Title: ITER Cryogenic System
1ITER Cryogenic System
ITER CODAC Colloquium 27th-28th October,
2008 Barcelona, SPAIN
Manel SanmartÃ, CIEMAT-F4E Plants DIvision, ITER
Department
2Outline
- ITER cryogenic requirements
- ITER CRYO project frame
- ITER cryogenic system
- Cryo controls and instrumentation
- Conclusions
3Main duties
- Basic
- Cool-down of the cryostat and torus cryopumps
- Gradual cool-down and filling of the magnet
system and the 80 K thermal shield in about one
month - Cool-down of the NB cryopumps, pellet units and
gyrotrons - Maintain magnets and cryopumps at nominal
temperatures over a wide range of operating modes
with pulsed heat loads due to nuclear heating and
magnetic field variations - Accommodate periodic regeneration of cryopumps
- Accommodate resistive transitions and fast
discharges of the magnets and recover from them
in few days - Additional
- Ensure high flexibility and reliability
- Low maintenance
4Cryogenic capacity loads
- LHe cryoplant 65 kW equivalent _at_ 4.5 K
- Cooling of the superconducting magnet system
- 39 kW _at_ 4.2 K
- Cooling of HTS current leads
- 150 g/s GHe at 50 K
- Cooling of cryo-pumps with high regeneration
frequency - 6.5 kW _at_ 4.5 K and 70 g/s of LHe liquefaction
- Small users
- 1 kW _at_ 4.5 K (Gyrotron)
- LN2 cryoplant 1300 kW _at_ 80 K
- Thermal shielding
- up to 800 kW _at_ 80 K during chamber baking
- LHe cryoplant pre-cooling
- up to 280 kW _at_ 80 K during normal operation
- HTS 50 K extra cooling power
- up to 180 kW _at_ 80 K during normal operation
5Magnets Pulsed Head Load
6Operation scenarios
- Uninterrupted operation in order to maximize
machine availability - The tokamak will be operated during two 8-hour
shifts - The third shift will be used to recover nominal
cryogenic conditions, for short interventions and
to regenerate the cryopumps up to 470 K - The large dynamic loads prevent full redundancy
but allow continuous and uninterrupted operation
without plasma - Short maintenance periods of few days every two
weeks - Major shutdowns every 16 months
- RAMI analysis to improve the design and
requirements for spares
7Technical variants
- Analysis of technical variants compatible with
the requirements and basic design principles are
presently under study - Simplification of the layout and improvement of
performances, reliability and availability or
reduction of investment and operation costs - Review and update of heat loads
- Large dynamic loads handling
- Pulse mitigation by temporary by-pass of the
structure load - Use of liquid helium storage buffering and
complex process control - Helium management and cold quench tank
temperature level - Optimal size, number of cold boxes and parallel
operation (flow sharing) - Thermodynamic cycle optimization for the
refrigerators - Developments of technology and engineering
solutions for key components - Example SHe circulating pumps and heat
exchangers
8Outline
- ITER cryogenic requirements
- ITER CRYO project frame
- ITER cryogenic system
- Few thoughts on control and instrumentation
- Conclusions
9The ITER CRYO project frame
- Cryoplants system helium refrigerators, LN2 and
80K loop system, ancillary equipment
(warm/cold/liquid tanks, recovery purification
systems) - Cryodistribution system main distribution boxes
with cold circulating pumps and cold compressors,
cryolines from cryoplant building and inside
tokamak complex - Cryoplant procurement packages are based on
functional specs and include manufacturing,
delivery, installation on-site individual
sub-package acceptance test
10Cryogenics Schedule
11Outline
- ITER cryogenic requirements
- ITER CRYO project frame
- ITER cryogenic system
- Few thoughts on control and instrumentation
- Conclusions
12ITER Cryoplant System
Cryodistribution
13Cryoplant architecture
14Cryoplant architecture
Pictures courtesy of CERN
15Cryoplant layout option 1
80 K He loop
Unloading area
LN2 plant
Instrumentation (control) room
Power supply
Room for power supply
Unloading area
Option 1 LN2 plant and boxes of 80 K helium
loop are located at outdoor area
16ITER Cryodistribution System
Cryodistribution
17Cryodistribution architecture
18ITER Cryodistribution system
gt50 Cold Boxes, 3 km of cryolines, 4500 components
Coming From cryoplant
CTCB
ACB STR
ACB PF
ACB TF
ACB CS
ACB Cryopumps
25000 LHe tank
Different levels
19Cryodistribution system PID
20ACB structure PID
21ACB Structure Detail Design
22Outline
- ITER cryogenic requirements
- ITER CRYO project frame
- ITER cryogenic system
- Controls and instrumentation for cryogenics
- As personal views this presentation does not
necessarily reflect those from other involved
parties (IO and IN DA) - Conclusions
23Instrumentation requirements
- Cryogenic instrumentation (industrial
process/plants) - Pressure (1-200b, mbar, vacuum), Temperature
(300-3.7K), Flow (warm/cold 2-2000 g/s), - Gas quality impurities (N2/H20/CxHy-ppm)
- Actuators Control Pneumatic Valves, Quench
valves (mech/PV), Heaters, Motors (On/Off, speed
control) - Switches (safety interlocks)
- Cryoplants
- Installed redundancy for inner instrumentation
Cold Boxes - Specific components like turbines (speed sensor,
gas impurities) - Cryoditribution
- Sub-atmospheric circuits (helium guard)
- Speed/Freq. controllers for circulators/cold
comp. - High magnetic fields and radiation environment
- Accessibility constrains (operation scenarios)
- Installed redundancy for inner instrumentation
ACB
24Estimated I/O (tbc)
25Control requirements
- Cryoplants
- Modular individual control sub-systems
- Commissioning (staged, acceptance)
- Operation scenarios
- Dedicated PLC for critical components by
suppliers turbines - Cryoditribution
- High magnetic fields and radiation environment
- Accessibility constrains (operation scenarios)
- Dedicated PLC for critical components by
suppliers cold circulators, cold comp. - Master control system
- Cryo Integrated control system (IN, IO, EU)
- General/individual data/interlocks exchange with
other WBS (magnets, TS, cryopumps) - Machine interface (CODAC)
- Standardization hardware and software
- Flexibility and accessibility during
commissioning and first years of operation - Logging and post-mortem system for data/event
analysis - Quality control (software updates, modifications)
26Cryoplant control architecture?
OWS 1..x
27Cryoplant control architecture?
OWS 1..x
Data Servers
EWS 1..x
Ethernet
Storage
LHe CP1
LHe CP2
LHe CP3
Recup Purif.
80K Loop 12
LHe CB1
LHe CB2
LHe CB3
CTCB
LN2_1
LN2_2
28Cryodistribution architecture?
29Cryodistribution architecture?
EWS 1..x
OWS 1..x
Data Servers
Ethernet
Str. ACB
TF ACB
PF ACB
CS ACB
Cryopumps ACB
Accessibility constrains High magnetic field High
radiation enviroment
30Conclusions
- Cryogenics is a large industrial plant system
- Instrumentation and controls requirements are
well understood and identified - Controls architecture not yet defined
- RAMI analysis and other projects experience to be
used - Integration with clients (magnets, cryopumps, TS,
others) - Radiation and high magnetic fields impact on
cryodistribution instrumentation and electronics
has to be validated - Standardization and integration of all cryogenics
sub-systems is mandatory - Hardware (IC) and software
- To be defined before PA by involved parties
- Common strategy and standard to be defined by all
involved parties (IO, IN DA F4E) before PA
31THANK YOU!!
Manel.Sanmarti_at_f4e.europa.eu