent with
    its principles

4
Two key issues
  • I wish to focus on two key principles of the ODV
    method that the draft Handbook would not
    implement consistently
  • The ODV method starts with a service that is to
    be delivered, and then incorporates all assets
    required to deliver that service
  • The ODV method requires market prices to be used
    for asset values

5
Start with service, include all assets
  • The ODV method
  • assumes that the value of assets to a business
    is equal to the cost the business would incur if
    it were deprived of the use of its assets and
    then took action to restore its operating
    position to the pre-deprival situation by
    replacing its old asset base, at the lowest
    possible cost, with an asset base providing an
    equivalent service potential (para 1.2 of draft
    Handbook)
  • Thus the test as to which assets are included in
    the valuation is determiend by the requirement
    that the asset base must be capable of delivering
    the equivalent service

6
Start with service, include all assets (contd)
  • The draft Handbook does not use this equivalent
    service test to determine the set of assets to
    be included in the valuation
  • It covers system fixed assets only
  • Some other fixed assets are covered by the
    current disclosure requirements, but these are
    not covered in the draft Handbook e.g. office
    buildings equipment, asset management systems
    (GIS), and computing systems.
  • It excludes assets on the basis of
  • The ability to shift the assets geographically,
    e.g. mobile sub-stations and generators
  • The service the asset provides being contestable,
    e.g. generators
  • The asset being intangible in nature, e.g. some
    easements, databases and intellectual property
  • None of these exclusions are consistent with the
    ODV method

7
Start with service, include all assets (contd)
  • This issue could be addressed by modifying the
    Handbook
  • To allow all types of assets to be included that
    are required to deliver the service, and not just
    system fixed assets
  • To ensure any tests for excluding assets are
    based directly on whether the asset is required
    to deliver the equivalent service
  • To remove the tests that exclude assets in a
    manner inconsistent with the ODV method

8
Market prices required for asset values
  • The lowest possible cost aspect of the ODV
    method reflects the need to optimise the network
    from an engineeering and economic perspective
  • The cost for the optimised set of assets should
    be market prices
  • The draft Handbook sets out maximum values that
    may be used for many assets
  • However lines businesses have provided evidence
    that these draft maximum values are in many cases
    below the prices at which they themselves can
    purchase the assets
  • E.g. the PwC submission on behalf of 19 lines
    businesses, Orion and Vector
  • The Commission has not publicly responsed to
    those claims, and to date has revealed neither
    the method its advisers used to arrive at the
    draft maximum values, nor the actual prices they
    used or their sources
  • Thus on the evidence so far it appears the draft
    schedule does not reflect market prices

9
Market prices required for asset values (contd)
  • This situation raises two issues
  • The extent to which a mandated schedule of prices
    is a reliable method for identifying market
    prices for the assets
  • To the extent that a schedule is used, whether
    the process relied upon by the Commission to date
    has delivered a credible result
  • Regarding (1), we understand the reason for a
    schedule is to aid consistency of valuation
    across lines businesses
  • For installations that are similar across lines
    businesses this consistency is probably desirable
  • Where the installations are not similar it is
    incorrect to expect the costs (or valuations) to
    be similar
  • This suggests there are limits to the extent to
    which a mandated schedule of prices will result
    in a reliable valuation

10
Market prices required for asset values (contd)
  • The limits to the reliability of using a mandated
    schedule could be addressed by allowing lines
    businesses to also use their actual costs in the
    valuation, subject to appropriate audit criteria
  • We note some lines businesses have already
    adopted this approach in their statutory
    accounts, demonstrating it can in practice be
    used under FRS-3
  • We also note that the use of actual costs would
    (presumably) be allowed under the DHC valuation
    method, and that (other than for optimisation
    reasons) there appears no good reason why the
    same approach could not be used under ODV

11
Market prices required for asset values (contd)
  • Regarding (2), it is usual for the Commission to
    expose its quantitative estimates to public
    scrutiny
  • And where there are confidentiality concerns, to
    restrict the flow of information appropriately
  • However in developing the draft schedule neither
    the methodology nor the prices have been
    subjected to scrutiny
  • There is evidence from lines businesses that the
    draft schedule is not a reliable reflection of
    the prices in practice available to lines
    businesses
  • And the Commission has not responded publicly to
    this evidence
  • This procedural issue raises concern not only for
    the development of the current schedule, but also
    in relation to how the schedules will be revised
    in the future

12
Market prices required for asset values (contd)
  • This procedural issue could be addressed by
  • Documenting the methodology to be used to update
    the schedules and issuing it for comment
  • Documenting the prices used and their sources and
    issuing them (if necessary as restricted
    information) for comment
  • Revising the schedules, taking into account the
    comments received
  • Committing in advance to updating the schedules
    on a regular basis (e.g. every 5 years), and to
    following a well specified and transparent
    procedure when doing so

13
Summary suggested way forward
  • The ODV method starts with a service that is to
    be delivered, and then incorporates all assets
    required to deliver that service
  • But the draft ODV Handbook excludes assets that
    are required to deliver the electricity
    conveyance service
  • The ODV method requires market prices to be used
    for asset values
  • But lines businesses appear unable in many cases
    to acquire and install assets at the stated
    prices in the draft ODV Handbook
  • Thus in my view the Commission does not have at
    this stage a Handbook that would implement ODV in
    a manner consistent with its principles

14
Summary suggested way forward (contd)
  • In order to take the draft ODV Handbook forward I
    suggest the Commission consider the following
    approach
  • Revise the draft Handbook to take account of the
    issues raised in submissions, at this conference,
    and in cross-submissions, and ensure that the
    Handbook would implement the ODV method
    consistent with its principles
  • Document how each issue raised in submissions has
    been addressed in the revised draft, or why it
    hasnt been addressed
  • Document the method used to revise the schedules,
    and the actual prices used
  • Issue all the above for comment (recognising the
    prices used in the schedule may be restricted
    information)
  • Finalise the Handbook, taking into account the
    comments recevied from the above process
Write a Comment
User Comments (0)
About PowerShow.com