Collaborative Business Portal - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Collaborative Business Portal

Description:

Objective business benefits in terms of metrics must be declared ... Latest Space craft model 400 wave guides (W/G) First w/g release 20 weeks 50% improvement ... – PowerPoint PPT presentation

Number of Views:16
Avg rating:3.0/5.0
Slides: 15
Provided by: soe60
Category:

less

Transcript and Presenter's Notes

Title: Collaborative Business Portal


1
Collaborative Business Portal
  • Case Study
  • A Clients Experience

2
Analysis, quantification validation of savings
in the extended enterprise using a collaborative
business portal CBP
  • BNSC SIBPC e-codevelopment Pilot
  • January 2003
  • Dr E Roberts, BAE Systems

3
Rationale - the analysis
  • Shrinking the effective product realisation cycle
    requires major out of the box thinking where.
  • This must address the extended global enterprise
    including SMEs (small medium sized
    enterprises)
  • It must leverage from innovative developments in
    Web technology standards
  • Key issues to be addressed include appropriate
    structure, interoperability security
  • Objective business benefits in terms of metrics
    must be declared

4
Quantify CBP product realisation
  • CBP achieved far higher levels of design maturity
    much sooner through..
  • Reduced Development Cycles
  • Effective risk reduction
  • Reduced interface costs
  • Improved quality management
  • Improved information transfer
  • Transfer of best practice

5
CBP Reduced Development Cycle
  • Cycle times were at the limit of current
    capabilities bottlenecks understood
  • Leveraged from flexible, low cost, innovative WEB
    technologies to address gaps
  • Key to this success was the ability to engage
    with SMEs globally
  • Used COTS packages developed in the financial
    sector (investment banking)

6
CBP Risk Reduction
  • Better planning/ WP management via
  • much earlier risk mitigation capability
  • real time reporting (nowhere to hide!)
  • highlighted all bottlenecks objectively
  • ability to manage late changes effectively
  • robust well understood process capability
  • standardisation common processes driver

7
CBP reduced Interface Costs
  • Rationale
  • Only realisable in the global extended enterprise
  • Is intimately associated with the product
    strategies of agent theory digitisation et al
  • Achieved a greater relative maturity but
    discovered it demands a disproportionate increase
    in digital data transfer. (email, FTP, CD alone
    are totally ineffective)
  • Much greater benefits accrued with increased
    product complexity highly distributed supply
    chains
  • Is generically applicable multi-sector
  • aerospace defence, automotive, health etc.

8
CBP Quality management.
  • Key to reducing cycle time was the ability to
    demonstrate much tighter levels of
    configuration control digitally
  • CBP data was always up to date referenced the
    master
  • In Lifecycle terms the process was started much
    earlier
  • Feed forward term allowed for MRP II long lead
    items to be scheduled
  • Requirement was well understood
  • e.g. not a single query on drawing issues during
    pilot
  • Innovative feature was for the supplier to
    produce a drawing at the point of manufacture.
    (for PDM)
  • Allowed for much more intuitive audit trail (up
    to 76 steps)

9
CBP Information Transfer
  • Speed accuracy
  • key to reducing cycle time
  • Interoperability functionality included
  • Allowed far more design iterations per unit time
    addressing
  • design for manufacture assembly issues
  • standardisation opportunities
  • design for cost added value
  • Drove common processes
  • Data was unambiguous seamless
  • Information was based on DMU product view
  • Resource management was much more effective

10
CBP Transfer of Best Practice
  • From financial sector to space (systems)
  • From pilot to other commodities.
  • Machining, RF cables etc
  • From space to aerospace
  • defence avionics et al
  • Characterised by
  • Low risk, quick wins project confidence
  • Further drove common processes
    standardisation.

11
CBP Lessons Learned
  • Cost model requires further work
  • Key that all product data is included (risk)
  • Workflow development required much effort but
    resulted in significant simplification
  • The CBP appears generically applicable to complex
    distributed organisations critically addresses
    the lessons learned from earlier developments.

12
Validation CBP objective metrics
  • Latest Space craft model gt 400 wave guides (W/G)
  • First w/g release 20 weeks gt 50 improvement
  • At panel release gt80 of w/g complete kitted
    (never before achieved)
  • Non-recurring gt30 improved
  • Total capacity confirmed at 18 w/g per week but
    complexity factor gt20
  • Learning curve with new s/c dramatically reduced
    (41)
  • Cycle time reduction of gt 20 than best
    previous design
  • Associated recurring cost reduction of gt20
    achieved through simplification standardisation
    (DFM)

13
Example of Reduced Interface Costs
  • Space craft waveguide payload digital design for
    manufacture initiative 2001
  • Characterisation
  • 5 unique digital files (total) per waveguide (no
    conventional 2D drawing)
  • 1 package represents up to 10Mb 1 or more
    waveguide runs
  • At least 2 iterations are required per waveguide
    (design approval)
  • 400 waveguides ( associated engineering
    changes)
  • Data flow prime (design, procurement) to supply
    chain return
  • In excess of 40 Gb of data transferred it is
    estimated over 30 weeks (could be as high as 80
    Gb)
  • Equivalent to 5 CDs per week DHL (gt150 total) -
    configured
  • Associated emails to support same.
  • Managing this process is expensive time
    consuming ( is never up to date)

14
Summary
  • Robust low cost digital co-ordination established
    with SMEs
  • CBP allows for much better resource management
  • Design evolved to reflect workflow SMEs
    process capability
  • Significant cycle time cost reduction
    demonstrated
  • Inherent feature is the huge capacity to manage
    late changes
  • Credible risk mitigation strategy demonstrated
  • Believed scalable multi-sector represents best
    practice
Write a Comment
User Comments (0)
About PowerShow.com