Title: Critical Area Mapping Update on Pilot Project
1Critical Area MappingUpdate on Pilot Project
- Local Critical Area Planners
- Quarterly Meeting
- October 23, 2008
2Critical Area MappingExisting Maps Arent Current
- Existing paper maps are 20 years old
- Maps were never ortho-rectified or georeferenced
- Methodologies varied
- Maps of municipalities are inadequate
- Shoreline and wetland changes have occurred
- Sea level rise has affected wetland acreage
3Critical Area MappingBetter Graphic Information
- Electronic maps need to match the landscape
- Need to be web accessible
- Shoreline and edge of wetlands should be based on
current data - 1,000 boundary should be digitally created and
georeferenced
4HB 1253 Includes Mapping Provisions
- Requires change from Critical Area as delineated
on 1972 Wetlands Maps to Critical Area as
delineated on Statewide Base Map - Aerial imagery from 2007 2008 is Base Map
- Boundary to be accurate to a scale of 11200 (1
100) - Shoreline and edge of wetlands to be identified
by the State with local input - Imagery, CIR imagery, 1972 Wetlands Maps, DNR
Wetlands Maps are being used
5HB 1253 Includes Mapping Provisions
- Consistent methodology and source data to be used
in all jurisdictions - CA Boundary to be digitally generated and
georeferenced - Edge match problems among jurisdictions will be
eliminated - Pilot project to be used to determine procedures,
identify source documents, and facilitate the
development of regulations - Regulations will address many aspects of the
mapping effort - Mapping methodology
- Shoreline/wetland changes
- Designation of new areas added into the
Critical Area - Property owner notification
6Mapping IssueOpen Water Areas Filled
- Determine if fill was legally permitted
- Use aerial imagery to determine boundary of
upland - CA boundary adjusted appropriately (waterward)
- Land area to be classified based on time of fill,
permit requirements, justification, and land use
as of original mapping date or July 1, 2008
7Open Water Areas FilledHart-Miller Island
- Islands eroded over time and are being restored
- State lands
- Will be classified as not intensely developed and
will generate growth allocation
8Mapping IssueAreas Excavated New Tidal Waters
- Determine if excavation was legally permitted
- Use aerial imagery and other source data to
determine boundaries of open water and wetlands - CA boundary adjusted appropriately (inland)
- Mapping software will determine acreage changes
in RCA, LDA, or IDA
9Mapping IssueNatural Changes in Wetlands
- Areas of wetlands converted to open water due to
storm events, erosion, sea level rise, etc. - Verify configuration and tidal connection
- Critical Area boundary may or may not change
10Mapping IssueNetwork of Islands Changed
- Identify changes in upland and wetland areas
- Use aerial imagery and other source data to
determine boundary of upland - Consider Countys original mapping
- CA boundary may be affected
- Upland areas to be classified the same as they
were originally
11Mapping IssueShoreline Has Substantially Eroded
- Use aerial imagery to determine boundary of
upland - Knowledge of shoreline condition (low cliff, high
cliff, undercut, etc.) helpful - CA boundary will move landward (to maintain 1,000
feet) - Old shoreline and boundary will still be shown on
the draft maps for information, comparison,
discussion purposes - New area will be classified based on land use
as of July 1, 2008
12Mapping IssueShoreline Has Substantially Eroded
13Mapping IssueAreas Mapped IDA are Less Than 20
Acres
- Several areas mapped as IDA are less than 20
acres - Appear to be an error in original mapping
- Commission will not require a correction of the
designation - Correction of errors -local government
coordination
14Mapping IssueVerifying Head of Tide Determination
- Common issue throughout maps
- Complex to address historical knowledge is
necessary - Some wetland areas have changed
- Using all map resources and heads-up digitizing
and analysis to make a determination - Analyze evidence of change related to
obstructions, storm events, beach erosion, etc. - Limited ground truthing will be necessary in
areas where there is significant change
15Mapping IssueVerifying Head of Tide Determination
16Mapping IssueChange in Extent of Wetlands
- Most common problem
- Numerous review points identified
- All map resources and vegetation analysis used to
make determination - Historical knowledge, project data, old aerial
imagery, and topographic data may be used - Ground truthing will be necessary in some areas
17Mapping IssueChange in Extent of Wetlands
18Mapping Schedule
- Baltimore County shoreline and wetlands review
almost complete - Final review underway
- New Critical Area boundary can then be generated
- Apply existing classifications
- Classify new areas
- Final analysis, quality control review, acreage
calculations - Final map prepared for local review and public
input January 2009 - Talbot County mapping approximately 60 days
behind Baltimore