Turbine/Generator Upgrades and Maintenance - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Turbine/Generator Upgrades and Maintenance

Description:

Turbine Blading & Steam Path Upgrades ... Improved material properties to resist SCC and LCF ... Converting original MH and analog EH controls to digital ... – PowerPoint PPT presentation

Number of Views:440
Avg rating:3.0/5.0
Slides: 31
Provided by: AEP71
Category:

less

Transcript and Presenter's Notes

Title: Turbine/Generator Upgrades and Maintenance


1
Turbine/Generator Upgrades and Maintenance
Presented by Daniel Sculley, Manager Turbine, Generator Piping Systems Engineering APP Site Visit October 30 November 4, 2006
2
Topics
  • Turbine Blading Steam Path Upgrades
  • Turbine Stop / Control Valve Upgrades
  • Turbine Control System Modernization
  • Generator Improvements

3
Steam Path Improvements
  • More than 20 units in plan for upgrade
  • Efficiency gain
  • Aerodynamic blade profiles
  • Improved inter-stage sealing
  • Reduction of sidewall secondary flow losses
  • Reduction in future OM costs
  • Extend time between overhauls
  • Reduction of solid particle erosion damage
  • Less coal burned

4
Glen Lyn 6 Series 235MW (GE) HP/IP
  • Nine (9) Units (Subcritical, 1957 - 1961)
  • Integral control valve chest girth weld creep
  • Purchased complete spare in 1990
  • Exchanged on other 8 units (1991 2004)
  • New rotors replaced C grade materials
  • New nozzles, diaphragms (Rows 1,9,10,12)
  • Reassemble non-outage 4-week reduction
  • Cost 8 Million (US) first unit installed,
    approx.
  • Cost 4 Million (US) subsequent units, approx.

5
(No Transcript)
6
Glen Lyn 6 Series 235MW (GE) HP/IP
  • Results
  • Restored CV chest with improved girth weld
  • Improved HP efficiency by 1.5 - 2.0
  • 2.5 MW and 35.28 kcal/kWh (140 Btu/kWh) gain
  • Erosion minimized, reduced repairs
  • Extended inspection intervals to 10-11 years
  • Re-inspections begun in 2001 confirm benefit

7
1300 MW Series (Alstom) HP
  • Six (6) Units (Supercritical, 1973 1989)
  • Use of spare rotor/inner casing assembly
  • Replaced all stationary/rotating rows (28)
  • Reuse rotor and re-round inner casing
  • Modified seal strips for steam swirl stability
  • Cost 6 Million (US) per unit installed,
    approx.
  • Results
  • Blading Efficiency gt 92.0, increase of 4.7
  • 20 MW and 28.5 kcal/kWh (113Btu/kWh)
  • Improved rotor stability against steam swirl
  • 3 Units completed - - 1 with premature
    degradation

8
600,800 MW Series (GE) HP/IP
  • Eight (8) Units (Supercritical, 1967 1972)
  • To date, four have been converted
  • New nozzles, diaphragms, seals
  • Reblade spare rotor reuse shells
  • Cost 6.5 Million (US) per unit installed,
    approx.
  • Results
  • 82.8 - 86.3 HP section efficiency
  • 11MW gained on 800MW Series
  • 600 MW Series HP fell short of expectations by up
    to 3.5 due to overstated recoverable losses by
    OEM.

9
Effect of Advanced Design Steam Path
10
Big Sandy Unit 1 HP-IP/SFLP
  • One (1) unit, W design (Subcritical, 1963)
  • HP turbine complete and IP/SFLP turbine rotor and
    inner casing install 2008
  • Inefficient original design
  • Internal components subjected to erosion and
    distortion
  • Creep damage evident
  • No spare blade rings or rotors

11
Original Design Issues
  • Efficiency

Turn-around (Pressure Loss)
Curtis Stage (Poor Efficiency)
Conventional Cylindrical Airfoil (Poor Efficiency)
12
Existing Maintenance Issues
  • Reliability

Large Dia. Inner Casing (CrMo casting) (Distortion
, Rubbing)
L-0 Shrunk-on Disc (SCC Potential)
Stage 1 Blade Root Distortion Stages 2-4 Blade
Untwist
IP/SFLP Rotor 44 years Old
L-0 Blade Fatigue Life (Blade Failure)
Large Blade Ring (Distortion, Rubbing, Blade
Leaning)
13
New HP Section Design
Separately supported blade rings and balancing
ring
ACC Packing (Active Clearance Control)
Integral Inner Casing
Monoblock No Bore Rotor
3-D Reaction Blades (ISB)
Rateau control stage
14
New IP/LP Section Design
ACC Packing (Active Clearance Control)
Separately-Supported Blade Rings
25in ISB
Mono block no bore rotor No Shrink-fit
3-D Reaction Blades (ISB)
Integral Inner Casing
15
Big Sandy Unit 1 Expectations
  • Anticipated Results
  • Improved reliability and design efficiency
  • HP efficiency 4.1 to 88.9
  • IP efficiency 3.1 to 94.6
  • Expect 18 MW at original design steam flow
  • Includes replacement throttle/governor valves
  • Installed cost 18Million (US), approx.

16
LP Turbine Performance Retrofits
  • AEP experience driven by reliability issues
  • Stress Corrosion Cracking on blades, disks and
    Low Cycle Fatigue on blade attachments
  • Flow limit for L-1 rotating blade causes
    curtailment
  • LP turbine exhaust limit 140 mm HgA (5.5 in
    HgA)
  • Frequently caused summer time curtailments
  • Solution LP Turbine Upgrade

17
LP Turbine Performance Retrofits
  • Four (4) BB73 W LP steam paths ruggedized
  • Improved material properties to resist SCC and
    LCF
  • Aerodynamic improvements to blades and inlet /
    exhaust flow guides
  • Improved seal design to reduce leakage
  • Full load capable to 203 mm HgA (8 in HgA)
    backpressure
  • Improved performance 3.4MW, 22.4 kcal/kWh (89
    Btu/kWh)

18
Stop/Control Valve Upgrades
  • Material Damage
  • Thermal fatigue, creep
  • Reliability
  • Tight shutoff, leaks
  • Maintenance
  • Weld repair to valve body, seats, bolt holes
  • Design Improvement
  • Improve OM
  • Reduce pressure drop

19
1300 MW Series SV/CV Upgrades
  • Original Design
  • Pressure drop across combined valves 5.1
  • Limited steam flow at VWO 5 overpressure
  • Significant solid particle erosion damage
  • Expensive repairs performed every 2-3 years

20
(No Transcript)
21
(No Transcript)
22
1300 MW Series SV/CV Upgrades
  • New Design
  • Separate stop and control valve chambers
  • Actual pressure drop across valves 2.08
  • Achieved 32 MW increased generation capability
    without changing boiler conditions
  • Updating valve actuators to digital controls

23
Turbine Control System Upgrades
  • Converting original MH and analog EH controls to
    digital
  • Integrated into plant Distributed Control System
  • Reuse or modify hydraulic systems
  • Use fire resistant fluids
  • Expectations
  • Enhanced control
  • Fewer unit trips
  • Faster startup/ramp rates
  • Online testing of turbine valves and protective
    devices

24
Turbine Control System Upgrades
  • Results
  • Smooth, rapid rollups to synchronous speed
  • CV position and load ramping optimized by stress
    probe
  • CV stroke ramped according to test throttle
    pressure
  • Improved reliability during protective device
    checks
  • Lower peak speeds reached during turbine trip
  • Reduction in boiler tube leaks due to soft
    trips
  • All contribute to improved reliability and
    performance

25
Generator Improvements
  • Inspection Intervals (typical)
  • Field in-place ( 5 years)
  • Field removed (10 years)
  • Perform routine cleaning, testing, repairs
  • Goal Achieve high reliability through design
    life of insulation systems

26
Generator Rewinds
  • Rewinds Offer Opportunity for Improvement
  • Required for reliability and maintenance purposes
  • Efficiency improvements are small added benefit
  • Stator Windings
  • Asphalt stator bar insulation replaced with
    modern epoxy-mica insulation
  • Potential for increased copper cross-section in
    original slots
  • Improved cooling gas or water flows reduce
    operating temperature and extend design life
  • Stator Cores
  • Inspect and test for looseness, hot spots,
    resonance
  • Several cores replaced (full, partial)
  • Reference papers available in Breakout Session

27
Generator Rewinds
  • Fields
  • Replace retaining rings with 18Mn 18Cr material
  • Improve end turn blocking design and materials
  • Restore/replace copper and replace all insulation
  • Optimize cooling gas flow

28
Summary
  • AEP has been retrofitting turbine generator
    equipment with efficiency improvements for more
    than 15 years.
  • Experience with OEM and non-OEM solutions.
  • Economic benefit drives the HP and IP turbine
    retrofits.
  • Must consider design improvement vs. restoration
    improvement.
  • Turbine valve design could provide upgrade
    potential.
  • Turbine control integration can produce thermal
    benefits.
  • Reliability benefit drives the LP turbine and
    generator retrofits (typically). Some small
    efficiency improvements are possible.

29
Breakout Session
  • Two Sessions on Tuesday Afternoon
  • Expert Attendees
  • Steve Molick Turbine Services Manager
  • Jim Michalec Staff Engineer, Generators
  • Alex Manukian Sr. Engineer, Turbines
  • Jim Cable Sr. Engineer, Turbines, Controls
  • Dan Sculley TGPSE Manager

30
Questions
Write a Comment
User Comments (0)
About PowerShow.com