Title: Preparations for a Lehman Review


1
Preparations for a Lehman Review
  • Elton Smith
  • Hall D Collaboration Meeting
  • Dec 11-13, 2003

2
Project acquisition process and CDs
DOE Order 413.3 (Initiated by the Office of the
Chief Financial Officer)
3
Project phases and federal budget
BRBudget Request, PEDProject and Engineering
Design Funds
4
Change Requests for G0 Experiment
Cost Cost Schedule Performance Approval
1 Minor, within WBS line item (lt5K or 1) float No impact Subsystem manager
2 Within subsystem contingency allocation (gt5k or 1) lt 1 Quarter delay of milestone Sub-system change not affecting subsystem performance or scope Above plus Project manager and Spokesperson
3 Within overall G0 contingency (gt100k or 10) gt 1 Quarter delay of milestone Subsystem change affecting subsystem performance but not G0 performance Above plus L. Cardman and Executive Committee
4 gt 1 Quarter delay of major project milestone Technical scope change, affects experiment capability Above plus Agencies
5
Lehman review gives CD-1 approval
  • Review of entire 12-GeV project
  • Cost
  • Schedule
  • Technical scope
  • Prerequisites
  • Acquisition plan
  • CDR
  • Preliminary project execution plan and baseline
    range
  • Project data sheet for design
  • Verification of mission need
  • Preliminary hazard analysis report

6
Practically, CD-1 is an approval of
  • CDR
  • pCDR
  • section on accelerator
  • cost and schedule book
  • Best preparation are the subsystem reviews that
    we are undertaking
  • Cost and schedule will have to be covered
    (perhaps at a later stage)

7
BABAR Conceptual Design Review
  • Combined a requirements review with their
    conceptual review
  • Level for conceptual design was one level below a
    module
  • WBS and preliminary cost estimate
  • Interface document to other systems
  • Grounding and shielding plan

Report of the Electronics Review
8
Are there any major items missing in the RD
list? Is the priority given to each appropriate?
  • It is critical that the choices made in the
    readout architecture reflect requirements imposed
    by the physics and detector choices.
  • Balance priority between design and prototyping

Report of the Electronics Review
9
A guess at the process
  • Assess costs and schedule of 12-GeV upgrade
    project
  • Adjust cost of project (accelerator and 4 halls)
    if outside the box
  • Review scope in light of cost envelop
  • Process will include PAC, similar to pCDR review
  • Not clear at which point we will need to
    de-scope
  • Conduct an internally commissioned review of
    project
  • Based on outcome, schedule the DOE (Lehman)
    review of project

10
Impact of budget profile on schedule
11
Lab resources after CD-0
  • Assignment of
  • Budget
  • Current staff
  • Determine the speed with which CD-1 can be
    achieved

12
Manpower (JLab)
13