Title: Towards the Commissioning of J-PARC
1Towards the Commissioning of J-PARC
- J-PARC Controls Group
- JAEA(JAERI) KEK
- Tadahiko Katoh
- Japan Atomic Energy Agency since Oct. 1, 2005
2Outline
- J-PARC Facilities
- Control System
- Construction Schedule
- Control System Status
- Photographs
3J-PARC Accelerator Complex
Phase 1
4J-PARC Accelerator Complex
Phase 2
5Parameters of Accelerators
Accelerator Energy Current Repetition
Linac 181 MeV (400 MeV) 600 MeV 50 mA (peak) 25 Hz 50 Hz
Rapid Cycling Synchrotron 3 GeV 333 uA 25 Hz
Main Ring Synchrotron 40 GeV 50 GeV 15 uA 1/3.64 (Typ.)
( ) with ACS Linac Phase 2
6J-PARC Acceleration Timing
7J-PARC Control System Configuration
8J-PARC Control Network Configuration
93-Layer Model of Control System
10Control System Configuration
Accelerator IOC HW OS IOC HW OS I/O
Linac VME (65) VxWorks Linux VME Modules PLC EMB-LAN WE7000
Rapid-Cycling Synchrotron VME (25) VxWorks Linux VME Modules PLC EMB-LAN
Main Ring Synchrotron VME (50) Linux VxWorks PLC BPMC WE7000 EMB-LAN
11Construction Schedule
12Software Development Schedule
Test
Device drivers / device supports
Basic appl. software
Test
Application software
Test
Commissioning
No Beam
Beam
-24 -18 -12
-6 0
Months
13J-PARC Facility Layout
14Main Ring Construction Schedule
15Linac Installation
16Linac Control Racks
17Linac Control Racks
183. ?????????
Materials and Life Sciences Facility
19Hadron Experimental Facility
20295 km West
Super Kamiokande
Neutrino Experimental Facility
21Please Visit .
PO1.001-1 Progress of a Control System for Slow-Extraction Beam Lines at J-PARC
PO1.009-1 Data Acquisition System for J-PARC 3GeV RCS
PO1.024-1 Development of Beam Monitor DAQ System for 3NBT at J-PARC
PO1.061-6 Beam-Monitor Software of the KEK Proton Linac for J-PARC
PO1.065-6 Development of a Portable EPICS Package miniEPICS
PO1.067-7 Development of Ante Mortem System to reduce the Beam Loss in Accelerator
PO2.069-4 Embedded EPICS On MICRO-ITRON/SH4-Based Controllers
PO2.070-5 Recent Development of a Monitoring System for Beam Line Status at the J-PARC Slow-Extraction Beam Line
PO1.080-7 Relational Database System for J-PARC Linac and RCS
PO2.084-5 Recent Activities on VME/Linux-based IOC Applications at KEK
PO1.102-8 Securing the Control System Resources
PO2.059-4 VME Reliability Monitor Board with Embedded EPICS
PO2.063-4 The BPM DAQ System using Fast Waveform Digitizer Based on CPCI-bus
22Thank You for Your Attention!