Title: Ralf Knig
1Contractual Negotiations
- Ralf König
- FFG/EIP
- Unit for International Cooperation
2Life cycle of a FP6 Project
- Phase 1 Feasibility, from an idea onwards
- Phase 2 Towards a proposal submission
- Phase 3 Evaluation
- Phase 4 Contract negotiation
- Phase 5 Run of the Project (management)
3Content
-
- Contract Negotiation Procedure
- Contract
- Structure
- Specific elements
4 Legal Framework
EC TREATY
INTERNATIONAL AGREEMENTS
PARTICIPATION AND DISSEMINATION RULES
FRAMEWORK PROGRAMME
CONTRACTS
SPECIFIC PROGRAMMES
GUIDELINES ON EVALUATION AND SELECTION
PROCEDURES
Other relevant EC Regulations FINANCIAL
REGULATION
WORK PROGRAMMES
Calls for proposals
5Negotiation procedure
- 1. Commission sends invitation to negotiate
- saying favourably evaluated
- Evaluation summary report (ESR) -
recommendations for project negotiation - deadline for returning Contract Preparation
Forms (CPF) - informing who is ? Project officer ?
Administrative officer - indicating necessary changes in technical content
- Contract Preparation Forms
6Negotiation procedure
- 2. Proposal coordinator sends to
Commission Draft CPF forms ( A forms) - Technical annex ( Part B)
- Documented accounts for last 3 year
- Legal documents establishing the organisation
(non-public bodies) - 3. Negotiation meeting(s)
- (for NOEs - finalise list of researchers)
- 4. Coordinator sends final CPF forms (signed) and
final Technical annex - 5. Project starts following contract signature by
Commission - 6. Partners sign Accession to the contract form
with coordinator
7 Electronic handling of CPF (1)
1. Contract preparation forms administrative
budgetary part gt CPF editor -
www.cordis.lu/fp6/contract-prep.htm gt CPF Data
file - Administrative officer ? partially
filled in by EC already gt Document CPF Editor
Users Guide 2. Annex I Description of work
content gt Word Format gt Document Negotiation
Guidance Notes for Coordinators of
.................. http//www.cordis.lu/fp
6/find-doc.htm
8 Electronic handling of CPF (2)
A1 General Information on the
proposal A2a-A2c Information on
participants A3.1 Financial Information whole
period gt Indication of overheads gt Indicat
ion of subcontracting
similar to proposal submission
A3.2 Financial Information breakdown by
period A4 Coordinators banking information
additional information
A5 Additional financial information
annexed to CPF A6 Simpliefied balance
sheet and profit and loss account
not apply to all coordinators
A2 form 1. Send data file to all project
partner 2. Import of A2 partner data in original
data file
9(No Transcript)
10 Technical Annex - Description of work
Table of Contents (should include page
numbering) 1. Project summary 2. Project
objective(s) and state of the art 3. Participants
list 4. Relevance to the objectives of the
specific programme and/or thematic
priority 5. Potential Impact 6. Project
management and exploitation/dissemination
plans 7. Workplan for whole duration of the
project 8. Project resources and budget
overview 9. Other issues (optional) Appendix A
- Consortium description A.1 Participants and
consortium A.2 Sub-contracting A.3 Third
parties A.4 Funding of third country
participants
11 Contract Structure
- Core contract (standard with specifics of
project) - Annex I (technical tasks - the project)
- Annex II General Condition (applicable
to every instrument) - Annex III Instrument specific provisions
(specific to individual instrument)
12Core - Contract Structure
- Art. 1 - Scope
- Art. 2 - Constitution of the Consortium
- Art. 3 - Evolution of the consortium
- Art. 4 - Entry into Force of the Contract and
Duration of Project - Art. 5 - Community financial contribution
- Art. 6 - Reporting periods
- Art. 7 - Reports
- Art. 8 - Payment modalities
- Art. 9 - Special clauses
- Art. 10 - Amendments
- Art. 11 - Communication
- Art. 12 - Applicable law
- Art. 13 - Jurisdiction
- Art. 14 - Annexes forming an integral part of
this contract
13 Amendments
- Art.10 of Core Contract Art.8 of Annex II
- Request in writing
- At the request of the coordinator, deemed to act
on behalf of the consortium - New Tacit amendments with implicit agreement of
the Commission within 6 weeks only for
modification and evolution of the consortium and
for technical reports - New in IP/NoE, enlargement of the consortium to
new contractors and new activities may be
foreseen. This enlargement follows a competitive
call launched by the consortium with evaluation
of proposals by external experts
14Signature and entry into force
- Contractual link of all contractors with the
Commission - Contract enters into force upon signature of
coordinator and Commission - All the contractors are identified in the core
contract Art. 1.2 - Coordinator must ensure other contractors sign
without delays - Evolution of consortium possible where one
or more does not sign the Form A article 2
in case of enlargement (new contractors)
article 3 - Project begins on the date established in the
contract (this can be before the contract enters
into force) or in the month after signature of
both parties
15Annex II - General conditions Structure
-
- Article II.1 - Definitions
- Part A Implementation of the Project
- Section 1 - Implementation and deliverables
- Section 2 - Termination of the contract and
responsibility - Part B Financial Provisions
- Section 1 - General financial provisions
- Section 2 - Controls, recoveries and sanctions
- Part C Intellectual Property Rights
16Annex II - General Conditions Structure
- Part A Implementation of the Project
- SECTION 1 - IMPLEMENTATION AND DELIVERABLES
- Art.II.2 - Activities
- Art.II.3 - Performance obligations
- Art.II.4 - Force majeure
- Art.II.5 - Suspension and prolongation of the
project - Art.II.6 - Subcontracting
- Art.II.7 - Reports and deliverables
- Art.II.8 - Evaluation and approval of reports
and deliverables - Art.II.9 - Confidentiality
- Art.II.10 - Communication of data
- Art.II.11 - Information to Member States and
Associated States - Art.II.12 - Publicity
- Art.II.13 - Liability
- Art.II.14 - Assignment
17Annex II - General Conditions Structure
- Part A Implementation of the Project
- SECTION 2 - CONTRACT TERMINATION
RESPONSIBILITY - Art.II.15 - Termination of the contract and
participation of contractors - Art.II.16 - Termination for breach of contract
and irregularity - Art.II.17 - Technical collective responsibility
- Art.II.18 - Financial collective responsibility
18Participation
- New Every legal entity that contributes to the
project (incl. Project Managers) - General Rule Participant contractor
- Every legal entity contributing to a project
must have a contractual link with the Community - Exceptional cases subject to very restrictive
rules - Third parties identified in Annex I (Technical
Annex - Subcontractors
-
19Participation
- Subcontracting
- Contractors shall ensure that the work to be
performed can be carried out by them. - Exception where it is necessary to subcontract
certain elements of the work, this should be
clearly identified in Annex I. - Minor services may be subcontracted
- which do not represent core elements of the
project - which cannot be directly assumed by contractors
- where necessary for the performance of the
project
20Third Parties
- No rights or obligations vis-à-vis EC or other
contractors - Contractor is responsible for
- ensuring all work is carried out
- any IPR generated is protected and used and
available for any necessary access rights (via
subcontract or agreement with third party) - ensuring that third party meets
requirements(auditing etc)
21LIABILITY (1)
- New Collective responsibility of the
contractors - Mechanism by which a contractor may be held
liable, technically and/or financially, fully or
partially, for the action of another contractor - Why?
- Reinforce the protection of the financial
interests of the Community, both quantitative
(only pay what is due to be paid) and qualitative
(ensure that the project continues) - Consequence of FP6 principle of autonomy of the
consortium if the money is granted to the
consortium, which decides on its allocation, then
the consortium as a whole is to be held liable
22LIABILITY (2)
- Implementation applied as a last resort
- Breach of contract
- Depending on the nature of the breach, the
consortium will be invited to find the
appropriate solution (technical responsibility) - If no solution is found, the defaulting
contractor is excluded and the consortium is
requested to continue the project (technical
responsibility with financial consequences) - If the consortium refuses to perform
- 1 - the contract is terminated
- 2 - the consortium is requested to reimburse
money owed by the defaulting contractor
(collective financial responsibility)
23LIABILITY (3)
- Implementation limitations
- Limited in proportion to the participants share
of costs in the project, up to the total payment
they are entitled to receive - IOs, public bodies or entities guaranteed by
MS/AS solely responsible for their own debts - Exceptions for specific actions for SMEs,
fellowships, duly justified cases of specific
support actions - Without prejudice to civil and criminal actions
to be launched against the defaulting contractor
24LIABILITY (4)
- Additional impacts
- Raises awareness among contractors
- 1 - constitution of the consortium
- 2 - projects with real and lasting common
interests (avoid artificial transnational
projects) - 3 - establishment of internal auto-controls and
checks and balances within the consortium - Limits systematic requests for bank guarantees
and performance of ex-ante financial controls - 1 - as foreseen in the new financial
regulations - 2 - depending on the impact of the limitations
(risk assessment - to be detailed in Guidelines
on negotiations)
25Annex II - General Conditions Structure
- Part B Financial provisions
- SECTION 1 - GENERAL FINANCIAL PROVISIONS
- Art.II.19 - Eligible costs of the project
- Art.II.20 - Direct costs
- Art.II.21 - Indirect costs
- Art.II.22 - Cost reporting models
- Art.II.23 - Receipts of the project
- Art.II.24 - Community financial contribution
- Art.II.25 - Reimbursement rates
- Art.II.26 - Audit certificates
- Art.II.27 - Interest yielded by pre-financing
- Art.II.28 - Payment modalities
26Annex II - General Conditions Structure
- Part B Financial provisions
- SECTION 2 - CONTROLS, RECOVERIES AND SANCTIONS
- Art.II.29 - Controls and audits
- Art.II.30 - Liquidated damages
- Art.II.31 - Reimbursement to the commission and
recovery orders
27Annex II - General Conditions Structure
- Part C Intellectual Property Rights
- Art. II.32 - Ownership of knowledge
- Art. II.33 - Protection of knowledge
- Art. II.34 - Use and dissemination
- Art. II.35 - Access rights
- Art. II.36 - Incompatible or restrictive
commitments
28IPR - General Concepts
- Definitions no major change compared to FP5
- knowledge, pre-existing know-how, use,
dissemination, ... - Ownership no major changes compared to FP5
- resides with the contractor (incl. JRC)
generating knowledge - exception for SME actions cooperative research
- SMEs own results not the RTD Performers - collective research - SME associations own
results - transfer of ownership prior notice to other
participants Commission (possible objection
within 30 days) - public procurement (Commission owns results)
29IPR - General Concepts
- Protection
- Where there is commercial application and subject
to legitimate interests, it is a requirement to
protect - Where there is no protection, Commission may
protect - Publication
- allowed if not detrimental to protection
- prior notice to Commission other contractors
(possible objection within 30 days) - Use / dissemination
- Obligation to use and disseminate
- Commission may disseminate itself if needed
30Access Rights
- General principles
- Granted on written request, access rights for use
of anothers results only where necessary (not by
right) - No sub-licensing (unless explicitly agreed
possible optional clause for software) - Obligatory Access Rights between contractors
limited to what they really need (either for
carrying out the project or for using their own
knowledge) but broader Access Rights may be
freely negotiated - Access Rights granted to third parties
Commission may object
31FP6 System of Access Rights
Access rights to
Access rights to
pre-existing know-how
knowledge
If a contractor needs them for carrying out its
own work under the project
For carrying out the project
Royalty-free unless otherwise agreed before
signing the contract
Royalty-free
If a contractor needs them for using its own
knowledge
For use (exploitation further research)
Non-discriminatory conditions to be agreed
Royalty-free unless otherwise agreed before
signing the contract
Possibility for participants to agree on
exclusion of specific pre-existing know-how
before signature of the contract (or before
entry of a new participant)
32Model Contract Web site
- Contracts and translations
- Rules for participation
- Guide to Amendments of contracts
- Special clauses and Guide to special clauses
- Guide to Financial issues
- Frequently Asked Questions
- IPR Guide and Guide to Article II.35.1.b
- Consortium agreement checklist
- Negotiation documents (CPF/guidance notes)
- http//europa.eu.int/comm/research/fp6/model-contr
act/index_en.html