Title: Hot InPlace Recycling
1The Multi-Stage Solution
The BC HIR Success Story
Celebrating the first 20 Years
Presented by Patrick Wiley
2Todays Content
- Current Situation
- Multi-Stage Recycling
- Project and Contractor Profiles
3A BIG thanks to Ken Fyvie
4Current Situation
- Pavement rehabilitation costs are skyrocketing
- Multi-Stage HIR is a proven solution
- Canadian HIR growth is at a virtual standstill
5Speakers Credentials
- 15 yrs developing HIR equipment
- 5 yrs developing decorative paving products
- Currently VP RD Integrated Paving Concepts Inc
6Speakers Credentials Patents
Two-Stage HIR Process
Co-invented with Al Rorison
7Speakers Credentials Patents
Hot Air IR Heater
Heat Stir Process
8Speakers Credentials Products
- SR60 Pavement Stamping Machine
- DuraTherm Crosswalk Safety Products
9DuraTherm
10Current ProjectHigh Visibility Crosswalk
Markings
11WWW.STREETPRINT.COMpat.wiley_at_streetprint.com
12Current Situation
- A Great Solution, Slow Adoption
13BC MoTH Project History
- HIP Recycling
- Over 160 projects completed to date.
- 24 million sq metres of highway since 1990.
- 10 million annually
Lane KM
14BC MoTH Rehabilitation Options
Crack Sealing / Patching
Sealcoating / HIP
Overlays / Mill and Fill
Performance
Reclamation
Time
15End Product Performance
(Estimated)
16Cost Comparison
17Multi-Stage Airports
- Prince George runway 15-33 (1988)
- Cranbrook runway 16-34 (1990)
- Castlegar runway 15-33 (1992)
- Penticton runway 16-34 (1994)
- Kamloops runway 08-26 (1994)
- Campbell River runway (1997)
- Quesnel runway 13-31 (1999)
- Smithers runway 15-33 (2000)
- Terrace runway 15-33 (2001)
- Prince George runway 15-33 (2003)
- Victoria airport runway, (2004)
- Abbotsford runway 01-19 (2005)
- Port Hardy runway 07-25 (2005)
18HIR Airport Story
19BC HIR History
- The Long and Winding Road
- (Lennon and McCartney)
20BC HIR History
- HIR first introduced in 1984 by Johnson Recycling
21HIR Equipment Design Criteria
- Heat / remove up to 50 mm
- Accurate, homogenous addition of additives
- Effective laydown process
22The BC Innovation Story
Hot/Air Infrared Artec International
Heat Stir Process Artec Recycling Systems
Emissions Systems PyroTech Asphalt Equip
Two-Stage Process Rorison-Wiley Blacktop
1986
1991
1992
1995
23The Big Challenge 50 mm depth
24The Multi-Stage Solution
- 50 mm depth
- Reduced emissions
25PyroTech Two-Stage Recycling Train
Developed in 1986 by Rorison-Wiley Blacktop
26PyroTech Heating/Milling Machine
Hot Milling Heads
Infrared Heater Bed
27PyroTech Emission System
28PyroTech Stage One
Heats and remove 50 of desired depth
29Stage Two
Transfer Conveyor
Heat and remove 2nd exposed layer
30PyroTechs Two-Stage Process
Stage Two
Transfer Conveyor
Stage One Heating Milling
31Artec Two-Stage Four Stage Trains
Developed in 1989 by Artec Equipment Ltd
32Artec 2 4 Stage Process
Split Heater
33Artec Remix/Repaver
Repave Screed
Both Remix and Repave Options
34Repave Option
35Martec AR2000 Hot Air/Infrared
Developed in 1994 By Artec International
Recycling Ltd
36Martec AR2000 Hot Air/Infrared
Recirculating Hot Air
37Martec AR2000 Hot Air/Infrared
Extra Pre-Heater Enables 50 mm Milling
Requires Post-Heater to Achieve Laydown
Temperature
38Martec Stage-Two
Post Heats Milled Pavement
39Martec Post Heater
Stirring blades create mini windrows
40Pug Mill Mixing Systems
Pugmill Mixer
41(No Transcript)
42Best Practice Heat Remove
Focus on constant speed!
Dont outrun your temperature!
Start late, finish late
43Best Practice HIR Laydown
20 ton rubber tire breakdown for lower temp
Heavy steel finish
Conventional paver for smoothness
44Project Selection Factors
- solid base
- min 50mm top lift
- min 5 AC content
- min 25penetration
- Max 19mm agg
45Design Considerations
- Existing mix and binder properties
- Establish target mix and binder properties
- Determine rejuvenator type and content
- Determine admix quantity and gradation
- Achieve a design VMA
- Achieve design air voids (3 to 5 common)
46Adding Rejuvenators
47Admix Options
- Increase air voids
- Reduce filler content
- Improve stability
- Reduce AC content
48BC EPS Approach
- Contractor for Mix Design and QC
- Penalty and bonus adjustment for
- Gradation
- Smoothness
- AC Content
- Segregation
- Compaction
- Lane Occupancy
49International Projects Sweden
- Government of Sweden
- Purchased PyroTech 2-Stage in 1990
- Over 10 million m2 recycled
50International Italy
- E80 Motorway Near Livorno, Italy
- Project Size 140,000 m2
- Type of Pavement Polymer Modified Porous Asphalt
- Year 2003
51International USA
- Project Interstate 55, Southern Mississippi
- Project Size 49 Lane Km, 180,000 m2
- Year of Completion 1998
52Foreign Projects Eastern Canada
- Project Highway 401, near Woodstock, Ontario
- Project Size 5.6 KM
- Type of Asphalt Dense Friction Course
- Year 1999
53401 Comparison Project
Best Ride after 3 years
Least Rutting after 3 years
Best Skid after 3 years
54Site Visit Arc Asphalt Recycling
Site Visit Arc Asphalt Recycling
55Site Visit Arc Asphalt Recycling
56Site Visit Arc Asphalt Recycling
57Site Visit Arc Asphalt Recycling
58Site Visit Arc Asphalt Recycling
59Site Visit Arc Asphalt Recycling
60Site Visit Arc Asphalt Recycling
61 HIR Value Proposition
- To the Agency
- A ten year mill fill alternative at an
attractive price - To the Contractor
- A long term, niche opportunity
62Someone must take a Risk
- The Agency
- Must commit to a sustained program
- Endure the learning curve
- The Contractor
- Must purchase equipment
- Endure the learning curve
63Next Generation?
Subject to demand
64How to go forward?
- Pavement rehabilitation costs are skyrocketing
- Multi-Stage HIR is a proven solution
- Canadian HIR growth is at a virtual standstill