Title: Injector, Sector 21, Bunch Compressor 1
1LCLS Maintenance Personnel and Procedures Paul
Bellomo
2Topics
- Scope and Perspective
- Why we know we are ready
- Department descriptions
- ARTEMIS
- The maintenance process
- Examples
3Scope and Perspective
- Accelerator equipment
- New electrical, mechanical, electro-mechanical
and electronic equipment from the injector gun
through the end of the tune-up dump TD-11. - New control room in Building 5
- New substations K10B, S520, MCC S20, panel-boards
- Operations Directorate
- 12 Departments, only 5 directly involved
- Controls, CEF, Klystron/Microwave, Mechanical
Fabrication, Power Conversion - Perspective
- Maintenance departments
4Why We Know We Are Ready
- All departments
- LCLS equipment possesses some new features, but
is not totally unlike the equipment that SLAC
currently services and maintains - Designers are the persons/groups that will
maintain the equipment - Maintenance personnel are qualified and have been
involved in the LCLS design from the start.
Training requirements are modest and provided by
LCLS, Department, or outside agency - Staff quantity is adequate to handle increased
LCLS workload. The documentation (detailed later)
needed to support the systems exist - Procedures (detailed later) needed to maintain
the systems exist
5Department Descriptions
- Department Head Hamid Shoaee, staff of 75
- Software and hardware sections
- Software Section
- Write low-level applications, EPICS drivers,
displays - Maintain MATLAB infrastructure (licenses), ensure
compatibility with all control room platforms - Provide network hardware and software
- Provide control room infrastructure (alarms,
displays, servers and workstations) - Development and maintenance are the same people
6Department Description - Controls (Continued)
- Hardware Section
- Beam Containment System (BCS)
- Prevents radiation from 'escaping' the shielding
enclosure - BSOICs, BTMs, LIONS, toroids and current monitors
- Machine Protection System (MPS)
- Protect equipment from beam damage
- VME processor-based protection ion chambers
(PICs), RTDs, digital monitors - Personnel Protection System (PPS)
- Protect personnel from radiation exposure, laser
and electrical hazards - PLC driven systems
- Vacuum - PLC based gages, valves, pumps and
interlocks - Movers - Tables, mirrors, cameras, wire scanners
7- Department Head John Weisend, staff gt 150
- CEF Operations - Bernie Romero, staff of 28
- Electrical maintenance of substations and
electrical distribution equipment - Beam-line manifolds and plumbing
- Documentation
- One-line diagrams
- Panel-board schedules
- Manufacturer drawings and instruction manuals
- Beam line assembly and layout drawings
8Klystron/Microwave Department
- Department Head - Chris Pearson, staff of 80
- Microwave Engineering and Maintenance/AMRF, staff
of 15 - Positron Source, Damping Rings, LINAC, LCLS LINAC
and SLC RF systems and 2856MHz pulsed klystrons - PEP (HER and LER) and SPEAR 3 RF systems and 1.2
MW, 476MHz CW klystrons - Documentation
- Rack front views and Captar rack profile drawings
- Electrical interconnect diagrams, cable database
- Electronic chassis diagrams
- Manufacturer drawings and instruction manuals
- ELPs, EWPs, bench test, hi-pot procedures
9Mechanical Fabrication Department (MFD)
- Department Head Karen Fant, staff of 80
- Mechanical fabrication/maintenance no design
- Vacuum gages and pumps on the vacuum side,
pneumatic valves, beam pipe and other components
designed by others (LCLS staff) - Magnet cooling water hoses, disassemble magnets
to find magnet problems and ground faults - On-call support of Operations
- Documentation
- Beam line assembly and layout drawings
- Vacuum pump-down procedures
10- Department Head Paul Bellomo, staff of 75
- DC magnet power systems and RF modulators
- Cables, cable tray and raceways
- Dedicated maintenance staff of 31 people, 24/7,
3-shift operation - Participate in power system commissioning
- Documentation
- Rack front views and Captar rack profile drawings
- Electrical interconnect diagrams, cable database
- Electronic chassis diagrams
- Manufacturer drawings and instruction manuals
- ELPs, EWPs, bench test, hi-pot procedures
11ARTEMIS
- Accelerator REMEDY Trouble Entry Maintenance
Information System - Web-based problem reporting, work scheduling and
work status program - Report and track both hardware and software
problems - Incorporates ISMS core functions
- Five states
- New Entry report problems or schedule
maintenance - In Progress Jobs in progress or have more work
to do - Scheduled Jobs Input from the New Entry state
- Review To Close All known work completed, ready
for management review - Closed trouble report entered into archive
12ARTEMIS
13The Process
14Example S20 Power Distribution Layout
15Example One-Line Diagram
Substation K10B 13.8kV480V to S20 MCC to 6 Power
Supply Racks Portion of S20 MCC shown
Excerpt from ID-950-075-03
16Example Rack/Equipment Profile
17Example Electrical Interconnect (EI/ELP) Diagram
18The PCD Process Example 1
- LCLS bend magnet system fails unexpectedly at
3AM. The indications are that a power supply has
failed. - LCLS Operations files an ARTEMIS and also
notifies the PCD owl shift supervisor/maintenance
manager (MM). Ops classifies the problem as
critical, because the machine is down without
this particular magnet. - MM evaluates the system, reviews past ARTEMIS
reports and chooses appropriate technicians to
troubleshoot the problem. - The MM, the technicians then assess the
situation, from the technical, logistics and
safety standpoints. The system is 480VAC input,
40VDC output. - Appropriate test equipment and PPE (Category 0
with Class 0 gloves) - The group notifies Ops that it is responding to
the call. Ops turns the system over to PCD. PCD
applies LOTO. ARTEMIS upgraded to in process
19The PCD Process Example 1 Continued
- Work progresses power system will not turn on.
After several hours, the solution is not readily
apparent. - Ops escalates the problem to the designated
system expert or Department Head. After 3 hours
without resolution the Department Head and LCLS
manager are notified. Work continues - The technical expert finds and solves a short in
the power supply rectifier. Parts are
field-replaced. - Ops is notified that the system is running. The
system is returned to Ops. - Technicians file review to close ARTEMIS
report, file e-log detailing the problem, the
solution and parts used. - The PCD MM checks the parts inventory and if
below a pre-determined critical level, orders
replacement parts. - PCD closes the job internally
20The PCD/MFD Process Example 2
- A ground fault is discovered in a magnet system.
Ops files ARTEMIS and notifies PCD. - The fault keeps the system off. It must be
repaired immediately - PCD locks out the system. They troubleshoot the
system and determine that the ground fault is in
the magnet. PCD asks Ops to notify MFD. The
ARTEMIS is annotated and responsibility
re-assigned. - PCD replaces personal LOTO with group LOTO. The
PCD MM is now responsible for the system. - MFD is called. MFD responds and confers with PCD.
PCD demonstrates that the power supply cannot be
turned on. - MFD apply personal locks over the PCD group
locks. MFD apply other LOTO, verify magnet
ground fault existence and perform work necessary
to remove the ground fault.
21The PCD/MFD Process - Example 2 Continued
- The ground fault is found and repaired. The
magnet is re-assembled and hi- potted. - MFD personnel remove their locks. PCD is
re-called. - PCD replaces Group with personal locks. PCD
hi-pots the system, remove their locks, turn the
system on and release it to Ops. - PCD technicians file a review to close the
ARTEMIS and file e-log entries - PCD MM conducts safety de-briefing and closes the
job
22Last Slide
- The SLAC maintenance groups are ready and eager
to safely and professionally support the LCLS
project