Regals New Rigs Delivered as Advertised - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Regals New Rigs Delivered as Advertised

Description:

Top Drive, Casing Stabbing Board and Derrickman Working Platform (Monkey Board) being rigged up ... of the rig against snow and frost to ensure operations ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 24
Provided by: harryv
Category:

less

Transcript and Presenter's Notes

Title: Regals New Rigs Delivered as Advertised


1
Regals New RigsDelivered as Advertised
2
Index
  • 3 Commitment
  • 4 Background
  • 6 Rig Assembly in USA
  • 8 Rig Commissioning in USA
  • 9 Shipment of 1st Rig
  • 10 1st Rig Arrival in the Ukraine
  • 11 Arrival of 2nd Rig
  • 12 Base Camp Construction
  • 15 Camp Facilities
  • 16 Equipment Arriving on Location
  • 18 Erection of 1st Rig in Ukraine
  • 23 Assembly of 2nd Rig in Ukraine

2
Regals New Rigs 2008
3
Commitment
  • In the first quarter of 2008 Regal Petroleum
    committed to a 5-year contract with Saipem SpA
    for 2 new-build 2000 horse power drilling rigs
    as the first step towards further development of
    the Companys assets in the Ukraine.

Kiev ____
  • ___Regal Licences

3
Regals New Rigs 2008
4
Background
  • Regal Petroleum decided to change over from
    locally available rigs to new-build
    high-performance rigs to improve overall drilling
    performance in the Ukraine and thus realise the
    full potential of the Companys assets.
  • Previously a typical 5000m well would take
    between 10 to 11 months drilling time while the
    expectation for the new-build rigs is to
    eventually be able to drill to 5000m in less
    than 6 months.
  • Reducing the drilling time has a significant
    impact on the economics of the field development,
    including accelerating production, which has a
    direct, positive impact on the net present value
    (NPV) of the project.

Regals New Rigs 2008
5
Background
  • The new rigs will also be able to explore the
    deeper objectives beyond 6000m, which are part of
    the current development plan.
  • The rigs will be managed by Saipem SpA, a well
    known international drilling contractor
    (www.saipem.eni.it).
  • The new rigs have been built by LeTourneau in
    Houston, USA. During the construction of the
    rigs, both Saipem and Regal have been actively
    involved in the design.
  • To meet the Companys targets, reduce the lead
    time on the construction of the rigs and prevent
    slippage, the manufacturing and assembly process
    was carried out around the clock.

Regals New Rigs 2008
6
Rig Assembly
  • LeTourneau Factory, Houston
  • Completed drilling rig components ready for
    transportation to designated site for testing and
    commissioning

? Each rig is supplied with a total of 3 mud pumps
? Hinged A-Frame mast section ready to be
assembled for commissioning and testing
Regals New Rigs 2008
7
Rig Assembly
  • To prevent any delay during the erection of the
    rigs in the Ukraine and down-time during
    operations, a significant amount of key Saipem
    personnel were trained by LeTourneau in Houston.
    In addition, prior to the shipment to the
    Ukraine, both rigs were fully assembled and
    tested with the key Saipem personnel present on a
    designated site in Houston.
  • The total time from start of the build to the
    last item loaded for shipment for 2 rigs was
    approx. 5 months a record performance for both
    LeTourneau and Saipem.
  • The first rig arrived in the Ukraine on the 23th
    September 2008.

Regals New Rigs 2008
8
Rig Commissioning in Houston
  • LeTourneau (Lewco) Assembly Yard, Houston
  • Prior to shipment, both rigs and all the
    equipment were fully assembled and commissioned
    in the presence of Saipem and all the different
    suppliers and manufacturers.
  • Any required rectifications and interface issues
    were immediately addressed and completed prior to
    shipment.

Regals New Rigs 2008
9
Shipment of 1st Rig
  • First rig loaded on the MV Peru in Houston

Regals New Rigs 2008
10
Arrival of 1st Rig
  • First rig arrived in the Ukraine on the 23rd
    September 2008

Regals New Rigs 2008
11
Arrival of 2nd Rig
  • The second rig arrived in the Ukraine on the 23rd
    October 2008 and erection commenced on the 17th
    November.
  • In addition to the two rigs, a drilling base camp
    had to be constructed to house approx. 200
    people. Purpose built accommodation units were
    imported from Italy.
  • This base camp is fully equipped with messing
    facilities, recreation facilities and a clinic
    with a full-time doctor. Both the camp and the
    rig are fully winterised to ensure continuous
    operations during severe winter conditions.
  • Saipem obtained a drilling licence for the
    Ukraine and are operating as a Ukrainian
    Licensed Drilling Company Saipem Ukraine LLC.

Regals New Rigs 2008
12
Base Camp Under Construction
  • The Saipem Base Camp includes a recreation area
    and a permanently staffed medical clinic

Regals New Rigs 2008
13
Base Camp Completed
The living quarters are near completion and
waiting for staff to move in during December 2008
13
Regals New Rigs 2008
14
Base Camp Completed
  • Junior accommodation facilities
  • ? Paramedics are permanently stationed on the rig
    site for support

14
Regals New Rigs 2008
15
Camp Facilities
Catering facility for 200 people
15
Regals New Rigs 2008
16
Equipment Arriving on Location
Regals New Rigs 2008
17
Equipment Arriving on Location
Draw Works, Mud Pumps and Generators
Regals New Rigs 2008
18
Erection of 1st Rig in Ukraine
Top Drive, Casing Stabbing Board and Derrickman
Working Platform (Monkey Board) being rigged up
Regals New Rigs 2008
19
Erection of 1st Rig in Ukraine
Assembly of the Substructure Mast and Top Drive
Regals New Rigs 2008
20
Erection of 1st Rig in Ukraine
Regals Supervisor, Gregoriy Lekhwar,
overseeing the assembly of the Mast and
inspecting the instrumentation in the Drillers
Cabin.
Regals New Rigs 2008
21
Erection of 1st Rig in Ukraine
  • First time raising of the mast (Well MEX-106 Rig
    5914)

Regals New Rigs 2008
22
Erection of 1st Rig in Ukraine
Installation of Winterisation (Well MEX-106 Rig
5914)
  • Winterisation is the covering and protection of
    the main parts of the rig against snow and frost
    to ensure operations can continue during winter.
  • A steam plant permanently heats the rig and
    rig systems during the winter.
  • The winterisation has been designed to stand up
    to a temperature of -20 Celsius.

Regals New Rigs 2008
23
Assembly of 2nd Rig in Ukraine
  • Key components being positioned for assembly of
    Rig 2 (Well SV-58 Rig 5915)

Regals New Rigs 2008