Title: Net Present Value
1Net Present Value Other Investment Criteria
- FIL 240
- Prepared by Keldon Bauer
2Good Decision Criteria
- We need to ask ourselves the following questions
when evaluating decision criteria - Does the decision rule adjust for the time value
of money? - Does the decision rule adjust for risk?
- Does the decision rule provide information on
whether we are creating value for the firm?
3Discounted Payback - Example
- As the Chief Financial Officer of Spamway, Corp.,
you have been presented with the following two
potential projects. Assume a 9 discount rate.
4Net Present Value
- The philosophy behind the net present value (NPV)
is how much should adoption of the project have
on the overall value of the firm. - NPV is the sum of all outlays in present value
terms. - Since outlays are negative, and inflows are
positive, the net represents addition to value of
the firm.
5Net Present Value
- How much value is created from undertaking an
investment? - The first step is to estimate the expected future
cash flows. - The second step is to estimate the required
return for projects of this risk level. - The third step is to find the present value of
the cash flows and subtract the initial
investment.
6NPV - Example 1
321.45 Net Present Value
7NPV - Example 2
643.83 Net Present Value
8NPV Decision Rule
- If the NPV is positive, accept the project
- A positive NPV means that the project is expected
to add value to the firm and will therefore
increase the wealth of the owners. - Since our goal is to increase owner wealth, NPV
is a direct measure of how well this project will
meet our goal.
9Decision Criteria Test - NPV
- Does the NPV rule account for the time value of
money? - Does the NPV rule account for the risk of the
cash flows? - Does the NPV rule provide an indication about the
increase in value? - Should we consider the NPV rule for our primary
decision criteria?
10Payback Period
- Meant to measure the time it takes to recoup the
initial investment (ignoring the time value of
money). - The quicker the payback period (smaller the
number), the better! - To calculate payback period follow the following
4 steps
11Payback Period - Steps
- Create cash flow time line.
- Add a line for cumulative cash flow.
- Identify the last year that cumulative cash flow
is negative, we will call it A. - Payback period is calculated as follows
12Payback Period - Example 1
Step 3 Last negative year is 3 È
13Payback Period - Example 2
Step 3 Last negative year is 3 È
14Decision Criteria Test - Payback
- Does the payback rule account for the time value
of money? - Does the payback rule account for the risk of the
cash flows? - Does the payback rule provide an indication about
the increase in value? - Should we consider the payback rule for our
primary decision criteria?
15Advantages and Disadvantages of Payback
- Disadvantages
- Ignores the time value of money
- Requires an arbitrary cutoff point
- Ignores cash flows beyond the cutoff date
- Biased against long-term projects, such as
research and development, and new projects
- Advantages
- Easy to understand
- Adjusts for uncertainty of later cash flows
- Biased towards liquidity
16Internal Rate of Return
- This is the most important alternative to NPV
- It is often used in practice and is intuitively
appealing - It is based entirely on the estimated cash flows
and is independent of interest rates found
elsewhere
17IRR Definition and Decision Rule
- Definition IRR is the return that makes the NPV
0 - Decision Rule Accept the project if the IRR is
greater than the required return - The internal rate of return (IRR) represents the
effective interest earned on the investment.
18Computing IRR For The Project
- If you do not have a financial calculator, then
this becomes a trial and error process - Calculator
- Enter the cash flows as you did with NPV
- Press IRR and then CPT
- IRR 16.13 gt 12 required return
- Do we accept or reject the project?
19Discounted Payback - Example
- As the Chief Financial Officer of Spamway, Corp.,
you have been presented with the following two
potential projects. Assume a 9 required return.
20IRR - Example 1
?
IRR 16.82
21IRR - Example 2
?
IRR 16.37
22IRR Problems
- IRR has two major problems.
- First, it assumes that all cash inflows will earn
the IRR rate instead of the much more likely
discount rate. - Second, depending on the cash flow streams there
can be more than one IRR.
23Multiple IRRs
- As an example of more than one IRR, lets assume
you have a project that will return a net 4,000
in year zero (salvage of old machine, and
financing, etc.), nets a negative 25,000 in year
one, and finishes with a positive 25,000 in year
three.
24Multiple IRRs - Example
- Since the IRR is defined as the discount rate
which yields an NPV of zero
25Multiple IRRs - Example
- Multiplying both sides by (1k)2 yields
Factoring the above polynomial
k IRR 25 or 400
26Multiple IRRs - Example
27Decision Criteria Test - IRR
- Does the IRR rule account for the time value of
money? - Does the IRR rule account for the risk of the
cash flows? - Does the IRR rule provide an indication about the
increase in value? - Should we consider the IRR rule for our primary
decision criteria?
28Advantages of IRR
- Knowing a return is intuitively appealing
- It is a simple way to communicate the value of a
project to someone who doesnt know all the
estimation details - If the IRR is high enough, you may not need to
estimate a required return, which is often a
difficult task
29NPV vs. IRR
- NPV and IRR will generally give us the same
decision - Exceptions
- Non-conventional cash flows cash flow signs
change more than once - Mutually exclusive projects
- Initial investments are substantially different
- Timing of cash flows is substantially different
30IRR and Nonconventional Cash Flows
- When the cash flows change sign more than once,
there is more than one IRR - When you solve for IRR you are solving for the
root of an equation and when you cross the x-axis
more than once, there will be more than one
return that solves the equation - If you have more than one IRR, which one do you
use to make your decision?
31Conflicts Between NPV and IRR
- NPV directly measures the increase in value to
the firm - Whenever there is a conflict between NPV and
another decision rule, you should always use NPV - IRR is unreliable in the following situations
- Non-conventional cash flows
- Mutually exclusive projects
32Modified Internal Rate of Return
- IRR has some problems that MIRR rectifies.
- There is only one MIRR for all projects.
- Reinvestment is assumed to be at k.
- MIRR can be seen as a more realistic return on
invested capital. - To calculate MIRR, you should follow 4 steps
33Modified Internal Rate of Return
- Create cash flow time line.
- Sum the present value of all cash outlays.
- Sum the future value of all cash inflows in the
projects final period. - Using only the present value from 2 and the
future value from 3, calculate the interest rate.
34MIRR - Example
- As the Chief Financial Officer of Spamway, Corp.,
you have been presented with the following two
potential projects. Assume a 9 discount rate.
35MIRR - Example 1- Steps 1 2
Because all outflows are already in present
value, no adjustments are needed.
36MIRR - Example 1 - Step 3
Future Value 2,802.53
37MIRR - Example 1 - Step 4
MIRR 13.32
38MIRR - Example 2 - Steps 1 2
Because all outflows are already in present
value, no adjustments are needed.
39MIRR - Example - Step 3
Future Value 5,606.49
40MIRR - Example - Step 4
MIRR 13.32
41NPV Profiles
- To create an NPV profile, plot NPV on the Y axis
and the discount rate on the X axis. - Since the discount rate should be sensitive to
changes in project risk, the NPV profile will
show how sensitive the projected NPV is to the
appropriate discount rate.
42NPV Profiles - Figure 8-3
43NPV Profiles
- The crossover rate is the rate at which both
projects have the same NPV. - If one knows the crossover rate, then one can
assess the probability of the discount rate being
that low (high), and can better rank the priority
of potential projects.
44NPV Profiles
- The slope of the lines in an NPV profile measures
the sensitivity of NPV to the discount rate
chosen. - In the books example the L represents a longer
payback and S a shorter payback. - The longer the payback the more sensitive the NPV
will be to the discount rate.
45Independent Projects
- If two projects are independent, then adopting
one does not affect the firms ability to adopt
the other. - If two projects are independent, all projects
with positive NPV and/or IRR and MIRR greater
than the discount rate should be adopted.
46Independent Projects
- All projects with positive NPV add value to the
firm. - All projects where IRR or MIRR are greater than
the discount rate will bring more return than
their cost of capital.
47Mutually Exclusive Projects
- If two projects are mutually exclusive, then the
firm can only adopt one of the two projects. - So which of the techniques should be used to
decide which project to adopt?
48Profitability Index
- Measures the benefit per unit cost, based on the
time value of money - A profitability index of 1.1 implies that for
every 1 of investment, we create an additional
0.10 in value - This measure can be very useful in situations
where we have limited capital
49Profitability Index - Example
- As the Chief Financial Officer of Spamway, Corp.,
you have been presented with the following two
potential projects. Assume a 9 discount rate.
50Profitability Index - Example
- Step 1 Calculate the present value of all
future cash flows - PV of G 1,821.45
- PV of Y 3,643.83
- Step 2 Divide the present value from step 1 by
the initial outlay
51Advantages and Disadvantages of Profitability
Index
- Advantages
- Closely related to NPV, generally leading to
identical decisions - Easy to understand and communicate
- May be useful when available investment funds are
limited
- Disadvantages
- May lead to incorrect decisions in comparisons of
mutually exclusive investments
52What is a Real Option?
- Real options exist when managers can influence
the size and risk of a projects cash flows by
taking different actions during the projects
life in response to changing market conditions. - Alert managers always look for real options in
projects. - Smarter managers try to create real options.
53What are Some Types of Real Options?
- Investment timing options
- Growth options
- Expansion of existing product line
- New products
- New geographic markets
54Types of Real Options (Continued)
- Abandonment options
- Contraction
- Temporary suspension
- Flexibility options