Title: AMS02 Uninterruptible Power Supply
1AMS-02 Uninterruptible Power Supply
Alpha Magnetic Spectrometer NASA / DOE
Status Summary
T. J. Urban / ESCG
January 31, 2006
2AMS-02 Uninterruptible Power Supply Status Summary
Alpha Magnetic Spectrometer NASA / DOE
- Battery Pre-Delivery Acceptance Review
- Review held July 18, 2005. Review deemed
successful. - All battery cell qualification and acceptance
test data reviewed - In compliance with SOW Appendix A.
- Cells are assembled into battery bricks, and
awaiting completion of integrated testing with
Battery Management System (BMS) electronics prior
to shipment. - Shipment, via sea due to energy density (approx.
3 weeks), following integrated testing. - BMS has had issues, delaying cell BMS delivery
until February 2006.
T. J. Urban / ESCG
2
January 31, 2006
3AMS-02 Uninterruptible Power Supply Five Cells
Alpha Magnetic Spectrometer NASA / DOE
T. J. Urban / ESCG
3
January 31, 2006
4AMS-02 Uninterruptible Power Supply Cell Details
Alpha Magnetic Spectrometer NASA / DOE
T. J. Urban / ESCG
4
January 31, 2006
5AMS-02 Uninterruptible Power Supply Vibration
Testing
Alpha Magnetic Spectrometer NASA / DOE
T. J. Urban / ESCG
5
January 31, 2006
6AMS-02 Uninterruptible Power Supply Cell
Destructive Testing
Alpha Magnetic Spectrometer NASA / DOE
Internal Short Test
Overvoltage Test
T. J. Urban / ESCG
6
January 31, 2006
7AMS-02 Uninterruptible Power Supply Status Summary
Alpha Magnetic Spectrometer NASA / DOE
- UPS Critical Design Review
- Review held August 9, 2005. Review deemed
successful. - Various actions taken and closed.
- UPS housing has been redesigned with a delta 15mm
in height. - To facilitate battery / BMS wiring.
- Drawings complete.
- Structural Analysis all margins are positive,
JS ESCG review of analysis report is complete. - UPS install bracket has been split in two to ease
installation. - Bottom Line Approval has been given for UPS
manufacture.
T. J. Urban / ESCG
7
January 31, 2006
8AMS-02 Uninterruptible Power Supply Module
Assembly
Alpha Magnetic Spectrometer NASA / DOE
T. J. Urban / ESCG
8
January 31, 2006
9AMS-02 Uninterruptible Power Supply Status Summary
Alpha Magnetic Spectrometer NASA / DOE
- Battery Management System (BMS) Testing Issue
- During BMS PCA level thermal cycle testing, 100kO
resistors failed either open, or gt 100kO
resistance. - Manufacturers assessment was material corrosion
in encapsulation material. - Most likely candidate overheating during
soldering. - Resistors have been replaced.
- Thermal re-testing has been completed.
- Integrated battery / BMS testing is underway.
- PRACA (Problem Reporting and Corrective Action)
initiated at JS ESCG, and will be reported to JSC
PSRP.
T. J. Urban / ESCG
9
January 31, 2006
10AMS-02 Uninterruptible Power Supply Status Summary
Alpha Magnetic Spectrometer NASA / DOE
- UPS SOW Revision B To be released 17 February
2006. - Redefine electrical interface battery safety
signal for overvoltage. - Work underway to determine if this is acceptable
to CAB. - Testing
- Update of UPS thermal testing based upon latest
integrated thermal analysis (acceptance test _at_
50C and qualification test _at_ 55C). - External short circuit (72 A vs. 80 A) verifying
with JSC/EP battery expert.
T. J. Urban / ESCG
10
January 31, 2006
11AMS-02 Uninterruptible Power Supply Status Summary
Alpha Magnetic Spectrometer NASA / DOE
- Further UPS Actions
- Provide portable UPS tester CSIST to provide by
1 April 2006. - Locate UPS fasteners from ESCG Shipment
delivery date to be provided by Urban to CSIST by
10 February 2006. - MIT procurement of UPS parts, latest EDT 28 -
February -2006
T. J. Urban / ESCG
11
January 31, 2006
12AMS-02 Uninterruptible Power Supply Battery Weight
Alpha Magnetic Spectrometer NASA / DOE
- Cell module 8.8 kg
- Battery box 3.4 kg
- BMS 0.75 kg
- Wire and connector ?
- Total est. 15 kg
T. J. Urban / ESCG
12
January 31, 2006
13AMS-02 Uninterruptible Power Supply UPS Module
Weight
Alpha Magnetic Spectrometer NASA / DOE
Misc. J1J2 230g Intercell Connector
200g Screw Nut 20g Adhesive 50g Flux
100g RTV566 200g Wire 100g (6.4g8m29.3g1.4m)
Total900g X 21.8kg
T. J. Urban / ESCG
13
January 31, 2006
14AMS-02 Uninterruptible Power Supply Schedule
Delay from BMS 3 Months
Alpha Magnetic Spectrometer NASA / DOE
- Shipment of batteries and BMS 17 February 2006.
- This will delay UPS delivery until mid-December
2006.
T. J. Urban / ESCG
14
January 31, 2006