Title: Asphalt QC 2000
1Asphalt QC 2000
2Topics
- Terminology
- Specifications
- Sampling and Testing
- Reporting/CQR
- Who Does What?
- Lube Oil Change
- All in 20 Minutes!
3In a Nutshell..
- Payment based on Contractors (Quality Control)
test data that has been verified - FDOT runs Verification tests at a lesser
frequency - Split-sample at plant by project personnel
- Independent sample at District Lab
- Payment is based on density on the roadway and
air voids, asphalt content and gradation at the
plant - Percent Within Limits (PWL) larger quantities
- Pay Table smaller quantities
- Big Change!
4General Details Include.
- Initial lot size mandatory 2000 tons
- Following lots may be 2000 or 4000 tons
- Contractors option w/Engineers Approval
- Deleted Initial Production Test Strip No
Pause - Typical lot size 4000 tons
- English and Metric the same
- 4 sublots per lot (1000 tons each)
- Plant lot and roadway lots are the same
- All sampling performed by the Contractor
- FDOT establishes when to sample
- Several options available
5Whos on First?
6General Overview - Plant
- Engineer (VT) directs Contractor (QC) when to
sample - Random basis generated by Excel Spreadsheet
- 1/sublot (1/1000 tons or 1/500 tons)
- QC splits out and boxes up Verification and
Resolution Samples - Tests include
- Asphalt Content (FM 5-563 only)
- Gradation (FM 1-T 030)
- Air Voids (AASHTO TP-4 FM 1-T 209)
7Verification - Plant
- Performed by Agency - FDOT or Consultant (CTQP
Plant Level I) - Tests run at plant
- Split-sample randomly selected 1/lot (1/4000
tons or 1/2000 tons) - Same tests as QC
- Precision statement comparison with QC results
- Gmm, Gmb, Pb, P-200, P-8
8Between-Laboratory Precision Values
9Verification Plant (Contd)
- If all results compare
- Accept material
- Payment based on Contractors QC results
- If the results dont compare
- VT tests remaining sublot samples for property
(or properties) in question. - If only initial unfavorable comparison accept
material and pay based on QC results - If two or more unfavorable Resolution
- Samples sent to District Lab
10Independent Verification - Plant
- District Materials takes two samples per 12,000
tons - Tested at District Lab
- Same tests as QC
- Results have to meet requirements of Master
Production Range - Go or no go.
11(No Transcript)
12Quality Control Sampling and Testing Roadway
- Core locations identified by VT
- Tonnage basis
- Contractor cuts five cores per sublot
- Example 1000 ton sublot, 12 ft wide lane
- 150 lb/sy 1 core/2000 feet
- 200 lb/sy 1 core/1500 feet
- 250 lb/sy 1 core/1200 feet
- 300 lb/sy 1 core/1000 feet
- QC tests cores per FM 1-T 166
- Retains cores for Verification/Resolution
13Verification - Roadway
- Tests performed by Verification Technician
- Tests run at plant
- Same-cores
- VT tests all five cores from a randomly selected
sublot - Same test as QC
- Precision statement comparison with QC results
- Gmb 0.022
- Compare favorably Pay based on QC results
- If not similar to plant Resolution
14Independent Verification Roadway
- District Materials directs Contractor to take
five additional cores from same sublot as plant
IV sample - Results have to meet requirements of Master
Production Range - Average density must meet minimum
- Go or no go.
15Compensation
- If two or less sublots use Small Quantity Pay
Table based on average deviations from target - If three or more sublots use the estimated
Percent Within Limits (PWL) for the lot, based on
the following characteristics - Density
- Air Voids
- AC Content
- P-200
- P-8
16Compensation (Contd)
- Pay factor for each characteristic is determined
- Composite Pay factor is based on
- 35 Density
- 25 Air Voids
- 25 AC Content
- 10 P-200
- 5 P-8
- All calculations by Excel spreadsheet
- Not by hand!
17Reporting
- Contractor reports all QC test results,
quantities, etc. - Daily Asphalt Plant Quality Control Report
- Daily Asphalt Roadway Quality Control Report
- Inputs into CQR
- CEI reports all Verification test results and
Verification activities - Verify mix spread rate, tack spread rate, mix
temperature, etc. - Asphalt Plant Verification Report
- Asphalt Roadway Verification Report
- Inputs into CQR
- Forms currently under development
- CQR access through District Construction Office
18Other Related Issues
- Implementation date July 2002 Letting
- All projects
- No Type S/FC-3 projects
- Specification only works with Superpave
- FC-9.5 FC-12.5 (FC-6) accepted per 334
- FC-5 specified in 337
- Tolerances based on FC-5 construction data
- Pay factors weighted differently
- Criteria 3/8 No.4 No. 8 sieve, and Binder
Content - Specification Refresher Course
19Thank You!
20Upcoming Specification Changes
21General
- The following Sections are sunset (but will
still be in the book) - 280 Asphalt Base Courses
- 331 Type S Asphalt Concrete, Quality Assurance
and Acceptance Procedures - 332 Type II Asphaltic Concrete
- 333 Type III Asphaltic Concrete
- 335 Sand-Asphalt Hot Mix
22New Specs
- 234 Superpave Asphalt Base
- Designated B-12.5
- SP-12.5 mix,
- TL B or C
- Fine Graded
- May substitute an SP-12.5 in lieu of B-12.5
- Accepted per 334 (QC 2000)
- Thickness determined by spread rate, not coring
23Changes
- 300 Prime and Tack Coats for Base Courses
- Contractor measures application rate of prime and
tack coats (twice per day) and provides basic QC - RA 500 replaces AC-5
- Can use in day or night
- 327 Milling of Existing Asphalt Pavement
- QC requirement to check cross-slope every 250
24More changes.
- 330 Hot Bituminous Mixtures - General
Construction Requirements - Specific Contractor QC requirements
- In addition to Section 105
- New temperature spec
- No paving in the rain
- Control of cross-slope
25Still more changes.
- 337 Asphalt Concrete Friction Courses
- FC-2, FC-3 will sunset
- FC-5 OGFC
- Placement temp down to 60F if good texture
- FC-9.5 new 9.5 mm friction course mix
- Placed 1 thick
- FC-12.5 (FC-6)
- Renamed FC-6
- FC-9.5 12.5 will require 100 polish resistant
aggregate - Exception 60 granite
26QC 2000 - Asphalt
- Welcome
- to the Real World.
27Industry Perspective QC 2000 Asphalt
Specifications
- Jim Warren
- Asphalt Contractors Association of Florida, Inc.
28Contractor perspectives
- Old
- What good will this do?
- Oh No!, Not another new specification!
- Lets go back to S-1
- Now
- Its no so bad I see some positives.
- Were trained, were equipped Lets Roll!
- Opportunities
29What's different from the old system?
- Same Superpave Mix as before
- Still going to test it the same way no new
tests - More QC responsibilities than before
- Must change focus from average to uniformity
about average (big change) - Its still Hot, Black, and Sticky.
30Whats in it for the contractor?
- More flexibility to run your operation.
- More responsibility and authority to make sure
the job is done right. - Less reliance of others for decisions of when to
pave, adjustments to make, etc. - Less rework, fewer call-backs, less wasted
profits and opportunity costs. - QC tests finally mean something.
- Finally, a payback for investing in QC personnel
and equipment. - Mo money (if you know what youre doing).
31Whats in it for the Industry?
- Levels the playing field for bidding.
- Improves the image of the Industry
Asphalt is State-Of-The-Art. - Continuously improving our product You want it?
We can deliver on time, on budget. - Eliminates lesser products from gaining a
foothold in our market. - Secures and protects the highway asphalt paving
market due to superior performance and lower
life-cycle cost.
32What does Industry need to do to make it work?
- Educating your crews Its not business as
usual anymore This aint no S-1 Think P401. - Stress the importance of attention to detail
Every ton counts! - Mgmt. Attitude you can make this work!
- If you believe it, exude it it will happen.
- Attend the refresher course A Gotta! Get up to
speed faster through a better understanding of
the specification.
33Making it Work!
- Schwartzkoff Rule 13 When placed in command
take charge - Warren Corollary to Rule 13 When placed in
leadership, lead! - Mgmt. Attitude you can make this work!
- If you believe it, exude it it will happen.
- Every Ton Counts!
34Whats in it for the Agency?
- Better, more reliable product.
- No need to look anywhere else for products.
- Flexibility to inspect where needed
- Less spent on inspection means more for
product (asphalt, bridges, etc.) - Meets the National goal of Get In, Do the Job,
Get Out and Stay Out - Schwartzkoff Rule 14 Do the Right Thing
- Warren Corollary to Rule 14. Add the First
Time
35What does the Agency need to do make it work?
- Have some patience change takes time big
changes dont happen overnight. - Cooperate during the transition
- Expect some mistakes, be willing to work them out
- Attend the refresher course get up to speed
faster through better understanding of the
specification.
36Refresher Course Objective
- The objective of this 1-day program is to
familiarize the participant with the new QC2000
asphalt specifications. Upon completion of this
program, the participant will be able to - - Identify whats different under these new
specifications compared to current
specifications, - - Understand the respective roles and duties of
the parties involved, and - - Understand the acceptance process.
37Refresher Course Agenda
- Introduction
- Definitions
- Review Specifications
- (234, 285, 320, 330, 334, 337)
- The Matrix
- Walking through the Plant Roadway
- Checks Balances
- Calculations and Spreadsheet
- Forms, Case Studies, QA
- Quiz
38(No Transcript)
39Whats in it for the Taxpayer?
- The Smooth Ride
- Achievable Goals
- No rutting
- No cracking
- No potholes
- Renewable Surface (roof) as part of entire paving
system. - A pavement that delivered the biggest bang for
the buck that lasts. - The Best Paving Product second to none.