Asphalt QC 2000 - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Asphalt QC 2000

Description:

Independent sample at District Lab ... Independent Verification - Plant. District Materials takes two samples per 12,000 tons ... Independent Verification. Roadway ... – PowerPoint PPT presentation

Number of Views:182
Avg rating:3.0/5.0
Slides: 34
Provided by: fdot
Category:

less

Transcript and Presenter's Notes

Title: Asphalt QC 2000


1
Asphalt QC 2000
  • The Adventure Begins.

2
Topics
  • Terminology
  • Specifications
  • Sampling and Testing
  • Reporting/CQR
  • Who Does What?
  • Lube Oil Change
  • All in 20 Minutes!

3
In a Nutshell..
  • Payment based on Contractors (Quality Control)
    test data that has been verified
  • FDOT runs Verification tests at a lesser
    frequency
  • Split-sample at plant by project personnel
  • Independent sample at District Lab
  • Payment is based on density on the roadway and
    air voids, asphalt content and gradation at the
    plant
  • Percent Within Limits (PWL) larger quantities
  • Pay Table smaller quantities
  • Big Change!

4
General Details Include.
  • Initial lot size mandatory 2000 tons
  • Following lots may be 2000 or 4000 tons
  • Contractors option w/Engineers Approval
  • Deleted Initial Production Test Strip No
    Pause
  • Typical lot size 4000 tons
  • English and Metric the same
  • 4 sublots per lot (1000 tons each)
  • Plant lot and roadway lots are the same
  • All sampling performed by the Contractor
  • FDOT establishes when to sample
  • Several options available

5
Whos on First?
6
General Overview - Plant
  • Engineer (VT) directs Contractor (QC) when to
    sample
  • Random basis generated by Excel Spreadsheet
  • 1/sublot (1/1000 tons or 1/500 tons)
  • QC splits out and boxes up Verification and
    Resolution Samples
  • Tests include
  • Asphalt Content (FM 5-563 only)
  • Gradation (FM 1-T 030)
  • Air Voids (AASHTO TP-4 FM 1-T 209)

7
Verification - Plant
  • Performed by Agency - FDOT or Consultant (CTQP
    Plant Level I)
  • Tests run at plant
  • Split-sample randomly selected 1/lot (1/4000
    tons or 1/2000 tons)
  • Same tests as QC
  • Precision statement comparison with QC results
  • Gmm, Gmb, Pb, P-200, P-8

8
Between-Laboratory Precision Values
9
Verification Plant (Contd)
  • If all results compare
  • Accept material
  • Payment based on Contractors QC results
  • If the results dont compare
  • VT tests remaining sublot samples for property
    (or properties) in question.
  • If only initial unfavorable comparison accept
    material and pay based on QC results
  • If two or more unfavorable Resolution
  • Samples sent to District Lab

10
Independent Verification - Plant
  • District Materials takes two samples per 12,000
    tons
  • Tested at District Lab
  • Same tests as QC
  • Results have to meet requirements of Master
    Production Range
  • Go or no go.

11
(No Transcript)
12
Quality Control Sampling and Testing Roadway
  • Core locations identified by VT
  • Tonnage basis
  • Contractor cuts five cores per sublot
  • Example 1000 ton sublot, 12 ft wide lane
  • 150 lb/sy 1 core/2000 feet
  • 200 lb/sy 1 core/1500 feet
  • 250 lb/sy 1 core/1200 feet
  • 300 lb/sy 1 core/1000 feet
  • QC tests cores per FM 1-T 166
  • Retains cores for Verification/Resolution

13
Verification - Roadway
  • Tests performed by Verification Technician
  • Tests run at plant
  • Same-cores
  • VT tests all five cores from a randomly selected
    sublot
  • Same test as QC
  • Precision statement comparison with QC results
  • Gmb 0.022
  • Compare favorably Pay based on QC results
  • If not similar to plant Resolution

14
Independent Verification Roadway
  • District Materials directs Contractor to take
    five additional cores from same sublot as plant
    IV sample
  • Results have to meet requirements of Master
    Production Range
  • Average density must meet minimum
  • Go or no go.

15
Compensation
  • If two or less sublots use Small Quantity Pay
    Table based on average deviations from target
  • If three or more sublots use the estimated
    Percent Within Limits (PWL) for the lot, based on
    the following characteristics
  • Density
  • Air Voids
  • AC Content
  • P-200
  • P-8

16
Compensation (Contd)
  • Pay factor for each characteristic is determined
  • Composite Pay factor is based on
  • 35 Density
  • 25 Air Voids
  • 25 AC Content
  • 10 P-200
  • 5 P-8
  • All calculations by Excel spreadsheet
  • Not by hand!

17
Reporting
  • Contractor reports all QC test results,
    quantities, etc.
  • Daily Asphalt Plant Quality Control Report
  • Daily Asphalt Roadway Quality Control Report
  • Inputs into CQR
  • CEI reports all Verification test results and
    Verification activities
  • Verify mix spread rate, tack spread rate, mix
    temperature, etc.
  • Asphalt Plant Verification Report
  • Asphalt Roadway Verification Report
  • Inputs into CQR
  • Forms currently under development
  • CQR access through District Construction Office

18
Other Related Issues
  • Implementation date July 2002 Letting
  • All projects
  • No Type S/FC-3 projects
  • Specification only works with Superpave
  • FC-9.5 FC-12.5 (FC-6) accepted per 334
  • FC-5 specified in 337
  • Tolerances based on FC-5 construction data
  • Pay factors weighted differently
  • Criteria 3/8 No.4 No. 8 sieve, and Binder
    Content
  • Specification Refresher Course

19
Thank You!
20
Upcoming Specification Changes
  • July 2002 Letting

21
General
  • The following Sections are sunset (but will
    still be in the book)
  • 280 Asphalt Base Courses
  • 331 Type S Asphalt Concrete, Quality Assurance
    and Acceptance Procedures
  • 332 Type II Asphaltic Concrete
  • 333 Type III Asphaltic Concrete
  • 335 Sand-Asphalt Hot Mix

22
New Specs
  • 234 Superpave Asphalt Base
  • Designated B-12.5
  • SP-12.5 mix,
  • TL B or C
  • Fine Graded
  • May substitute an SP-12.5 in lieu of B-12.5
  • Accepted per 334 (QC 2000)
  • Thickness determined by spread rate, not coring

23
Changes
  • 300 Prime and Tack Coats for Base Courses
  • Contractor measures application rate of prime and
    tack coats (twice per day) and provides basic QC
  • RA 500 replaces AC-5
  • Can use in day or night
  • 327 Milling of Existing Asphalt Pavement
  • QC requirement to check cross-slope every 250

24
More changes.
  • 330 Hot Bituminous Mixtures - General
    Construction Requirements
  • Specific Contractor QC requirements
  • In addition to Section 105
  • New temperature spec
  • No paving in the rain
  • Control of cross-slope

25
Still more changes.
  • 337 Asphalt Concrete Friction Courses
  • FC-2, FC-3 will sunset
  • FC-5 OGFC
  • Placement temp down to 60F if good texture
  • FC-9.5 new 9.5 mm friction course mix
  • Placed 1 thick
  • FC-12.5 (FC-6)
  • Renamed FC-6
  • FC-9.5 12.5 will require 100 polish resistant
    aggregate
  • Exception 60 granite

26
QC 2000 - Asphalt
  • Welcome
  • to the Real World.

27
Industry Perspective QC 2000 Asphalt
Specifications
  • Jim Warren
  • Asphalt Contractors Association of Florida, Inc.

28
Contractor perspectives
  • Old
  • What good will this do?
  • Oh No!, Not another new specification!
  • Lets go back to S-1
  • Now
  • Its no so bad I see some positives.
  • Were trained, were equipped Lets Roll!
  • Opportunities

29
What's different from the old system?
  • Same Superpave Mix as before
  • Still going to test it the same way no new
    tests
  • More QC responsibilities than before
  • Must change focus from average to uniformity
    about average (big change)
  • Its still Hot, Black, and Sticky.

30
Whats in it for the contractor?
  • More flexibility to run your operation.
  • More responsibility and authority to make sure
    the job is done right.
  • Less reliance of others for decisions of when to
    pave, adjustments to make, etc.
  • Less rework, fewer call-backs, less wasted
    profits and opportunity costs.
  • QC tests finally mean something.
  • Finally, a payback for investing in QC personnel
    and equipment.
  • Mo money (if you know what youre doing).

31
Whats in it for the Industry?
  • Levels the playing field for bidding.
  • Improves the image of the Industry
    Asphalt is State-Of-The-Art.
  • Continuously improving our product You want it?
    We can deliver on time, on budget.
  • Eliminates lesser products from gaining a
    foothold in our market.
  • Secures and protects the highway asphalt paving
    market due to superior performance and lower
    life-cycle cost.

32
What does Industry need to do to make it work?
  • Educating your crews Its not business as
    usual anymore This aint no S-1 Think P401.
  • Stress the importance of attention to detail
    Every ton counts!
  • Mgmt. Attitude you can make this work!
  • If you believe it, exude it it will happen.
  • Attend the refresher course A Gotta! Get up to
    speed faster through a better understanding of
    the specification.

33
Making it Work!
  • Schwartzkoff Rule 13 When placed in command
    take charge
  • Warren Corollary to Rule 13 When placed in
    leadership, lead!
  • Mgmt. Attitude you can make this work!
  • If you believe it, exude it it will happen.
  • Every Ton Counts!

34
Whats in it for the Agency?
  • Better, more reliable product.
  • No need to look anywhere else for products.
  • Flexibility to inspect where needed
  • Less spent on inspection means more for
    product (asphalt, bridges, etc.)
  • Meets the National goal of Get In, Do the Job,
    Get Out and Stay Out
  • Schwartzkoff Rule 14 Do the Right Thing
  • Warren Corollary to Rule 14. Add the First
    Time

35
What does the Agency need to do make it work?
  • Have some patience change takes time big
    changes dont happen overnight.
  • Cooperate during the transition
  • Expect some mistakes, be willing to work them out
  • Attend the refresher course get up to speed
    faster through better understanding of the
    specification.

36
Refresher Course Objective
  • The objective of this 1-day program is to
    familiarize the participant with the new QC2000
    asphalt specifications. Upon completion of this
    program, the participant will be able to
  • - Identify whats different under these new
    specifications compared to current
    specifications,
  • - Understand the respective roles and duties of
    the parties involved, and
  • - Understand the acceptance process.

37
Refresher Course Agenda
  • Introduction
  • Definitions
  • Review Specifications
  • (234, 285, 320, 330, 334, 337)
  • The Matrix
  • Walking through the Plant Roadway
  • Checks Balances
  • Calculations and Spreadsheet
  • Forms, Case Studies, QA
  • Quiz

38
(No Transcript)
39
Whats in it for the Taxpayer?
  • The Smooth Ride
  • Achievable Goals
  • No rutting
  • No cracking
  • No potholes
  • Renewable Surface (roof) as part of entire paving
    system.
  • A pavement that delivered the biggest bang for
    the buck that lasts.
  • The Best Paving Product second to none.
Write a Comment
User Comments (0)
About PowerShow.com