ITER Cryogenic System - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

ITER Cryogenic System

Description:

ITER Cryogenic System – PowerPoint PPT presentation

Number of Views:159
Avg rating:3.0/5.0
Slides: 32
Provided by: jesusiz2
Category:
Tags: iter | bam | cryogenic | system

less

Transcript and Presenter's Notes

Title: ITER Cryogenic System


1
ITER Cryogenic System
ITER CODAC Colloquium 27th-28th October,
2008 Barcelona, SPAIN
Manel Sanmartí, CIEMAT-F4E Plants DIvision, ITER
Department
2
Outline
  • ITER cryogenic requirements
  • ITER CRYO project frame
  • ITER cryogenic system
  • Cryo controls and instrumentation
  • Conclusions

3
Main duties
  • Basic
  • Cool-down of the cryostat and torus cryopumps
  • Gradual cool-down and filling of the magnet
    system and the 80 K thermal shield in about one
    month
  • Cool-down of the NB cryopumps, pellet units and
    gyrotrons
  • Maintain magnets and cryopumps at nominal
    temperatures over a wide range of operating modes
    with pulsed heat loads due to nuclear heating and
    magnetic field variations
  • Accommodate periodic regeneration of cryopumps
  • Accommodate resistive transitions and fast
    discharges of the magnets and recover from them
    in few days
  • Additional
  • Ensure high flexibility and reliability
  • Low maintenance

4
Cryogenic capacity loads
  • LHe cryoplant 65 kW equivalent _at_ 4.5 K
  • Cooling of the superconducting magnet system
  • 39 kW _at_ 4.2 K
  • Cooling of HTS current leads
  • 150 g/s GHe at 50 K
  • Cooling of cryo-pumps with high regeneration
    frequency
  • 6.5 kW _at_ 4.5 K and 70 g/s of LHe liquefaction
  • Small users
  • 1 kW _at_ 4.5 K (Gyrotron)
  • LN2 cryoplant 1300 kW _at_ 80 K
  • Thermal shielding
  • up to 800 kW _at_ 80 K during chamber baking
  • LHe cryoplant pre-cooling
  • up to 280 kW _at_ 80 K during normal operation
  • HTS 50 K extra cooling power
  • up to 180 kW _at_ 80 K during normal operation

5
Magnets Pulsed Head Load
6
Operation scenarios
  • Uninterrupted operation in order to maximize
    machine availability
  • The tokamak will be operated during two 8-hour
    shifts
  • The third shift will be used to recover nominal
    cryogenic conditions, for short interventions and
    to regenerate the cryopumps up to 470 K
  • The large dynamic loads prevent full redundancy
    but allow continuous and uninterrupted operation
    without plasma
  • Short maintenance periods of few days every two
    weeks
  • Major shutdowns every 16 months
  • RAMI analysis to improve the design and
    requirements for spares

7
Technical variants
  • Analysis of technical variants compatible with
    the requirements and basic design principles are
    presently under study
  • Simplification of the layout and improvement of
    performances, reliability and availability or
    reduction of investment and operation costs
  • Review and update of heat loads
  • Large dynamic loads handling
  • Pulse mitigation by temporary by-pass of the
    structure load
  • Use of liquid helium storage buffering and
    complex process control
  • Helium management and cold quench tank
    temperature level
  • Optimal size, number of cold boxes and parallel
    operation (flow sharing)
  • Thermodynamic cycle optimization for the
    refrigerators
  • Developments of technology and engineering
    solutions for key components
  • Example SHe circulating pumps and heat
    exchangers

8
Outline
  • ITER cryogenic requirements
  • ITER CRYO project frame
  • ITER cryogenic system
  • Few thoughts on control and instrumentation
  • Conclusions

9
The ITER CRYO project frame
  • Cryoplants system helium refrigerators, LN2 and
    80K loop system, ancillary equipment
    (warm/cold/liquid tanks, recovery purification
    systems)
  • Cryodistribution system main distribution boxes
    with cold circulating pumps and cold compressors,
    cryolines from cryoplant building and inside
    tokamak complex
  • Cryoplant procurement packages are based on
    functional specs and include manufacturing,
    delivery, installation on-site individual
    sub-package acceptance test

10
Cryogenics Schedule
11
Outline
  • ITER cryogenic requirements
  • ITER CRYO project frame
  • ITER cryogenic system
  • Few thoughts on control and instrumentation
  • Conclusions

12
ITER Cryoplant System
Cryodistribution
13
Cryoplant architecture
14
Cryoplant architecture
Pictures courtesy of CERN
15
Cryoplant layout option 1
80 K He loop
Unloading area
LN2 plant
Instrumentation (control) room
Power supply
Room for power supply
Unloading area
Option 1 LN2 plant and boxes of 80 K helium
loop are located at outdoor area
16
ITER Cryodistribution System
Cryodistribution
17
Cryodistribution architecture
18
ITER Cryodistribution system
gt50 Cold Boxes, 3 km of cryolines, 4500 components
Coming From cryoplant
CTCB
ACB STR
ACB PF
ACB TF
ACB CS
ACB Cryopumps
25000 LHe tank
Different levels
19
Cryodistribution system PID
20
ACB structure PID
21
ACB Structure Detail Design
22
Outline
  • ITER cryogenic requirements
  • ITER CRYO project frame
  • ITER cryogenic system
  • Controls and instrumentation for cryogenics
  • As personal views this presentation does not
    necessarily reflect those from other involved
    parties (IO and IN DA)
  • Conclusions

23
Instrumentation requirements
  • Cryogenic instrumentation (industrial
    process/plants)
  • Pressure (1-200b, mbar, vacuum), Temperature
    (300-3.7K), Flow (warm/cold 2-2000 g/s),
  • Gas quality impurities (N2/H20/CxHy-ppm)
  • Actuators Control Pneumatic Valves, Quench
    valves (mech/PV), Heaters, Motors (On/Off, speed
    control)
  • Switches (safety interlocks)
  • Cryoplants
  • Installed redundancy for inner instrumentation
    Cold Boxes
  • Specific components like turbines (speed sensor,
    gas impurities)
  • Cryoditribution
  • Sub-atmospheric circuits (helium guard)
  • Speed/Freq. controllers for circulators/cold
    comp.
  • High magnetic fields and radiation environment
  • Accessibility constrains (operation scenarios)
  • Installed redundancy for inner instrumentation
    ACB

24
Estimated I/O (tbc)
25
Control requirements
  • Cryoplants
  • Modular individual control sub-systems
  • Commissioning (staged, acceptance)
  • Operation scenarios
  • Dedicated PLC for critical components by
    suppliers turbines
  • Cryoditribution
  • High magnetic fields and radiation environment
  • Accessibility constrains (operation scenarios)
  • Dedicated PLC for critical components by
    suppliers cold circulators, cold comp.
  • Master control system
  • Cryo Integrated control system (IN, IO, EU)
  • General/individual data/interlocks exchange with
    other WBS (magnets, TS, cryopumps)
  • Machine interface (CODAC)
  • Standardization hardware and software
  • Flexibility and accessibility during
    commissioning and first years of operation
  • Logging and post-mortem system for data/event
    analysis
  • Quality control (software updates, modifications)

26
Cryoplant control architecture?
OWS 1..x
27
Cryoplant control architecture?
OWS 1..x
Data Servers
EWS 1..x
Ethernet
Storage
LHe CP1
LHe CP2
LHe CP3
Recup Purif.
80K Loop 12
LHe CB1
LHe CB2
LHe CB3
CTCB
LN2_1
LN2_2
28
Cryodistribution architecture?
29
Cryodistribution architecture?
EWS 1..x
OWS 1..x
Data Servers
Ethernet
Str. ACB
TF ACB
PF ACB
CS ACB
Cryopumps ACB
Accessibility constrains High magnetic field High
radiation enviroment
30
Conclusions
  • Cryogenics is a large industrial plant system
  • Instrumentation and controls requirements are
    well understood and identified
  • Controls architecture not yet defined
  • RAMI analysis and other projects experience to be
    used
  • Integration with clients (magnets, cryopumps, TS,
    others)
  • Radiation and high magnetic fields impact on
    cryodistribution instrumentation and electronics
    has to be validated
  • Standardization and integration of all cryogenics
    sub-systems is mandatory
  • Hardware (IC) and software
  • To be defined before PA by involved parties
  • Common strategy and standard to be defined by all
    involved parties (IO, IN DA F4E) before PA

31
THANK YOU!!
Manel.Sanmarti_at_f4e.europa.eu
Write a Comment
User Comments (0)
About PowerShow.com