Title: Asbestos in Soil


1
Asbestos in Soil
  • Greg Holt
  • Stapleton Redevelopment Program
  • City and County of Denver
  • October 3, 2008

2
Stapleton Redevelopment
  • Stapleton Airport closed in 1995
  • Largest Brownfield Urban Project
  • 4000 Acres
  • 2900 acres Developable
  • 1100 acres Open Space
  • Redevelopment began in 1998
  • Three programs
  • Environmental
  • Demolition
  • Airfield Pavement Removal

3
Development
  • Land Transfer Environmental Standards
  • Stapleton Numeric Criteria-SNC
  • City, EPA and State of Colorado
  • Certification from Property Owner
  • NFA/NAD for Environmental Sites
  • Approximately 120 NFAs received
  • Master Developer Chosen

4
Asbestos
  • Under Regulation 8
  • 125 Building abated prior to demolition
  • 50 of the Fuel Distribution System
  • Utilities
  • Water
  • Electric
  • Communication/ Telephone

5
Asbestos in Soil
  • Lowery and Buckley
  • Regulation Change - May 2006
  • Land Transfer Requirements
  • Industry Changes
  • Environmental Site Assessments
  • Sophistication of Asbestos Abatement Contractors
  • Close out reports / NFA Requests

6
Highline Canal Phase 1 Filing 16
  • History
  • City Purchased the land for airport expansion mid
    1950s
  • Lateral of the Highline canal
  • Canal backfilled with mixed waste
  • Overall site was backfilled for runway
    expansion-mid 1960s

7
Filing 16 Timeline
  • Environmental Assessments- 6/04 and 1/05
  • Site Characterization- Summer 2005
  • Work Plan Approved by CDPHE - Fall 2005
  • Insurance Acceptance of Claim Fall 2005
  • Project Bid - November 2005
  • Contractor Selected - January 2006
  • NTP March 2006
  • Abatement April 2006- Current

8
Filing 16 2006
9
Filing 16 - 2008
10
Filing 16 Timeline
  • Work Plan Approved by CDPHE - Fall 2005
  • Joint meeting with CDPHE - March 2006
  • Original Work Plan amended 3 times
  • Development of site wide work plan
  • Creation of Clearance Protocol -Fall 2006
  • Suspension of Work Plan- October 2008

11
Filing 16
  • Original Scope of Work
  • Est. 120,000 yds
  • 70,000 yds Non- Friable ACM
  • 50,000 yds Friable ACM
  • Area approximately 40 acres
  • Duration 180 days
  • Actual
  • Est. 730,000 yds
  • 480,000 yds Non- Friable ACM
  • 250,000 yds Friable ACM
  • Area increased to 105 acres
  • Duration 29 months

12
Filing 16
13
Filing 16
14
Filing 16
15
Filing 16
16
Filing 16
17
Filing 16
18
Filing 16
19
Filing 16
  • Suspension of Work
  • Why?
  • City reached Sitewide Cap on costs
  • Insurance reimbursement
  • Slow in payments
  • Payments in arrears.

20
Filing 16
  • Suspension of Work
  • Site Status
  • Canal Cleared
  • 88 of the total site has been cleared
  • 15 of the site has been backfilled
  • Remaining area is under a stockpile.

21
Filing 16
  • Suspension of Work
  • Site Security
  • Site Stabilization
  • Protection of Human Health and Environment
  • Air Monitoring

22
Filing 16
  • Insurance Reimbursement
  • Original Scope of Work
  • 7,000,000.00
  • Estimate to Completion
  • 50,000,000.00

23
Stapleton
  • Asbestos
  • One site complete - closure report and NFA
    submitted
  • Two sites complete awaiting submittal
  • Two sites in progress
  • Five sites not started

24
Stapleton
  • Lessons learned
  • Site size-
  • Unit pricing
  • Type of equipment to be used
  • Wetting methods
  • Material
  • Friable
  • Non-Friable
  • Mixture
  • Mechanical means
  • Use of excavators, graders, other heavy equipment
  • Soil preparation
  • Methods to achieve adequately wet

25
Stapleton
  • Questions