Injector, Sector 21, Bunch Compressor 1 - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Injector, Sector 21, Bunch Compressor 1

Description:

Beam-line manifolds and plumbing. Documentation. One-line diagrams. Panel-board schedules ... Example One-Line Diagram. Excerpt from ID-950-075-03 ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 23
Provided by: paulbe5
Category:

less

Transcript and Presenter's Notes

Title: Injector, Sector 21, Bunch Compressor 1


1
LCLS Maintenance Personnel and Procedures Paul
Bellomo
2
Topics
  • Scope and Perspective
  • Why we know we are ready
  • Department descriptions
  • ARTEMIS
  • The maintenance process
  • Examples

3
Scope and Perspective
  • Accelerator equipment
  • New electrical, mechanical, electro-mechanical
    and electronic equipment from the injector gun
    through the end of the tune-up dump TD-11.
  • New control room in Building 5
  • New substations K10B, S520, MCC S20, panel-boards
  • Operations Directorate
  • 12 Departments, only 5 directly involved
  • Controls, CEF, Klystron/Microwave, Mechanical
    Fabrication, Power Conversion
  • Perspective
  • Maintenance departments

4
Why We Know We Are Ready
  • All departments
  • LCLS equipment possesses some new features, but
    is not totally unlike the equipment that SLAC
    currently services and maintains
  • Designers are the persons/groups that will
    maintain the equipment
  • Maintenance personnel are qualified and have been
    involved in the LCLS design from the start.
    Training requirements are modest and provided by
    LCLS, Department, or outside agency
  • Staff quantity is adequate to handle increased
    LCLS workload. The documentation (detailed later)
    needed to support the systems exist
  • Procedures (detailed later) needed to maintain
    the systems exist

5
Department Descriptions
  • Department Head Hamid Shoaee, staff of 75
  • Software and hardware sections
  • Software Section
  • Write low-level applications, EPICS drivers,
    displays
  • Maintain MATLAB infrastructure (licenses), ensure
    compatibility with all control room platforms
  • Provide network hardware and software
  • Provide control room infrastructure (alarms,
    displays, servers and workstations)
  • Development and maintenance are the same people

6
Department Description - Controls (Continued)
  • Hardware Section
  • Beam Containment System (BCS)
  • Prevents radiation from 'escaping' the shielding
    enclosure
  • BSOICs, BTMs, LIONS, toroids and current monitors
  • Machine Protection System (MPS)
  • Protect equipment from beam damage
  • VME processor-based protection ion chambers
    (PICs), RTDs, digital monitors
  • Personnel Protection System (PPS)
  • Protect personnel from radiation exposure, laser
    and electrical hazards
  • PLC driven systems
  • Vacuum - PLC based gages, valves, pumps and
    interlocks
  • Movers - Tables, mirrors, cameras, wire scanners

7
  • Department Head John Weisend, staff gt 150
  • CEF Operations - Bernie Romero, staff of 28
  • Electrical maintenance of substations and
    electrical distribution equipment
  • Beam-line manifolds and plumbing
  • Documentation
  • One-line diagrams
  • Panel-board schedules
  • Manufacturer drawings and instruction manuals
  • Beam line assembly and layout drawings

8
Klystron/Microwave Department
  • Department Head - Chris Pearson, staff of 80
  • Microwave Engineering and Maintenance/AMRF, staff
    of 15
  • Positron Source, Damping Rings, LINAC, LCLS LINAC
    and SLC RF systems and 2856MHz pulsed klystrons
  • PEP (HER and LER) and SPEAR 3 RF systems and 1.2
    MW, 476MHz CW klystrons
  • Documentation
  • Rack front views and Captar rack profile drawings
  • Electrical interconnect diagrams, cable database
  • Electronic chassis diagrams
  • Manufacturer drawings and instruction manuals
  • ELPs, EWPs, bench test, hi-pot procedures

9
Mechanical Fabrication Department (MFD)
  • Department Head Karen Fant, staff of 80
  • Mechanical fabrication/maintenance no design
  • Vacuum gages and pumps on the vacuum side,
    pneumatic valves, beam pipe and other components
    designed by others (LCLS staff)
  • Magnet cooling water hoses, disassemble magnets
    to find magnet problems and ground faults
  • On-call support of Operations
  • Documentation
  • Beam line assembly and layout drawings
  • Vacuum pump-down procedures

10
  • Department Head Paul Bellomo, staff of 75
  • DC magnet power systems and RF modulators
  • Cables, cable tray and raceways
  • Dedicated maintenance staff of 31 people, 24/7,
    3-shift operation
  • Participate in power system commissioning
  • Documentation
  • Rack front views and Captar rack profile drawings
  • Electrical interconnect diagrams, cable database
  • Electronic chassis diagrams
  • Manufacturer drawings and instruction manuals
  • ELPs, EWPs, bench test, hi-pot procedures

11
ARTEMIS
  • Accelerator REMEDY Trouble Entry Maintenance
    Information System
  • Web-based problem reporting, work scheduling and
    work status program
  • Report and track both hardware and software
    problems
  • Incorporates ISMS core functions
  • Five states
  • New Entry report problems or schedule
    maintenance
  • In Progress Jobs in progress or have more work
    to do
  • Scheduled Jobs Input from the New Entry state
  • Review To Close All known work completed, ready
    for management review
  • Closed trouble report entered into archive

12
ARTEMIS
13
The Process
14
Example S20 Power Distribution Layout
15
Example One-Line Diagram
Substation K10B 13.8kV480V to S20 MCC to 6 Power
Supply Racks Portion of S20 MCC shown
Excerpt from ID-950-075-03
16
Example Rack/Equipment Profile
17
Example Electrical Interconnect (EI/ELP) Diagram
18
The PCD Process Example 1
  • LCLS bend magnet system fails unexpectedly at
    3AM. The indications are that a power supply has
    failed.
  • LCLS Operations files an ARTEMIS and also
    notifies the PCD owl shift supervisor/maintenance
    manager (MM). Ops classifies the problem as
    critical, because the machine is down without
    this particular magnet.
  • MM evaluates the system, reviews past ARTEMIS
    reports and chooses appropriate technicians to
    troubleshoot the problem.
  • The MM, the technicians then assess the
    situation, from the technical, logistics and
    safety standpoints. The system is 480VAC input,
    40VDC output.
  • Appropriate test equipment and PPE (Category 0
    with Class 0 gloves)
  • The group notifies Ops that it is responding to
    the call. Ops turns the system over to PCD. PCD
    applies LOTO. ARTEMIS upgraded to in process

19
The PCD Process Example 1 Continued
  • Work progresses power system will not turn on.
    After several hours, the solution is not readily
    apparent.
  • Ops escalates the problem to the designated
    system expert or Department Head. After 3 hours
    without resolution the Department Head and LCLS
    manager are notified. Work continues
  • The technical expert finds and solves a short in
    the power supply rectifier. Parts are
    field-replaced.
  • Ops is notified that the system is running. The
    system is returned to Ops.
  • Technicians file review to close ARTEMIS
    report, file e-log detailing the problem, the
    solution and parts used.
  • The PCD MM checks the parts inventory and if
    below a pre-determined critical level, orders
    replacement parts.
  • PCD closes the job internally

20
The PCD/MFD Process Example 2
  • A ground fault is discovered in a magnet system.
    Ops files ARTEMIS and notifies PCD.
  • The fault keeps the system off. It must be
    repaired immediately
  • PCD locks out the system. They troubleshoot the
    system and determine that the ground fault is in
    the magnet. PCD asks Ops to notify MFD. The
    ARTEMIS is annotated and responsibility
    re-assigned.
  • PCD replaces personal LOTO with group LOTO. The
    PCD MM is now responsible for the system.
  • MFD is called. MFD responds and confers with PCD.
    PCD demonstrates that the power supply cannot be
    turned on.
  • MFD apply personal locks over the PCD group
    locks. MFD apply other LOTO, verify magnet
    ground fault existence and perform work necessary
    to remove the ground fault.

21
The PCD/MFD Process - Example 2 Continued
  • The ground fault is found and repaired. The
    magnet is re-assembled and hi- potted.
  • MFD personnel remove their locks. PCD is
    re-called.
  • PCD replaces Group with personal locks. PCD
    hi-pots the system, remove their locks, turn the
    system on and release it to Ops.
  • PCD technicians file a review to close the
    ARTEMIS and file e-log entries
  • PCD MM conducts safety de-briefing and closes the
    job

22
Last Slide
  • The SLAC maintenance groups are ready and eager
    to safely and professionally support the LCLS
    project
Write a Comment
User Comments (0)
About PowerShow.com