Title: CPM Model
1CPM Model In 1958 Du Pont Company used a
technique called Critical Path Method (CPM) to
schedule and control a very large project like
overhauling of a chemical plant, there by
reducing the shutdown period from 130hrs to 90
hrs saving the company 1 million dollar. Both of
these techniques are referred to as project
scheduling techniques.
2Differences between PERT CPM
3(No Transcript)
4- Cost considerations in PERT / CPM
- The total cost of any project comprises of two
costs. - Direct cost - material cost, manpower loading
- Indirect cost - overheads such as managerial
services, equipment rent, building rent etc. -
5 Direct cost
Crash
Normal
Job duration
Shorter the duration higher will be the Direct
expenses
6 Indirect cost
Normal
Crash
Job duration
Shorter the duration lesser will be the Indirect
expenses
7Total cost
Cost
Direct cost
Indirect cost
Normal
Optimum
Crash
Job duration
8Find the lowest cost and optimum cost schedule
for the following project, given the over head
expenses as Rs.45/-day.
91.Construction of the Network
4
7 - 3
10
3 -1
1
2
5 - 2
40
20
4 - 2
40
3
Normal duration Crash duration
Key
Cost of crashing per day in Rs.
102.Determination of Critical path
4
7 - 3
10
3 -1
1
2
5 - 2
40
20
4 - 2
40
3
Normal duration Crash duration
Key
Cost of crashing per day in Rs.
11Step 1.
3 -1
4 - 2
5 - 2
1
3
2
4
20
40
40
4
7 - 3
10
12 days
12Step 2.
3 -1
4 - 2
3 - 2
1
3
2
4
20
40
40
7 - 3
10
10 days
13Step 3.
3 -1
4 - 2
2 - 2
1
3
2
4
20
40
40
6 - 3
10
9 days
14Step 4.
1 -1
4 - 2
2 - 2
1
3
2
4
20
40
40
6 - 3
10
7 days
15Step 5.
3 -1
2 - 2
2 - 2
1
3
2
4
20
40
40
4 - 3
10
5 days
16Differences between PERT CPM
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)