Title: The NIKHEF production
1Production of Muon chambers_at_MPI
- Introduction
- The NIKHEF production
- Three Production Schemes
- MPI NOW
- MPI FUTURE
- NIKHEF CLAMPS
- Conclusions
- Appended photographs
2MPI-NOW
- Tubes from Dubna
- Gluing at MPI-Munich
- Installation gas-system at MPI
- Testleak-fix at Garching(Munich)
- 17 chambers sofar, proven 8 day production cycle.
- How?
West side has expansion length o 0.1m in Xras
s
3MPI-NOW
- Spacer glued inside, finished outside
- Day 1 bring in bare cross-plateslongbeams --gt
Glue spacer - Day 2
- remove spacer, bring in a fully prepared
(sensorscabling). - Glue Tubes
- Day 3 - 7 Glue all tube layers
Minimal 7 days in practice 8 days.
We can adopt this procedure directly at
NIKHEF Requires no hardware changes Outside
cleanroom no special mechanics, no experts - No
RASNIK pre-test (still could) - Day 2 is busy.
Could start in A-
West side has expansion length o 0.1m in Xras
s
4MPI-Future
- Spacer fully prepared outside cleanroom on
standard industrial iron worktable (100um
precision, costs 50k) - Day 1 Bring in spacerGlue tubes
- Day 2-6 Glue tube layers
Minimal 6 days in practice probably sometimes 7
days.
Optimal use of granite table - Requires large
irreversible investment - Requires experts
outside cleanroom - Day 1 is busy. Could start
in A-
West side has expansion length o 0.1m in Xras
s
5NIKHEF-CLAMPS
- Spacer sensors prepared outside cleanroom using
temporary clamps (requires worktable 1cm
precision, costs5k) - Day 1 bring in spacer glue
- Day 2-7 Glue tube layers
Minimal 7 days in practice probably 8 days.
Allows full RASNIK pre-test - Requires
mechanicsspace - Some expertise needed outside
cleanroom
West side has expansion length o 0.1m in Xras
s
6Conclusions
- Any change in procedure will badly affect
efficiency around granite table - Therefore, adopt MUNICH-NOW small change,
maximal effect. - NIKHEF-CLAMPS allows RASNIK pre-tests, but it
requires a special setup with some precision - MUNICH-FUTURE. Would save 90 days, costs probably
also 90 days50k. Anyway wait for experience of
MPI - If really necessary, Saturdays for spacer gluing
could be introduced in the MUNICH-NOW scheme.
West side has expansion length o 0.1m in Xras
s
7Introduction
- KEY TO FAST PRODUCTION
- Only use the granite table for work that requires
the granite table (precision) - But realize such approach only would be
efficacious if granite table is the bottle neck
in the assembly process! - Thus, the very first step is to ensure that the
granite table is used full-time! - Lets have a look at MPI
- Then, Let us study three possible production
scenarios
West side has expansion length o 0.1m in Xras
s
8MPI production
- People work concentrated, not interrupted by
physicists or loud music - Preparations are done very carefully and where
possible in advance - One expert technician guides two younger persons.
The people seem to feel very proud and
responsible for their work.
Probably it has a positive effect if somebody is
in charge around the granite table who gives
guidance to youngsters.
West side has expansion length o 0.1m in Xras
s
9Organization
- We can give up the Frascati tension check on the
table. Can be done in advance by anybody (think
about safe tube handling!) - We can put the clocking pins on the tubes well in
advance! - We can do the RASNIK measurements with finished
chamber outside cleanroom
West side has expansion length o 0.1m in Xras
s