An Overview of the EAST Project - PowerPoint PPT Presentation

About This Presentation
Title:

An Overview of the EAST Project

Description:

An Overview of the EAST Project – PowerPoint PPT presentation

Number of Views:57
Avg rating:3.0/5.0
Slides: 52
Provided by: songt
Learn more at: https://fire.pppl.gov
Category:
Tags: east | bens | overview | project

less

Transcript and Presenter's Notes

Title: An Overview of the EAST Project


1
EAST
ASIPP
An Overview of the EAST Project
Songtao Wu and the EAST Team Institute of Plasma
Physics, Chinese Academy of Sciences, P.O. Box
1126, Hefei, Anhui, 230031, P.R. China 1.
Introduction 2. Tokamak Machine and Key
Technologies 3. Results of the First
Commissioning 4. Future Plan 5. Summary

1
2
EAST
ASIPP
1. Introduction

2
3
EAST
ASIPP
The EAST National Project of China The
Experimental Advanced Superconducting Tokamak
(EAST) project was approved in 1998 by the China
government and began construction in 2000.
  • The Scientific and Engineering Missions of
    the EAST Project are
  • to study physical issues of the advanced
    steady-state operation modes
  • to establish technology basis of full
    superconducting tokamaks for future reactors


3
4
EAST
ASIPP
cryogenic and refrigerator system
Power supply system
Vacuum pumping and gas puffing system
Diagnostic system
Superconducting Tokamak Machine
The main construction tasks of the project
Experimental Hall
Test Facility System
Control and data processing system
Non-inductive current drive and heating system
Water cooling system

4
5
EAST
ASIPP
Main Parameters of the EAST Nominal Upgrade B
o 3.5 T 4.0 T IP 1 MA 1.5 MA Ro 1.7
m 1.7 m a 0.4 m 0.4 m R/a 4.25 4.25 Kx
1.2-1.5 1.5-2 dx 0.2-0.3 0.3-0.5 Heating
and Driving ICRH 3 MW 6 MW LHCD 3.5 MW 8
MW ECRH 0.5 MW 1.5 MW NBI 8 MW Pulse
length 1000 s Configuration Double-null
divertor Single-null divertor

5
6
EAST
ASIPP
The EAST machine assembly has been pre-completed
in Jan. 2006. The first engineering commissioning
began from Feb. 7, 2006 and finished on Mar. 17.

6
7
EAST
ASIPP
  • On Mar. 4 all superconducting coils were cooled
    down to lower than 4.5K.


7
8
EAST
ASIPP
  • Total 260 shots have been energized. The longest
    TF current duration was 5000 s and the highest TF
    current was 8200A.


8
9
EAST
ASIPP
ICRH LHCD system
CICC large scale magnet
Control data acquisition system
Most of key technologies are developed in ASIPP
Vacuum pumping system
SC magnet test facility
210MW Power supply system
2kW/4.5K Cryogenic refrigerator system

9
10
EAST
ASIPP
2. Tokamak Machine and Key Technologies

10
11
EAST
ASIPP
Main Components of the EAST Machine

11
12
EAST
ASIPP
Cryostat
Thermal Shield
Central Solenoid
PF Coils
Vacuum Vessel
TF Coils
EAST Device Height10 m Diameter8 m Weight414
ton
Supports of TFPF
Main Support

12
13
EAST
ASIPP
3 Tangential Ports
8 Standard Ports
Final VVTS Section Assembly
5 Big Ports
Final TF Assembly
Top View and Ports Arrangement of EAST

13
14
EAST
ASIPP
PF System
PF Parameters Coil No. 14 Iop 14.5 kA Bmax 4.5
T dB/dt lt 7 T/s Top lt4.2K Cond. CICC Material Nb
Ti
PF9
PF11
PF7
PF13
PF5
PF3
PF1
R1.94, a0.44, kx1.76, dx0.56
R1.94, a0.46, kx1.69, dlx0.54

14
15
EAST
ASIPP
TF System
Manifold Interface
TF Parameters Coil No. 16 Bmax 5.85 T
(6.72T) Iop 14.3 kA (16kA) Estored 298 MJ
(390MJ) Top lt4.2K (3.8K) Cond. CICC Material NbTi
Shearing Pins and Bolts
TF Wedges
The maximum central force is 1293 ton
The maximum out-plane torque is 332 Tonm
The maximum tress on TF is 340 MPa

15
16
EAST
ASIPP
16 completely welded sections of double-shell
structure
Vacuum Vessel
Vacuum Vessel Parameters Weight
43 ton IV-Surface( with ports) 162
m2 IV-Volume(without ports) 40 m3 Port
No. 48 Material 316L Toroidal
Resistance 85.4 µ?
48 ports for pumping, heating driving and
diagnostics
The maximum tress on VV is 170 MPa

16
17
EAST
ASIPP
Cryostat Vessel
Cryostat Vessel Parameters Inner Diameter
7322 mm Outer Diameter 7372 mm Height 7545
mm Port No. 72 Material 304L
The maximum stress with 1.5atm pressure inside CV
is 27MPa
The maximum tress on CV is 144 MPa

17
18
EAST
ASIPP
In-vessel Components
Divertor
Supports
Feed back control coil
Passive stabilizer
Cryopump
Cooling bake circuit

18
19
EAST
ASIPP
Superconducting Technology Development Main
Parameters of SC Strands Strand Diameter
0.85 mm Critical Current 500 A (at 4.5
K, 5 T) 426 A
(at 4.5 K, 5.8 T) Number of Filament
8910 Filament Diameter 6 µm Twist Pitch
10 mm CuSC 1.381 RRR
gt 70

19
20
EAST
ASIPP
Short Samples Parameters

20
21
EAST
ASIPP
B5.8 T dm/dt2.8 g/s
Ic are 10-12 lower than strand data. The
degradation could be due to the filaments broken
in the strand.
Lower Tcs than calculations could be caused by
high inter-strands transverse resistance and
stainless steel wrapping on the sub-cable.
Time constant are much lower than expected.
Wrapping function at high frequency was confirmed
by lower losses.

21
22
EAST
ASIPP
The main parameters of the EAST CICC
TF CS/Divertor Big PF
Rated peak field 5.8 T 4.5 T 2 T
Rated operation current (Iop) 14.3 kA 14.5 kA 14.5 kA
Rated operation temperature 4.2 K 4.2 K 4.2 K
Cable configuration (2SC2Cu)?3?4?51CCC (2SC2Cu)?3?4?51CCC (1SC2Cu)?3?4?51CCC
Conductor dimension 20.4? 20.4 mm2 20.3? 20.3 mm2 18.5? 18.5 mm2
Conduit thickness 1.5 mm 1.5 mm 1.5 mm
Number of SC strand 120 120 60
Number of Cu strand 12021 12021 12021
Diameter of SC strands 0.850.87 mm 0.850.87 mm 0.850.87 mm
Diameter of copper strands 0.98 mm 0.98 mm 0.98/0.87 mm
RRR of Cu strands gt 100 gt 100 gt 100
Coating materials Pb-30Sn-2Sb Nickel Pb-30Sn-2Sb
Solder thickness on strands 2-3 ?m 2 ?m 3 ?m
Cu fraction (fcu) 0.54 0.54 0.44
Helium fraction (fhe) 0.34 0.35 0.359
Iop/ Ic 0.28 0.224 0.31
Temperature margin (Tcs-Top) 1.88 K 2.54 K 2.29 K
Energy margin (?E) 250 mJ/cm3 350 mJ/cm3 400 mJ/cm3

22
23
EAST
ASIPP
A 600 m CICC jacketing line was set up in ASIPP
and more than 34 km CICC have been produced.
Conduit Cleaning
Conduit Surface Check
Conduit Welding
Conductor Extruding
Conductor Receiving

23
24
EAST
ASIPP
Technologies to fabricate PF and TF coils in
pre-bending and continuous winding way have been
developed.
15 PF coils fabricated

24
25
EAST
ASIPP
To test the superconducting performances of coils
before installation, a cryogenic test facility
system set up in ASIPP.
Power Supply 24 kA/0-100V(CW) 100kA/0800V(
5s)
Cryogenic test facility system
Cryostat with CLs Diameter 3.4 m Height
6.7 m Vacuum 1 10-5
? Current leads 2 pairs
20-30 kA
Control and Data Collection System
Refrigerator 500 W/4.5 k

25
26
EAST
ASIPP
The tests of the CS prototype coil had shown
pretty good results in 2003.
CS prototype coil inside the cryostat of the test
facility
Current charge/discharge
0.5 kA/s
Iq16.37 kA Top6.79K Bmax3.6T
1kA/s
Quench current test Extrapolated Iq 54kA (3.8K,
4.5T)
AC losses test

26
27
EAST
ASIPP
After TF prototype coil test, sixteen TF magnets
have been tested successfully and shown similar
performances
One TF coil inside the cryostat of the test
facility
Quench current test Extrapolated Iq 58kA (3.8K,
6.72T)
1 TF
6 TF
5 TF
4 TF
3 TF
2 TF
12 TF
13 TF
14 TF
15 TF
16 TF
8 TF
9 TF
10 TF
7 TF
11 TF

27
28
EAST
ASIPP
The central solenoid (CS) assembly, which is
consisted of six coils, has been tested before
installation.
CS in the assembly
CS installation for test

28
29
EAST
ASIPP
HTc Current Leads
  • To reduce the cryogenic consuming, EAST uses 5
    pairs HTc current leads at the first operation
    stage.
  • 13 pairs of HTc current leads have been tested
    with LN and at the same operation condition from
    15kA to 20kA.

Coolant inlet/outlet

29
30
EAST
ASIPP
Installation of the HTc Current Leads
LN2 vessel
HTc modules
Insulation breaks
CICC joint terminals

30
31
EAST
ASIPP
  • Cryogenic and Refrigerator System
  • The SC magnet system has a cold mass of 200 tons
    at 3.8-4.5K and 20 tons at 80K.
  • For normal operation the machine heat load
    estimated is about 890W/4K and 17kW/80K.
  • One pair of 14kA conventional current leads for
    the TF coils and 6 pairs of 15kA leads for the PF
    coils require 7.5g/s cooling flow.
  • An oil ring pump has been employed to reduce the
    helium suction pressure to 0.37 bars at the
    volumetric flow rate of 3100 Nm3/h for ensuring
    1050 W/3.5 K refrigeration ability.


31
32
EAST
ASIPP
Schematic Flow of Helium Refrigerator 1050W/3.5K
200W/4.5K 13 g/s LHe (1325)kW/80K

32
33
EAST
ASIPP
  • Power Supply System
  • The power supply system consists of
  • Power supplies for Toroidal Field (TFPS),
    Poloidal Field (PFPS), Fast Plasma Position
    Control (FPPS), Auxiliary Heating and Current
    Drive (AH/CDPS)
  • A new 110kV overhead line and a 110kV/83MVA
    substation was set up at ASIPP.

110kV/83MVA Power Substation

33
34
EAST
ASIPP


36 group 15 kA AC-DC convertors total nominal
power 210 MVA
The Power Distribution System
Dump resistance and explosive breakers

34
35
EAST
ASIPP
  • The LHCD System Consists of
  • 20 klystron amplifiers with CW output power of 2
    MW in total at a frequency of 2.45 GHz.
  • 1.5 MW/2.45 GHz, instead of 2 klystron amplifiers
    with 1.5 MW output power and 1000s pulse length
    at a frequency of 3.7 GHz.
  • Antennas consisting of 4 32 sub-wave guides.
  • A 4 MW/4.6 GHz system is planed to be set up in
    the future.
  • The ICRF System is Composed by
  • Two subsystems, each one has 1.5 MW output power
    and the frequency range is from 30MHz to 110MHz.


35
36
EAST
ASIPP
  • Control System
  • The EAST control system features PC (personal
    computer) constructed Distributed Control System
    (DCS), including plasma control system (PCS), and
    other sub-systems.
  • The EAST PCS is based on and developed from
    DIII-D PCS and strongly supported by DIII-D PCS
    team.
  • Aimed at Real-time Shaped Plasma Control
    (RT-EFIT).


36
37
EAST
ASIPP
DIII-D/EAST PCS is Flexible, Scalable Multi-cpu
Control System Supporting Arbitrarily Complex
Algorithms
DIIID/EAST plasma control system hardware
structure
  • Commercial Off-The-Shelf components

DIIID/EAST Tokamak
IDL-based GUI
Linux-based OS and C-code allows complex
algorithms, rapid modification and development
32 96 channel PCI format 250 kHz D-TACQ
digitizers
Intel VME cpu/digital and analog output converters
2.4 GB/sec Myrinet network
Multiple CPUs run in parallel 10 ?s -10 ms cycle
times
PCS real-time Network Gatewaycomputer and user
interface host
Remotely located real-time computers
3.1 GHz Real-time Intel computer array

37
38
EAST
ASIPP
  • Diagnostics
  • Limited diagnostics are employed, such as plasma
    current, position and shape, electron density and
    temperature, radiation power, impurity content,
    MHD and fluctuation, edge plasma, divertor and
    plasma facing components.
  • Only magnetic measurements, part of laser
    interferometers, plasma image and RGA will be
    newly built, while others will be modified from
    the HT-7 diagnostics equipment.


38
39
EAST
ASIPP
The assembly procedure of the EAST machine
consists of three main sub-procedures
The second procedure
The bases assembly procedure
The tori of VV, vacuum vessel TS and TF assembly
procedure
The peripheral assembly procedure

39
40
EAST
ASIPP
  • The bases assembly procedure
  • The three tori assembly procedure
  • The peripheral parts assembly procedure


40
41
EAST
ASIPP
View Inside the vacuum vessel of the EAST

41
42
EAST
ASIPP
3. Results of the First Commissioning

42
43
EAST
ASIPP
  • The main purposes of the first commissioning
  • Validation of correctness, reliability and
    security of the tokamak machine integrated with
    sub-systems, such as the cryogenic and
    refrigerator system, vacuum pumping system, the
    power supply system, feeders with current leads
    and superconducting bus-lines, etc.
  • Debugging and adjusting of the quench detection
    system, the interlock and safety system, the
    machine diagnostic system, PCS checking of the
    insulation, the magnetic field shapes and
    distribution, mass flow, pressure drop, CICC
    joint resistance, displacement of the magnet
    during cooling down and charging.
  • Providing necessary experiment data and suggested
    operation modes for the future operation.


43
44
EAST
ASIPP
  • Important achievements
  • The cryogenic ability of the system is above the
    design value and reached to 2.4kW/4.5K.
  • Four sets of PF power supply system and the TF
    power supply system energized different coils
    successfully.
  • The pumping system successfully operated through
    whole commissioning experiments.
  • The superconducting magnet system worked very
    well.
  • Quench detection and magnetic diagnostics were
    tested successfully.
  • Eight pairs of copper current leads and four HTc
    current leads worked properly.
  • Most of total eighty-seven CICC joint resistances
    are less than 10 n?. But few of them are more
    than 15 n? and but still acceptable.


44
45
EAST
ASIPP
  • Problems we suffered
  • Shafts of four turbines of the cryogenic system
    got stuck several times. Finally, one of them
    totally damaged.
  • After pumping and cooling down, the insulation
    resistance of the magnet system dropped down to
    less than 0.5M? (2.75kV) from 2G? (5.7kV) before
    the cryostat vessel was covered, which was caused
    by the dirtying surface on the current leads,
    quench detecting wire and its sockets.
  • One minor leakage was found during cooling down
    in the outer thermal shield system.


45
46
EAST
ASIPP
4. Future Plan

46
47
EAST
ASIPP
Three phases of operation

47
48
EAST
ASIPP
CICC Technology
SC magnets Technology
Insulation Technology
Machining
ITER related technologies developed in ASIPP
Power Supply System Technology
SC magnet test
Cryogenic Technology
Plasma Facing Components
HTc Current Leads
PCS

48
49
EAST
ASIPP
EAST vs. ITER
  • ITER
  • Experimental reactor
  • R6.2 m, a2 m
  • Pulse length 400 s
  • Single null plasma
  • Superconducting magnets, steady-state heating and
    diagnostics, remote control, shield and six
    tritium blankets
  • EAST
  • Experimental device
  • R1.9 m, a 0.5 m
  • Pulse length 1000 s CW
  • Single/Double null plasma
  • Superconducting magnets, steady-state heating and
    diagnostics, one or two tritium blankets
  • Experimental benchmark for ITER


49
50
EAST
ASIPP
5. Summary
  • All the main technologies mentioned above have
    been developed very well in ASIPP in the past
    five years.
  • The successful EAST first engineering
    commissioning gives the EAST team strong
    confidence that the EAST will be successfully
    constructed.
  • Now all the ports and main in-vessel components
    have been installed, except for the graphite
    armors.
  • The first physical experiment is going on right
    now. But the turbine problem happened again.
  • EAST system will provide fusion community a very
    good international research facility for steady
    state divertor plasma research.


50
51
EAST
ASIPP
Thanks for your attention!

51
Write a Comment
User Comments (0)
About PowerShow.com