Title: Current Status Report on AIDC TCS Program
1Current Status Report onAIDC TCS Program
- Drj Dar-Jen Sun,Joe Chen, YW Chen,Grand Jiang,
Chia-Fa Ou, YIAO-TENG HO,YUNG-KUO CHIANG, David
Ho, Marco Yao, Alan Hsu, Benjamine Lee, Camel
Hsa,Steven Uong, Peter Tang, Max Yen, Andrew
Shih, Chung-Jen Tsai, John Peng, Eric Hwang, DICK
WANG
Aerospace Industrial Development Corp. Taiwan,
R.O.C.
2In the past three months, we complete
- All FM machining parts
- Integration jigs installation
- 1st FM tracker panel
- 1st Tracker panel heater installation Thermal
testing (w/ NSPO, CGS)
3? Delivery
4AMS02 TCS PROGRAM
M. Radiator Mid Brackets
5AMS02 TCS PROGRAM
M. Radiator Lower Brackets
6AMS02 TCS PROGRAM
Tracker Radiator Rod Brackets
7VSB Carbon fiber parts
8? _at_ Clean Room
9RAM JIG INSTALLATION
10RAM JIG INSTALLATION
11RAM JIG INSTALLATION
Approaching USS
12RAM JIG INSTALLATION
Lower down
13WAKE Jig
RAM Jig
Integration at CERN clean room
14Professor Ting NASAs Visitors During AIDC
integration team activity at CERN
151st FM Tracker radiator panel
- Hot bonding ammonia HP embedded
- 2600 mm L x 500 mm W
- Skin0.5mm 2024T81 Al Alloy
- CoreRohacell 51WF
- Planarity 0.5mm
- Holes Positioning 0.1mm
- 12.69Kg
16Visual Inspection
- Visual inspection all heaters
- Label the lead wire near the heaters
- Check resistant of all heaters
17Panel Preparation
- Clean the bonding surface
- Determine the required position
18Heater Tape Installation
- To press the heater onto the panel.
- Roll from the center toward the edges
19Wired heater in 5 groups
- Wired heaters in series into 5 groups
- Power on heater groups in 120V DC
- To press and repeat several times on heaters.
20Electric Checkouts
- Electrically isolated with the panel
- Record the voltage and current values
- Put glue on the edges of heaters.
21Thermal testing _at_AIDC on Jan 24-25,2008
Special thanks to NSPO team and CGS (Ivan
Corradino) to strongly support and fulfill this
testing efficiently
22Thermal Test fixture set-up (vertical and
horizontal)
23typical IR photo for heat pipe activation behavior
Final report is under preparation by NSPO and
will be released and reviewed by all related AMS
colleagues
24The next step
- 2nd set tracker panel manufacturing is in process
(other parts completed except skins) - RAM main radiator BOF fabrication is in process
(will be completed in mid-Feb) - WAKE main radiator drawing review is in process
- Working on radiator panel air shipping
25Radiator Panels DELIVERY SCHEDULE
PRODUCT DESCRIPTION DUE DATE 2. 1st
TRACKER RADIATOR
Production 2007/11/30 Thermal Test
(Heater Insta.) 2008/1/23 Delivered
at CERN (by sea) 2008/4/30 3. 2nd TRACKER
RADIATOR
Production 2008/3/06 Thermal Test
(Heater Insta.) 2008/3/17 Delivered at
CERN (by sea) 2008/4/30
(OptionDelivered with 2nd Tracker radiator )
(One week off for Lunar new year)
(67 weeks)
26DELIVERY SCHEDULE
PRODUCT DESCRIPTION DUE DATE 4. RAM
RADIATOR PANEL DRW RELEASED 2007/11/09
Production 2008/03/24 Thermal Test
(Heater Insta.) 2008/04/24 Delivered at
CERN (by air) 2008/05/02 5. WAKE RADIATOR
PANEL DRW RELEASED 2008/02/15
(Prediction) Production 2008/04/29
Thermal Test (Heater Insta.) 2008/05/29
Delivered at CERN (if by air) 2008/06/06
(assumed for complicated configuration)
(assumed for complicated configuration)