Cost and Energy Impacts of Fish and Wildlife Operations - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Cost and Energy Impacts of Fish and Wildlife Operations

Description:

Summer draft limits at Coulee, Libby, Horse and Dworshak. Bypass Spill (purpose) ... Libby and Horse Integrated Rule Curves. Little Goose Spring Spill. Grand ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 21
Provided by: johnf77
Category:

less

Transcript and Presenter's Notes

Title: Cost and Energy Impacts of Fish and Wildlife Operations


1
Cost and Energy Impacts ofFish and Wildlife
Operations
  • NW Power Planning Council
  • April 3, 2002
  • Boise, Idaho

2
Why are we doing this?
  • To help the Council focus on where best to spend
    research money.
  • To help prioritize fish and wildlife measures in
    the event that some may have to be curtailed for
    power emergencies.
  • To help the Council choose between two or more
    alternatives that achieve the same biological
    objectives.

3
What is it?
  • Each component of the fish and wildlife main-stem
    operation is analyzed separately.
  • Each scenario has one and only one component
    removed from (or added to) current operations.
  • We observe the average monthly change in
    generation and the cost for each component.

4
What is it not?
  • A cost/benefit analysis for fish and wildlife
    measures
  • An integration of fish wildlife and power
    planning
  • A balancing of power and fish wildlife needs

5
Caveats
  • Not all components were examined
  • Components are not independent
  • The cost of removing two components at the same
    time is not the same as the sum of the cost of
    each separately.
  • Cannot simply add up the cost of all components
    to get the total cost of current operations.

6
Components of a FW Operation
  • Flow Augmentation
  • Reservoir Elevation
  • Bypass Spill

7
Flow Augmentation (purpose)
  • To reduce travel time
  • To keep redds under water
  • To reduce water temperature

8
Flow Augmentation (examples)
  • Chum flows at Bonneville (fall and winter)
  • Vernita Bar flows (winter and spring)
  • Summer flow augmentation (Snake and Columbia)
  • Water releases for temperature control in late
    summer

9
Reservoir Elevation (purpose)
  • Winter fill to store water for flow augmentation
  • Spring-Summer release for flow augmentation
  • Drafting/filling limits for resident fish

10
Reservoir Elevation (examples)
  • Winter fill at Coulee, Libby, Horse and Dworshak
  • VARQ flood control at Libby, Horse and Coulee
  • Integrated Rule Curves at Libby and Horse
  • Coulee retention time operation
  • Summer draft limits at Coulee, Libby, Horse and
    Dworshak

11
Bypass Spill (purpose)
  • Increase survival past dams
  • Most useful at sites w/o guidance systems
  • Coordinate spill with transportation policy

12
(No Transcript)
13
Stable (?) Electricity Prices
14
(No Transcript)
15
Highest Cost Components
  • John Day Summer Spill
  • Bonneville Summer Spill
  • The Dalles Summer Spill
  • John Day Spring Spill
  • The Dalles Spring Spill
  • Ice Harbor Spring Spill
  • Ice Harbor Summer Spill
  • Bonneville Spring Spill
  • Lower Monumental Spring Spill

16
Low Cost Components
  • Grand Coulee Winter Fill
  • Lower Granite Spring Spill
  • Libby and Horse Integrated Rule Curves
  • Little Goose Spring Spill
  • Grand Coulee Summer Draft
  • Libby Summer Draft
  • Dworshak Summer Draft
  • McNary July Flow Augmentation
  • Lower Granite July Flow Augmentation
  • McNary Spring Spill

17
No Cost Components
  • Lower Granite August Flow Augmentation
  • Generally no flow augmentation water is left
  • Upper Snake 427 Kaf Flow Augmentation
  • Libby Winter Fill
  • Dworshak Winter Fill
  • Hungry Horse Winter Fill

18
Revenue Increasing Components
  • McNary August 1-15 Flow Augmentation
  • VarQ Flood Control (Libby, Horse, Coulee)
  • Hungry Horse Summer Draft
  • McNary August 16-31 Flow Augmentation
  • Chum Flows
  • Grand Coulee Retention Time Operation

19
Cost of Spill Changes with Flow
  • When bypass spill is a percentage of outflow
  • When flows are above turbine capacity
  • Forced spill is counted first and does not add to
    the cost of bypass spill
  • Does not change when the gas supersaturation
    limit is reached

20
Bypass Spill vs. Outflow(when spill is a
percentage of outflow)
Write a Comment
User Comments (0)
About PowerShow.com