Title: CRWR-PrePro Calculation of Hydrologic Parameters
1 CRWR-PreProCalculation of Hydrologic
Parameters
Texas Department of Transportation (TxDOT) Water
Resources Modeling Using GIS 2000 - Austin, Texas
- Francisco Olivera, Ph.D.
- Center for Research in Water Resources
- University of Texas at Austin
2Hydrologic Parameters
- Watershed
- Abstractions and routing method
- Parameters
- Stream
- Routing method
- Parameters
3Watershed Abstractionsand Routing Method
- Abstractions rainfall/runoff transformation
- SCS curve number method
- Initial loss constant rate loss
- Routing runoff/flow transformation
- Soil Conservation Service (SCS) synthetic unit
hydrograph
4Watershed Abstractions
Precipitation (mm/hr)
Runoff (mm/hr)
Soil properties
Runoff f(precipitation, soil properties,
moisture conditions)
5Watershed Routing
Runoff (mm/hr)
Watershed
Flow (m3/s)
6Watershed Routing
Time
Runoff (mm/hr)
Runoff and Flow
Flow (m3/s)
Time
Flow f(Runoff, Watershed hydrologic properties)
7Hydrologic Parameters
- Watershed
- Abstractions and routing method
- Parameters
- Stream
- Routing method
- Parameters
8Watershed
- Area
- Average curve number
- Initial constant rate loss
- Length of longest flow-path
- Slope of longest flow path
- Lag time
9Watershed Abstractions
Average Curve Number
Initial Loss (mm)Constant Loss (mm/hr)
SCS Method
Initial Constant Method
10Elevation Grid
11Flow Length Downstream
12Flow Length Upstream
13Longest Flow-Path
14Flow Length Downstream to the Watershed Outlet
15Hydrologic Parameters
- Flow length downstream to the sub-basin outlet.
16Flow Length Upstreamto the Watershed Divide
17Hydrologic Parameters
- Flow length upstream to the sub-basin divide.
- A NODATA cell is defined at the sub-basin outlets
before running the flow length function.
18Watershed Longest Flow-Path
19Hydrologic Parameters
- Sub-basin longest flow-path.
- The longest flow-path is the geometric locus of
the points for which the sum of both flow lengths
is a maximum.
20Slope of WatershedLongest Flow Path
21Hydrologic Parameters
- Sub-basin lag-time according to the SCS formula
tp sub-basin lag-time (min) LW length of
sub-basin longest flow-path (ft) CN average
Curve Number in sub-basin S slope of the
sub-basin longest flow-path () ?t analysis time
step (min)
22Watershed Lag-Time (SCS)
Flow length upstream and downstream
AverageCurve Number
Lag-time
23Hydrologic Parameters
- Sub-basin lag-time according to 0.6 L/v formula
tp sub-basin lag-time (min) Lw length of
sub-basin longest flow-path (ft) Vw average
velocity sub-basin longest flow-path
(m/s) ?t analysis time step (min)
24Watershed Lag-Time (L/V)
Flow length upstream and downstream
Longest flow-path average velocity
Length of the longest flow-path
Lag-time
25Hydrologic Parameters
- Sub-basin parameters Grid code, area (Km2), unit
hydrograph model (SCS), length of longest flow
path (m), slope of longest flow path (fraction),
average curve number, lag-time (min), baseflow
(none).
26Hydrologic Parameters
- Watershed
- Abstractions and routing method
- Parameters
- Stream
- Routing method
- Parameters
27Routing Method
28Pure-Lag Method
tlag flow time in the reach I inflow to the
reach Q outflow from the reach
- Flow is delayed a fixed amount of time tlag.
29Muskingum Method
S storage in the reach K flow time in the reach
(Dt lt K lt Dt/2X) X storage parameter I inflow
to the reach Q outflow from the
reach Dt analysis time step
- Flow is delayed a fixed amount of time K, and
redistributed around its centroid.
30Routing Method
Flow time (Ls/Vs)
Ls/Vs lt Dt
Ls/Vs gt Dt
MuskingumRouting
Pure LagRouting
Ls length of the stream Vs flow velocity in the
stream Dt analysis time step
31Hydrologic Parameters
- Watershed
- Abstractions and routing method
- Parameters
- Stream
- Routing method
- Parameters
32Hydrologic Parameters
- Reach lag-time for Pure Lag routing
tlag reach lag-time (min) Ls length of reach
(m) Vs reach average velocity (m/s)
33Hydrologic Parameters
- Reach lag-time and number of sub-reaches for
Muskingum routing
K Muskingum parameter K (hr) X Muskingum
parameter X Ls reach length (m) Vs reach
average velocity (m/s) n number of sub-reaches
34Hydrologic Parameters
- Pure lag routing for Ls/60vs lt Dt, otherwise
Muskingum routing. - Reach parameters Grid code, sub-basin code,
length(m), velocity (m/s), routing method (Lag or
Muskingum), lag time (min), Muskingum X,
Muskingum K (hr), number of sub-reaches.