FLIXBOROUGH A MODIFICATION ACCIDENT JUNE 1974 - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

FLIXBOROUGH A MODIFICATION ACCIDENT JUNE 1974

Description:

... was a mound of ash and fused metal. Plant declared safe 13 days after the ... Location of key buildings 2 accidents resulted in the total destruction of or ... – PowerPoint PPT presentation

Number of Views:623
Avg rating:3.0/5.0
Slides: 20
Provided by: carolw60
Category:

less

Transcript and Presenter's Notes

Title: FLIXBOROUGH A MODIFICATION ACCIDENT JUNE 1974


1
FLIXBOROUGH A MODIFICATION ACCIDENT JUNE 1974
2
The NYPRO PLANT operated by the ROYAL DUTCH
SHELL COMPANYat FLIXBOROUGH
3
Produced caprolactam H2N(CH2)5COOH a raw material
for the manufacture of Nylon 6 from benzene
4
PRODUCTION OF nylon 6 from BENZENE
  • Benzene C6H6 H2-------------gt Cyclohexane
    C6H12 under high pressure
  • Cyclohexane NH3 O2 ---------gt Cyclohexane
    oxide 02 needs to be carefully controlled
  • Cyclohexane oxide oleum -------gt Caprolactam
  • Caprolactam H20 ---gt HOOC(CH2)5NH2 ? 260o
    ------------------------------gt Nylon 6
  • --C(CH2)5NC(CH2)5N-- n nH20
  • 0 HO H

5
PRE ACCIDENT
  • Brine system used to cool the reactors was
    shutdown for repair
  • Water containing nitrates used instead of brine
  • Reactor 5 (out of 6 in series) taken out of
    system as it was leaking cyclohexane
  • A temporary by-pass put in a dog leg with
    bellows was used to connect reactors 4 6
  • By pass inadequately supported
  • Repair was rushed and not built under the
    supervision of an engineer.
  • System checked using N2 instead of H20 the
    STANDARD SAFETY TEST

6
(No Transcript)
7
ACCIDENT
  • 1st June pressure built up quickly
  • Cause was not found -almost certainly a high
    presure N2 leak into the system
  • Fire detected on an 8 section of pipe
  • By pass pipe ruptured - under the strain of high
    prssure, high temperature and stress fracture
    caused by the nitrates in the cooling water
  • 60 seconds later the H2 plant caught light and
    detonation of 30 tons of cylohexane occurred
  • Fires lasted 10 days

8
Violent Explosion
  • 28 men died - no one survived from the control
    room
  • Only 8 bodies recovered
  • 53 other workers needed hospitalised treatment
  • Blast waves felt 4 miles away
  • 18 million in todays terms 200 million asset
    totally destroyed
  • 1821 houses, 167 shops/factories damaged
  • Plant was a mound of ash and fused metal
  • Plant declared safe 13 days after the accident

9
What went wrong?
  • Changing the cooling procedure using water
    instead of brine caused stress corrosion in
    reactor 5. Nitrate induced cracking was known by
    METALLURGISTS but was less well known by CHEMICAL
    ENGINEERS MODIFICATION 1
  • Pressure of cooling water higher than that used
    with brine SIGNIFICANCE NOT KNOWN
  • Inadequate design of dog leg
    by-pass,connecting reactors 4 6.The men
    responsible for building the 20 temporary by
    -pass were not engineers.THEY DID NOT KNOW THAT
    THEY DID NOT KNOW MODIFICATION 2

10
  • The modified system was tested using pressurised
    N2 for leaks the STANDARD SAFETY TEST uses H20,
    had water been used the by-pass would have been
    found to be defective MODIFICATION 3
  • Inadequate support of by-pass, bellows free to
    rotate when pressure rose
  • By-pass pipe and bellows were not inspected
  • Design of plant inadequate not enough thought to
    the potentials of an accident
  • Lack of N2 for inerting - putting out of fires
  • Lack of provision for releasing gas build ups
  • .

11
  • There was no professional engineer in the plant
  • at the time of the accident - and there were
  • critical decisions to be made
  • Huge quantities of highly inflammable
  • cyclohexane stored on site.
  • Modification approval not taken seriously,
  • British Standards neither consulted nor
  • adhered to, no body consulted the British
  • Standards Handbook

12
LESSONS DRAWN
  • Modifications to be designed, constructed, tested
    and maintained to the same standards as the
    original plant - there needs to be a full
    assessment of the potential consequences
  • All managers to visibly inspect the plant
  • A full assessment of potential consequences if
    there is a failure in the plant
  • Companies to ensure they employ enough qualified
    and experienced staff to make critical decisions
  • Plants to be laid out to avoid the domino
    effect
  • Occupied buildings close to hazardous plants to
    be blast resistant

13
  • The storage of hazardous compounds to be kept to
    a minimum
  • Sufficient inerting material on site.
  • Any modifications, permanernt or temporary are
    the source of a potential disaster, which may
    change the validity and the results of HAZOP and
    Risk Analysis

14
(No Transcript)
15
  • HIGH COST ACCIDENTS SINCE
  • FLIXBOROUGH
  • Since Flixborough there have been 24 UK high cost
    accidents conservative estimate 500 million
    (1996 values).
  • In most high cost accidents there were no
    deaths (two had one death and one had five
    deaths). Several accidents with a high death toll
    eg Bhopal around 4000 deaths and Mexico City gt500
    deaths were not high cost
  • COMMON FEATURES
  • Isolation valves - problems with isolation leaks
    of ignited flammablesubstances was a major factor
    in 2 accidents. In each case isolating valves
    could not be closed either because they were not
    remotely operable or couldnt be accessed as too
    close to the fire/damaged by the fire

16
  • Fire water -in several accidents the water
    supplies for fire fighting were inadequate
  • Storage protocol a lack of understanding and poor
    management of storage/process/chemical
    segregation was a factor in 3 accidents
  • Perceived LOW risk at least 2 accidents involved
    activites which were not considered to be the
    main high risk activity on site
  • Escalation potential- in 2 accidents the intense
    heat generated by the fire posed a real threat of
    escalation to involve adjacent storage tanks. The
    fire services set up water coooling monitors
  • Routine inspection maintenance of critical
    equipment -3 accidents revealed deficiences in
    the inspection maintenance procedures

17
  • Unreliable inadequate control systems-4
    accidents revealed a combination of inadequate
    and unreliable process control equipment eg pump
    failed for several hours, in another level
    indicators were KNOWN to give false readings, in
    another the process system failed to identify the
    correct position of valve equipment and in the
    fourth vital pressure information was not
    displayed on the VDU used by the operators
  • Location of key buildings 2 accidents resulted in
    the total destruction of or severe damage to the
    control room buildings
  • Loss of process control- 2 of the accidents
    resulted in runaway reactions
  • Information to the public- 2 accidents revealed
    that information to the public was inadequate-
    great public concern was generated!

18
  • MAJOR ACCIDENTS 1999-2002
  • COMAH (Control of Major Accident Hazards) apply
    to 1200 establishments that have the potential to
    cause major accidents. The general duty of the
    regulationsis that Every Operator shall take all
    measures necessary to prevent major accidents and
    limit their consequencesto persons and the
    environment
  • 1999 - 2002 there were 21 COMAH major accidents
  • 4 prosecutions 5 investigations ongoing
  • Employee error- failure to follow procedures,
    runaway chemical reaction cause unknown, ruptured
    bellows, corrosion of defective welds/ tanks,
    pipework failure, ruptured valves

19
  • Inadequate maintenance, pipe fatigue, incorrrect
    setting of valves all contributed to these
    accidents
  • FAILURES
  • Check pipework not corroded
  • Bellows not to correct specification
  • Lack of back up isolation valves
  • Incompatible substances stored in the same
    warehouse
  • Inadequate smoke detection and fire fighting
    facilities
  • Time delays 50 minutes before accident reported
    to emergencies services
  • Inadequate identification of potentially
    hazardous imurities
  • Hazard markings not checked on tankers, driver
    documentation not checked allcauses of accidents
Write a Comment
User Comments (0)
About PowerShow.com