Current Status Report on AIDC TCS Program - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Current Status Report on AIDC TCS Program

Description:

Current Status Report on AIDC TCS Program – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 27
Provided by: mmol6
Category:
Tags: aidc | tcs | current | neth | program | report | status

less

Transcript and Presenter's Notes

Title: Current Status Report on AIDC TCS Program


1
Current Status Report onAIDC TCS Program
  • Drj Dar-Jen Sun,Joe Chen, YW Chen,Grand Jiang,
    Chia-Fa Ou, YIAO-TENG HO,YUNG-KUO CHIANG, David
    Ho, Marco Yao, Alan Hsu, Benjamine Lee, Camel
    Hsa,Steven Uong, Peter Tang, Max Yen, Andrew
    Shih, Chung-Jen Tsai, John Peng, Eric Hwang, DICK
    WANG

Aerospace Industrial Development Corp. Taiwan,
R.O.C.
2
In the past three months, we complete
  • All FM machining parts
  • Integration jigs installation
  • 1st FM tracker panel
  • 1st Tracker panel heater installation Thermal
    testing (w/ NSPO, CGS)

3
? Delivery
4
AMS02 TCS PROGRAM
M. Radiator Mid Brackets
5
AMS02 TCS PROGRAM
M. Radiator Lower Brackets
6
AMS02 TCS PROGRAM
Tracker Radiator Rod Brackets
7
VSB Carbon fiber parts
8
? _at_ Clean Room
9
RAM JIG INSTALLATION
10
RAM JIG INSTALLATION
11
RAM JIG INSTALLATION
Approaching USS
12
RAM JIG INSTALLATION
Lower down
13
WAKE Jig
RAM Jig
Integration at CERN clean room
14
Professor Ting NASAs Visitors During AIDC
integration team activity at CERN
15
1st FM Tracker radiator panel
  • Hot bonding ammonia HP embedded
  • 2600 mm L x 500 mm W
  • Skin0.5mm 2024T81 Al Alloy
  • CoreRohacell 51WF
  • Planarity 0.5mm
  • Holes Positioning 0.1mm
  • 12.69Kg

16
Visual Inspection
  • Visual inspection all heaters
  • Label the lead wire near the heaters
  • Check resistant of all heaters

17
Panel Preparation
  • Clean the bonding surface
  • Determine the required position

18
Heater Tape Installation
  • To press the heater onto the panel.
  • Roll from the center toward the edges

19
Wired heater in 5 groups
  • Wired heaters in series into 5 groups
  • Power on heater groups in 120V DC
  • To press and repeat several times on heaters.

20
Electric Checkouts
  • Electrically isolated with the panel
  • Record the voltage and current values
  • Put glue on the edges of heaters.

21
Thermal testing _at_AIDC on Jan 24-25,2008
Special thanks to NSPO team and CGS (Ivan
Corradino) to strongly support and fulfill this
testing efficiently
22
Thermal Test fixture set-up (vertical and
horizontal)
23
typical IR photo for heat pipe activation behavior
Final report is under preparation by NSPO and
will be released and reviewed by all related AMS
colleagues
24
The next step
  • 2nd set tracker panel manufacturing is in process
    (other parts completed except skins)
  • RAM main radiator BOF fabrication is in process
    (will be completed in mid-Feb)
  • WAKE main radiator drawing review is in process
  • Working on radiator panel air shipping

25
Radiator Panels DELIVERY SCHEDULE
PRODUCT DESCRIPTION DUE DATE 2. 1st
TRACKER RADIATOR
Production 2007/11/30 Thermal Test
(Heater Insta.) 2008/1/23 Delivered
at CERN (by sea) 2008/4/30 3. 2nd TRACKER
RADIATOR
Production 2008/3/06 Thermal Test
(Heater Insta.) 2008/3/17 Delivered at
CERN (by sea) 2008/4/30
(OptionDelivered with 2nd Tracker radiator )
(One week off for Lunar new year)
(67 weeks)
26
DELIVERY SCHEDULE
PRODUCT DESCRIPTION DUE DATE 4. RAM
RADIATOR PANEL DRW RELEASED 2007/11/09
Production 2008/03/24 Thermal Test
(Heater Insta.) 2008/04/24 Delivered at
CERN (by air) 2008/05/02 5. WAKE RADIATOR
PANEL DRW RELEASED 2008/02/15
(Prediction) Production 2008/04/29
Thermal Test (Heater Insta.) 2008/05/29
Delivered at CERN (if by air) 2008/06/06
(assumed for complicated configuration)
(assumed for complicated configuration)
Write a Comment
User Comments (0)
About PowerShow.com