Title: BEPCII Prealignment Installation Survey and Alignment
1BEPCII Prealignment Installation Survey and
Alignment
- Accelerator Center of IHEP
- Xiaolong Wang
- 2007.5.3
2Brief introduction of BEPCII Alignment
- BEPCII alignment can be divided into three parts,
calibration magnets, prealignment installation
and tunnel survey and alignment. - As BEPCII is constructed in the existing BEPC
tunnel, the space for survey and installation is
very narrow. So we arranged calibration magnets
and prealignment installation in a hall outside
of the tunnel. - There are 84 cells need to do prealignment
installation ,and it was started on August 2005
and finished on August 2006.
3BEPCII Prealignment Installation introduction
- We arranged two groups to do magnets calibration
and prealignment installation together. Each
group includes two alignment technicians and two
workers. Beside these, a lift worker worked for
these two groups. - Measurement devices are laser tracker, leica NA2
and electronic gradienter. - The components need to install in a cell
generally are dipole, quadruple, sextuple, BV
magnet, vacuum system, girder and so on. - Each time can install two cells and finished in
4-5 days.
4BEPCII Prealignment Installation introduction
- According to the sequence of the prealignment, it
includes calibration magnets, install magnets on
the girder, roughly adjust the magnets, install
vacuum system, precisely adjust the magnets and
the vacuum chamber, fix the magnets and the
vacuum system to the girder, lifting and
transport the cell to the tunnel. - We use laser tracker to do magnets calibration.
Through measuring the fiducial planes and the
fiducal points on the magnet, we can construct a
frame for the magnet, in this frame we can get
the coordinates of the fiducal points.
5BEPCII Prealignment Installation introduction
Calibration dipole
Prealignment cell
Calibration sextuple
6BEPCII Prealignment Installation introduction
- Accelerator physics requires dipoles Roll
tolerance should be 0.1mrad, its can not be
realized only with laser tracker. We use leica
NA2 and electronic gradienter to do the Roll
calibration.
Electronic gradienter
Target
Leica NA2
Fiducial plane
Adjust the lower pole to level
Measure dipoles Roll
7BEPCII Prealignment Installation introduction
- After get the calibration coordinates of the
magnets that are installed in one cell, we should
calculate the nominal coordinates of these
magnets. For each cell, we constructed a frame.
The frames origin is on the center of the
dipole, z points to the beam direction, y
vertically points to the up, right hand
coordinate system. According to the parameters
given by accelerator physics we can convert these
calibration coordinates to the nominal
coordinates in the cell frame. - After get the nominal coordinates, we input them
into the laser tracker and then survey and adjust
the magnets to the required installation
precision.
8BEPCII Prealignment Installation introduction
- We found temperature change can markedly
influence the precision of the magnets position.
Its necessary to do some correction to the
nominal coordinates. - Through longtime experiment, we got an
appropriate correctional coefficient, each time
before adjustment, we use this coefficient
multiply the nominal coordinates to do the
correction.
9BEPCII Prealignment Installation introduction
- Requirement of magnets calibration and
prealignment installation precision.
X (mm) Y (mm) Z (mm)
quadruple 0.05-0.08 0.05-0.08 0.08
sextuple 0.05-0.08 0.05-0.08 0.08
BV magnet 0.15 0.15 0.15
vacuum chamber 0.5 0.3 0.5
X (mm) Y (mm) Z (mm)
dipole 0.1 0.1 0.15
quadruple 0.04 0.04 0.1
sextuple 0.05 0.05 0.1
BV magnet 0.15 0.15 0.15
magnets calibration precision
prealignment installation precision
10BEPCII storage rings alignment introduction
Storage Ring 240 meters long
LINAC, 202 meters long
Beijing Synchrotron Radiation Facility
Two transport lines, total 160 meters long
Beijing Spectrometer
Beijing Synchrotron Radiation Facility
11BEPCII storage rings alignment introduction
- The BEPCII Surface Network consists of 4
permanent monuments named T65P, T65E, L101 and
L102. We use T65P and T65E to control the storage
ring position, use the L101 and L102 to control
the LINAC position.
LINAC
Storage Ring
Transport Line
230 meters
Two permanent points to control ring
Y
Two permanent points to control LINAC
X
12BEPCII storage rings alignment introduction
- LINAC alignment was finished in 2005, here only
introduce the storage rings installation and
alignment. - We layout a three dimensional control network in
storage rings tunnel, measure its horizontal
coordinate with total station and laser tracker,
measure its vertical coordinate with level, and
then we measure and adjust the components
position with laser tracker relative to the three
dimension network.
13The Alignment Tolerance(rms)
- The global point error of horizontal network is
0.82mm - The relative point error of horizontal network
between two adjacent control point is 0.08mm. - The global point error of vertical network is
0.33mm - The relative point error of vertical network
between two adjacent control point is 0.06mm. - The global position accuracy of equipment in
horizontal is 0.82mm and vertical is 0.33mm. - The relative position accuracy of equipments in
horizontal and vertical is 0.15mm
14BEPCII storage rings alignment introduction
- The surface network in horizontal consist of 37
main control points. - In collision area (from R25 to R30) and aisle
area (R37,R1,R17,R18 ), we have to measure
between long distance and the interference to
measurement is great, so we use total station
TDA5005 to measure the surface network. It needs
about 5 days.
The surface network of the BEPCII storage rings
15BEPCII storage rings alignment introduction
We use the total station of Leica TDM5005 to
survey the surface network in horizontal in
forced centering mode on the ground.
- The total station was centered on the point to
measure the directions and distances of other
points like the figure. The triangulation
measurement accuracy of the total station is 2.2
seconds. The distance measurement accuracy of the
total station is 0.17mm.
16BEPCII storage rings alignment introduction
- In the arc area, we have good measurement
environment, so use laser tracker to measure the
surface network can be efficiently.
monuments on the wall .about 1.8m high
Laser tracker .
- The floor and wall of storage rings tunnel was
populated with 3 dimensional monuments
monuments on floor along the girder . intervals
are about 3.5m
monuments on floor along the foot of the wall .
The Cut View of Tunnel
17BEPCII storage rings alignment introduction
Laser tracker station
- Each station, laser tracker measures two front
sections and three back sections. In one station
20 monuments can be measured. - It needs about 10-12 days to finish the network
survey by laser tracker.
monuments
Laser tracker surveys tunnel network
18BEPCII storage rings alignment introduction
Optical tooling scale for measuring height of
wall monument
- We use the Leica NA2 level to measure the
vertical coordinate of the tunnel network. - The level is setup along tunnel at intervals of 7
meters to measure the height of every monument in
direct and reversed observation mode.
The leveling staff for measuring the height of
floor monument
19BEPCII storage rings alignment introduction
- The closing error of height in direct and
reversed observation should be less than 0.1mm. - Using shanwei software to do the vertical
coordinate adjustment. - The maximum absolute vertical coordinate error
should be 0.33mm(rms). The maximum relative
vertical coordinate error between adjacent
control points should be 0.06mm.
20BEPCII storage rings alignment introduction
- The construction of 3 dimensional nominal
coordinate of the tunnel network . - The three dimensional coordinate of the network
consists of horizontal coordinate and vertical
coordinate. - The horizontal coordinate stems from a
measurement to the network in horizontal with
total station and tracker. - The vertical coordinate stems from a measurement
to the network in vertical with level.
21BEPCII storage rings alignment introduction
- For the installation and alignment of the storage
ring, we use laser tracker to align the
components with respect to the 3D tunnel control
network, and also improve the alignment accuracy
with level and electronic gradienter . - Before adjust a cell, we first check the position
correlation of the magnets on the girder. If
their correlation occurs to change and dont
satisfied with the requirement, we will readjust
them.
22BEPCII storage rings alignment introduction
- When adjusting the position of a component, we
first use the laser tracker to measure monuments
populated in 3 dimensions adjacent to the
component, and best-fit the actual coordinates of
these monuments to their nominal coordinates of
the network, the standard deviation of the
best-fit should be less than 0.07mm. After the
best-fit of coordinates, the difference between
nominal position and actual position of the
component can be displayed by laser tracker. - Adjust the component until the offsets within
required installation precision. - We measured the tunnel network and components
again after all components of BEPCII storage
rings had been wholly installed, then smoothed
all the components.
23BEPCII storage rings alignment introduction
- Storage rings alignment schedule.
- Jul. 2005 - Aug. 2005 Survey the tunnel network.
- Sep.2005 Oct.2005 Mark beam lines on the tunnel
floor. - Mar.2006 Sep.2006 Storage rings tunnel
installation and alignment. - Oct.2006 Nov.2006 The adjustment to smooth all
the components.
24BEPCII storage rings alignment introduction
- Tolerable displacements for storage ring magnets
(components) defined by the accelerator physics
The circumference of storage rings cannot
deviate from its design value by more than 5mm
the difference between two rings has to be set
within 4mm.
25Summary
- According to the component installation tolerance
of the BEPCII storage rings which accelerator
physics gives, the scheme of every taches had
been carefully studied and the total tolerance
was reasonably distributed to the taches in
course of the component installation. So the
total tolerance of the component installation is
successfully limited in the range of physics
requirement. - Thanks for your attentions !